Temporary Power for Building a House in Bengaluru: KERC Clause 12 Explained

Plot owners building a house in Bengaluru usually need temporary power first. KERC's Conditions of Supply, published by BESCOM, require a meter, advance consumption charges of 12 units per kW per day, a licensed contractor and permits, and cap renewals at two years. The temporary connection must be surrendered before BESCOM's fast track permanent connection. Here is how it works.

Buying Guides
Updated on
November 25, 2026
12 min read

The bhoomi puja is done, the borewell is drilled, and the contractor wants power on site by Monday. For a plot owner building a house in Bengaluru, the first electricity connection is often a temporary one. KERC's Conditions of Supply, published on BESCOM's website, set out how that temporary supply is sanctioned, billed and refunded, and they put a hard ceiling on how long it can run: two years.

Clause 12 of the KERC Conditions of Supply of Electricity deals with temporary supply. It says every temporary installation shall be serviced only with a meter, and it requires an advance deposit calculated at 12 units per kW per day for the period of supply.

The short answer. To get temporary construction power, you apply to the BESCOM section or sub-division office, pay service charges and an advance at 12 units per kW per day, and provide a contractor's wiring diagram and test report, an agreement and any permit or NOC. The advance is adjusted against bills and refunded within two months, with 1 percent per month interest for delay. Renewal cannot go beyond two years. The trade-off: a longer construction schedule means more advance money locked up and, past two years, a fresh sanction, so a realistic build timeline saves both cash and paperwork.

How do you apply for temporary power?

At the local BESCOM office, with a contractor. Clause 12.01 says the prospective consumer applies in the prescribed form to the section or sub-division office of the licensee, with no registration cum processing fee, paying service charges per installation and the advance consumption charges. The licensee prepares an estimate for the service line and communicates the temporary power sanction with the charges.

The work order is issued once the licensee receives the contractor's wiring diagram and completion-cum-test report, the agreement in the prescribed form, copies of any permit, licence or NOC, and the advance. The applicant executes the service line work through a licensed electrical contractor to the licensee's estimate and specifications, paying supervision charges of 10 percent of the estimate, subject to a minimum of Rs 100 per work, and the line work starts only after the sanction order. The consumer must provide a current limiter, an earth leakage circuit breaker and any capacitors required.

How is the advance calculated and refunded?

On a fixed formula. Clause 12.01(c) says the applicant deposits advance estimated power consumption charges for energy calculated at 12 units per kW per day for the duration of temporary supply, at the prevailing tariff. The advance is adjusted against periodical bills based on actual consumption. Any balance after disconnection is refunded on application within two months by cheque, or adjusted to an existing permanent RR number in the same consumer's name on request.

If the refund is not made within two months of a valid refund bill, the clause says the licensee pays interest at 1 percent per month for the actual number of days of delay. If the deposit falls short of actual charges, the licensee recovers the balance. For loads of 50 kW or more, fixed charges are also payable. The temporary tariff in force applies throughout. The table below summarises the key numbers as published.

Item under Clause 12Published rule
Advance consumption charges12 units per kW per day for the supply period, at prevailing tariff
Refund of unused advanceWithin two months of a valid refund bill, or adjusted to an existing permanent RR number
Delay in refundInterest at 1 percent per month for actual days of delay
Supervision charges for self-executed line work10 percent of estimate, minimum Rs 100 per work
Maximum period with renewalsTwo years from the date of service; beyond that, a fresh sanction

How big is the advance in practice?

It scales with load and time. Because Clause 12.01(c) fixes the advance at 12 units per kW per day, the number of units you pay for in advance is simple arithmetic. Take an illustrative sanctioned load of 5 kW for a construction period of 365 days: 12 units multiplied by 5 kW multiplied by 365 days gives 21,900 units, charged at the prevailing temporary tariff. Halve the period and the units halve. PropNewz is not quoting a rupee figure, because the tariff in force changes; ask the sub-division office to show the calculation in the sanction letter.

The units are only an advance. The clause says actual bills are adjusted against it based on real consumption, and the unused balance comes back after disconnection. For loads of 50 kW or more, fixed charges are added. A builder or owner who asks for more load or a longer period than needed simply locks up more money until the refund.

Can you use an existing permanent connection instead?

Only in limited cases. Clause 12.02 says use of power within a consumer's premises for temporary purposes for bona fide domestic use is permitted, provided the total load on the installation does not exceed the sanctioned load, and that portable equipment such as floor polishing machines used temporarily must have an earth leakage circuit breaker. That covers minor temporary use at an existing home, not a construction site on a new plot.

If you are rebuilding on the same site, Clause 9.05 is stricter: on demolition and reconstruction, the existing installation is surrendered and temporary supply from the existing RR number is not arranged for construction.

What if construction starts late or power is not used?

The start date can move, within limits. Clause 12.01(g) says the date of availing temporary supply may be amended by applying to the authority that issued the sanction before the commencement date in the order, but any alternate date must commence within 15 days of the date of the first order. Clause 12.01(h) says that if power is not availed, the advance is refunded within two months after deducting Rs 100, on a valid refund bill, with the same 1 percent per month interest for delay.

When the installation is serviced, the licensee's engineer gives a service certificate listing the RR number, date of service, sanctioned and connected load, meter details, seal condition, advance collected, contractor's licence number, period of sanction and how often bills will be issued. Keep it; you will need it for refunds and extensions.

How long can temporary supply continue?

Two years at most. Clause 12.01(k) says that for an extension, the consumer applies to the jurisdictional engineer at least one week before expiry, paying up-to-date charges and arrears. Clause 12.04 says officers empowered to sanction temporary supply can renew it up to a maximum of two years from the date of service, and that there shall be no extension of temporary power supply beyond two years; for anything longer, a fresh sanction is needed.

The clause also says that if a permit, licence or NOC is withdrawn by the competent authority after servicing, the installation shall be disconnected forthwith and reconnected only after the permit is restored, with no liability on the licensee and no refund or reduction of charges on that account. If a meter stops recording, billing for that period is at 12 units per kW per day of sanctioned or connected load, whichever is more.

How does temporary supply end?

With surrender, before the permanent connection. BESCOM's new connection eligibility page says its fast track permanent connection for a new building is provisioned only after any temporary connection availed is surrendered. Plan the switch with your contractor so that wiring, meter board and service main cable are complete, since the same page lists incomplete wiring among the grounds that make premises ineligible for the fast track. Once the permanent connection is in place, file the refund bill for the temporary advance promptly, or ask for the balance to be adjusted to the new permanent RR number in your name, which Clause 12.01(c) allows on request. Keep the temporary service certificate with the refund request.

If you are financing the build, our guide to plot and construction loans in Bengaluru covers the lender's side, and today's guide to BESCOM new connections covers the permanent one. Use this checklist.

  1. Estimate the construction period realistically, since the advance is calculated per day of supply.
  2. Keep any building permit or NOC copies ready for the temporary supply application.
  3. Engage a licensed electrical contractor to prepare the wiring diagram and test report.
  4. Pay the advance and keep the sanction order and service certificate safely.
  5. Apply for any extension at least one week before expiry, with dues cleared.
  6. Plan to finish before the two year ceiling, or budget for a fresh sanction.
  7. Surrender the temporary connection and file the refund bill when applying for permanent supply.

Frequently asked questions

How much advance does BESCOM collect for temporary power?

Clause 12.01 of the KERC Conditions of Supply says the applicant deposits advance estimated power consumption charges calculated at 12 units per kW per day for the duration of temporary supply, at prevailing tariff. The advance is adjusted against actual bills, and any balance after disconnection is refunded on application within two months.

How long can temporary power supply continue?

Clause 12.04 says officers empowered to sanction temporary supply can renew it for up to a maximum of two years from the date of service. It says there shall be no extension of temporary power supply beyond two years, and for anything longer the consumer has to take a fresh sanction.

What if BESCOM delays refunding the temporary power advance?

Clause 12.01 says that if the balance due to the consumer is not refunded within two months of receiving a valid refund bill, the licensee shall pay interest at 1 percent per month for the actual number of days of delay. The balance can also be adjusted to an existing permanent RR number in the same name on request.

Does the temporary connection affect the permanent connection?

Yes. BESCOM's fast track new connection page says the service is provisioned only after any temporary connection taken for the new building is surrendered. Plan the switch from temporary to permanent supply with your contractor, and keep the temporary account clear so the refund of any balance can be processed.

Last updated 2026-11-25. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.