How Long BESCOM Can Take to Connect Your New Home: KERC Time Limits Explained
Under the KERC (Duty of the Licensee to supply Electricity on request) Regulations, 2004, published with BESCOM's conditions of supply, a distribution licensee must give supply within one month where no extension is needed, within 45 days for LT supply needing extension, and within 15 days of readiness where the applicant self-executes. Here is what Bengaluru buyers can expect.
The flat is ready, the agreement with BESCOM is signed, and the family has given notice on the rented home. Then comes the question new owners ask the sub-division office: when will the meter go live? KERC's answer is written into regulation. Under the Duty to Supply regulations published with BESCOM's conditions of supply, a distribution licensee must give supply within one month where no line extension is needed, and within 45 days for an LT connection that does need one.
The KERC Conditions of Supply of Electricity published on BESCOM's website carry these rules as Annex 1, the KERC (Duty of the Licensee to supply Electricity on request) Regulations, 2004. They were made under Section 43 and Section 181 of the Electricity Act, 2003.
The short answer. BESCOM must give supply within one month of the application where no extension of distribution mains or new substation is needed; within 45 days for LT supply where mains must be extended; and within 15 days of your readiness intimation where you self-execute the extension with all statutory approvals. If it misses the deadline, the regulations make it liable to pay amounts under KERC's standards of performance rules. The trade-off: these clocks run from a complete application, so the time you save by applying early is lost if papers are missing or the wiring is not ready.
What do the regulations promise?
A time limit for every type of connection. Regulation 3 says an application for supply is filed by the owner or occupier of the premises in duplicate with the prescribed fee, and the licensee returns the duplicate acknowledged with seal and signature and informs the applicant of these regulations. The same provisions apply to load enhancement and change of voltage level.
Regulation 3.1 says that where supply does not require any extension of distribution mains or commissioning of new substations, every distribution licensee shall give supply within one month of receipt of the application. Regulation 3.2 sets longer periods where extension of distribution mains is needed, measured from receipt of the application. The table below lists them.
| Type of connection | Time limit from receipt of application |
|---|---|
| No extension of mains or new substation needed | Within one month |
| Low tension supply needing extension of mains | 45 days |
| 11 kV HT supply needing extension | 60 days |
| 33 kV HT supply needing extension | 90 days |
| Extension executed by applicant on self-execution basis | 15 days from readiness intimation, with all statutory approvals |
What if a new substation is needed?
The timeline depends on the Commission. Regulation 3.3 says that where extension of supply needs a new substation already included in the investment plan approved by the Commission, the licensee completes the work and starts supply within the period so approved. Where the substation is not in the approved plan, the licensee must, within 15 days of receiving the application, submit a proposal to the Commission for the substation with the time required, and then complete the work within the period the Commission approves.
For a buyer in a large new project, this is the scenario that can stretch timelines furthest. Ask the builder whether the project's power needs a new substation and whether it has been approved, because neither the one month nor the 45 day limit applies in that case. Separately, EHT supply above 33 kV carries a 180 day limit, which concerns large consumers rather than homes.
What has to happen between sanction and supply?
A sequence set out in Clause 4.03 of the main conditions. Once the point of entry of the supply mains and the position of meters are decided, the licensee communicates a power sanction stating the charges for any electric line or plant, the initial security deposit, the meter security deposit and other charges, and, under the amended text, that installation of a solar water heating system is mandatory where the government notification applies. Clause 4.02 adds that the local office shall assist with filling up the application and identify or nominate an official for that purpose.
Before the service line work begins, the applicant must furnish the consent of any other property owner whose land the service line will cross, execute the agreement, pay the amounts in the sanction, submit the contractor's completion-cum-test report with wiring diagram in duplicate and an undertaking on the solar water heater where required, and execute an indemnity bond if needed. Clause 4.03(iii) says the work order is issued only after all these conditions are met, and supply is then arranged within the period in the Duty to Supply regulations. Clause 4.03(iv) says that if these requirements are not met within the stipulated time and the applicant is not ready, the application is treated as cancelled, the licensee's liability to pay for delay ceases and the registration fee is forfeited, though a renewal of the sanction may be granted not more than once if requested before expiry, on payment of re-registration charges.
The consent rule matters for plots where the service line must cross a neighbour's land. Clause 4.03 says the licensee reserves the right to discontinue supply if that consent is withdrawn after servicing, and the consumer remains liable for dues as if the installation were in service until the initial agreement period ends. If your plot depends on such access, get the consent in writing and keep it with your title papers.
What happens if BESCOM misses the deadline?
It becomes liable to pay. Regulation 4.1 says a distribution licensee that fails to comply with the time frame in Regulation 3 shall be liable to pay the applicant the amount specified in the KERC (Licensee's Standards of Performance) Regulations, 2004. The Conditions of Supply do not reproduce those amounts, so ask BESCOM or check KERC's standards of performance regulations for the current figures.
Regulation 5 says the time frame is not operative where the licensee is prevented from giving supply by force majeure conditions, listing war, mutiny, civil commotion, riot, flood, cyclone, lightning, earthquake or other causes beyond its control, and strikes, lock-outs or fire affecting its installations and activities. Keep the acknowledged duplicate of your application: it is the starting point for any claim about delay. If the period passes, write to the sub-division office and keep a copy of that letter too.
Can the buyer also lose out on time limits?
Yes, in two ways. Regulation 4.1 says that where a power sanction letter is issued and the applicant fails to avail supply within the specified time, the licensee's responsibility to pay ceases and the application is treated as cancelled. Regulation 4.2 says that where the sanction letter is issued and the agreement executed, but the applicant fails to avail supply in time, the installation is deemed to have been serviced at the end of the period, and the consumer is liable to pay demand or fixed charges under the tariff for the initial agreement period.
Clause 4.08 of the main conditions repeats this: after the sanction letter, agreement and approval of the applicant's installation, the engineer commences supply under intimation, and if the applicant fails to avail it within the time specified, the installation is deemed serviced and charges apply. In plain terms, do not sign the agreement until the wiring, meter board and completion report are ready, or you may pay fixed charges for a connection you are not yet using.
How does the fast track fit with these limits?
It is a faster route for simpler cases, within the same framework. BESCOM's new connection eligibility page describes Janasnehi Vidyuth Sevegalu as its fast track for LT1 domestic and LT3 commercial loads below 18 kW, and excludes premises needing line extension, premises requiring an occupancy certificate and unauthorised layouts, among others. PropNewz covered the fast track and its documents in today's guide to BESCOM new connections for a Bengaluru home.
If your home falls outside the fast track, the regulatory time limits above remain the benchmark. Note them on your calendar from the day the application is acknowledged.
How should a new owner plan the connection?
Around possession, not after it. Our handover week checklist for Bengaluru buyers covers the wider possession process. For electricity, use this checklist.
- Confirm whether your premises needs an extension of distribution mains or only a service connection.
- File a complete application and keep the duplicate acknowledged with seal and signature.
- Note the deadline: one month, or 45 days for LT supply needing extension.
- If you self-execute the extension, send the readiness intimation with all statutory approvals and note the 15 day limit.
- Sign the power supply agreement only when the wiring and completion report are ready.
- If the deadline passes, ask BESCOM in writing about the amount payable under KERC's standards of performance.
- For a large project, ask the builder whether a new substation is needed and approved.
Frequently asked questions
How long does BESCOM have to give a new connection?
The KERC Duty to Supply Regulations, 2004 say that where supply does not require extension of distribution mains or new substations, the licensee shall give supply within one month of receiving the application. Where LT supply requires extension of distribution mains, the period is 45 days from receipt of the application.
What if the applicant lays the line extension on self-execution basis?
Regulation 3.4 says that where the extension of the distribution main is executed by the applicant on self-execution basis, the licensee shall provide supply within 15 days from receiving the consumer's intimation of readiness to avail power supply, on production of all statutory approvals.
What happens if BESCOM misses the deadline?
Regulation 4.1 says a distribution licensee that fails to meet the time frame is liable to pay the applicant the amount specified in the KERC Licensee's Standards of Performance Regulations, 2004. The regulations also suspend the time frame during force majeure events such as floods, riots or fire affecting the licensee's installations.
What if the buyer does not take supply after the sanction?
Regulation 4.2 says that if a power sanction letter is issued and the agreement executed, but the applicant fails to avail supply within the time limit, the installation is deemed serviced at the end of that period, and the consumer must pay demand or fixed charges under the tariff for the initial agreement period.
Last updated 2026-11-25. PropNewz Team.