Power Supply in a Bengaluru Plotted Layout: What the Developer Owes Plot Buyers
KERC's Conditions of Supply and its Recovery of Expenditure regulations, published on BESCOM's website, say the developer of an approved layout executes the electric lines and transformers at its own cost and maintains them until at least 25 percent of applicants take power. If the developer defaults, plot owners pay per kW charges. Here is what plot buyers should check.
Picture a gated plotted layout off a Bengaluru highway: tarred roads, a compound wall, a sales office, and rows of empty sites. What is under the road matters as much as the road. The rules published on BESCOM's website say that in an approved layout, the developer, not the plot buyer, pays to build the electrical network, and must keep maintaining it until a quarter of the houses are connected.
Those rules sit in Clause 10 of the KERC Conditions of Supply of Electricity published by BESCOM, and in the KERC Recovery of Expenditure for Supply of Electricity Regulations, 2004 annexed to it. They set out what a developer owes, and what plot owners end up paying if the developer walks away.
The short answer. For an approved layout, the developer executes the 11 kV lines, transformers and LT lines at its own cost through a licensed contractor, pays supervision charges of 10 percent of the estimate up to Rs 15 lakh, maintains the network until at least 25 percent of applicants take power, and gives a one year guarantee after BESCOM takes over. If the developer defaults, BESCOM recovers per kW charges from plot owners. The trade-off: a cheaper plot from a developer who has not laid the network may cost you later in electrification charges and delay.
What must the developer do under Clause 10?
Apply with an approved layout plan. Clause 10.01 says the application for power to a layout is registered at the jurisdictional sub-division office with a layout plan approved by the competent authority, showing the nature of service required, anticipated load and number of street lights required, with the prescribed registration fee. It adds that the licensee's sanctioning authority shall verify the bona fides of the developer and obtain and verify the developer's permanent residential address.
Clause 10.02 says that for commercial or industrial applicants within such layouts, the cost of line and plant is recovered under the Recovery of Expenditure regulations, and that those regulations also apply to buildings in the layout with loads of 25 kW or more or built-up area above 500 sq m. Clause 10.03 says the licensee retains the right to tap a service line laid for one consumer to supply others in the vicinity.
Who builds and pays for the network?
The developer, at its cost. Regulation 3.2.1 of the Recovery of Expenditure regulations says that in layouts approved by a competent authority, the developer shall execute at its cost the electric line and plant, including extension of 11 kV line or aerial bunched cable, transformers and LT lines, excluding augmentation works at the station or strengthening of the distribution main. The work must be done by an appropriate class of licensed electrical contractor, to the licensee's estimate, standard specifications and drawings.
The developer pays supervision charges to the licensee at 10 percent of the estimated cost, excluding employees' cost, subject to a maximum of Rs 15 lakh. The regulations also say developers must use aerial bunched cables for 11 kV and LT lines in new layouts in the Bruhat Bangalore Mahanagara Palike area.
Very large developments carry a heavier obligation. Regulation 3.2.4 says that where layouts, buildings or clusters of buildings on a common site need a total requisitioned load of more than 7,500 kVA, the developer or applicant must provide space for a sub-station and bear the entire charges of the sub-station and associated lines and equipment. The work is done either by the licensee, recovering the estimated charges, or by the applicant through a licensed contractor on payment of 10 percent of the estimate as supervision charges. A buyer in a project of that size can ask whether the sub-station is built, planned or still to be funded, since power for every phase may depend on it.
When does BESCOM take over?
After a quarter of the houses connect. The regulation says the developer executes an agreement on stamp paper consenting to maintain the lines and transformer centres in the layout until 25 percent of the applicants avail power supply to their houses. After satisfactory completion and once at least 25 percent of applicants have power, the entire distribution system and transformers are taken over by the licensee without payment, for maintenance.
The developer also gives a one year guarantee on materials and quality of work from the date of takeover. For plot buyers, this matters in the early years. Until 25 percent of plots have houses connected, the developer is responsible for maintaining the network, so it is worth knowing whether the developer is still around and solvent. Ask the developer for a copy of the maintenance agreement signed with BESCOM and the date of any takeover, and keep both with your sale documents.
What if the developer did not lay the lines?
Plot owners pay. Regulation 3.2.3 says that where the developer has defaulted and not laid the electric line or plant in the layout, the licensee recovers expenditure towards it from applicants. The table below shows the published rates, which differ by location and site size; check current charges with BESCOM before relying on them.
| Where the site is | Published charge where developer defaulted |
|---|---|
| Bengaluru corporation, BDA and agglomeration areas, site up to 1,200 sq ft | Rs 4,000 per kW of requisitioned load, minimum Rs 4,000 per site |
| Bengaluru corporation, BDA and agglomeration areas, site above 1,200 sq ft | Rs 4,000 per kW of requisitioned load, minimum Rs 12,000 per site |
| Other urban areas within town limits | Rs 4,000 per kW per site, minimum Rs 4,000 per site |
| Beyond town limits in other layouts | Rs 3,000 per kW per site, minimum Rs 3,000 per site |
| Revenue sites, stray sites outside village or town panchayat limits, not in abandoned layouts | Rs 3,000 per kW, minimum Rs 3,000 per site |
The regulation adds that for loads above 3 kW, charges for the additional load are recovered at slab rates, or the applicant may execute the line work on a self-execution basis, and that in the Bangalore Metropolitan Area an additional Rs 1,000 per kW is collected for loads above 3 kW towards underground or aerial bunched cable systems. These are figures as published in the conditions on BESCOM's website, so treat them as a guide and confirm the demand letter.
How does this fit with fast track connections and unauthorised layouts?
Unauthorised layouts are excluded from the fast track. BESCOM's new connection eligibility page says applications for connections in unauthorised, revenue and abandoned layouts are not eligible under its Janasnehi Vidyuth Sevegalu fast track, along with premises attracting line extension or network modification. A plot in a layout where the developer has not built the network may well need that kind of extension.
Developers can also seek a BESCOM NOC for the purpose of layout plan approval by local authorities. Clause 30.11 of the conditions lists charges for such an NOC for layouts of Rs 100 per site or Rs 10,000 per layout, whichever is higher, where sites exceed 300, and Rs 50 per site or Rs 5,000 per layout, whichever is higher, for 300 sites or fewer. A buyer can reasonably ask whether such an NOC was obtained. PropNewz explained the wider development works a layout owes buyers in its guide to plots in RERA layouts and development works.
What about government scheme sites for weaker sections?
A separate, lower charge applies. Regulation 3.2.2 says that for sites or houses granted to economically or socially weaker sections under any scheme sanctioned by the Government of Karnataka or the Government of India, the licensee recovers Rs 2,000 per site from the applicant, the government or the person in charge of the scheme and arranges power supply, or the cost of electrification may be budgeted in the scheme itself and paid to the licensee.
For most private plotted layouts this does not apply, but it explains why electrification costs can differ sharply between neighbouring sites of different origins. Our guide to BESCOM new connections for a Bengaluru home covers the next step, once the house is built. Use this checklist before buying a plot.
- Confirm the layout plan is approved by the competent authority and get a copy.
- Ask whether the developer obtained a BESCOM NOC for layout plan approval.
- Check on site whether 11 kV lines, transformers and LT lines have been laid in the layout.
- Ask whether BESCOM has taken over the network, or whether the developer is still maintaining it.
- Ask how many plots already have houses connected, since takeover follows 25 percent connections.
- If the network is missing, budget for per kW electrification charges and delay.
- Avoid assuming a fast track connection for a plot in an unauthorised, revenue or abandoned layout.
Frequently asked questions
Who pays for the electricity network in a Bengaluru plotted layout?
Under the KERC Recovery of Expenditure regulations published with BESCOM's conditions of supply, in layouts approved by the competent authority the developer executes the electric lines and plant at its own cost, including 11 kV lines, transformers and LT lines, through a licensed contractor and to the licensee's estimate and specifications, paying supervision charges.
When does BESCOM take over a layout's electrical network?
The regulations say the developer signs an agreement to maintain the lines and transformer centres until 25 percent of applicants take power supply to their houses. After satisfactory completion and at least 25 percent connections, the distribution system and transformers are taken over by the licensee without charge, with a one year developer guarantee.
What happens if the developer never laid the power lines?
The regulations say that where the developer defaults and has not laid the electric line or plant, the licensee recovers expenditure from applicants. For sites in Bengaluru's corporation, BDA and agglomeration areas, the published rate is Rs 4,000 per kW, with minimums of Rs 4,000 per site up to 1,200 sq ft and Rs 12,000 above.
What documents are needed to arrange power to a layout?
Clause 10.01 of the KERC Conditions of Supply says the application is registered with a layout plan approved by the competent authority, showing the nature of service, anticipated load and number of streetlights, and that the licensee's sanctioning authority verifies the developer's bona fides and permanent residential address.
Last updated 2026-11-25. PropNewz Team.