BESCOM's Janasnehi Vidyuth Sevegalu fast track covers domestic and commercial new connections below 18 kW, but excludes buildings needing an occupancy certificate, tall or large buildings and unauthorised layouts. KERC's Conditions of Supply list the documents and say arrears on a terminated connection are collected from a fresh applicant. Here is what Bengaluru buyers should check.

Buying Guides
Updated on
November 25, 2026
12 min read

The keys are handed over, the gruhapravesha date is fixed, and the house has no meter. For buyers of independent houses and small buildings in Bengaluru, the last step between a finished structure and a liveable home is a BESCOM connection. BESCOM runs a fast track for it, called Janasnehi Vidyuth Sevegalu. But its own eligibility page for new connections lists premises that cannot use that route, and one of them is any premises requiring an occupancy certificate.

That single line connects electricity to the approvals a buyer should already be checking. A building that needs an occupancy certificate cannot take the fast track, and the regulations BESCOM publishes also say how earlier arrears on a property can follow it to the next applicant.

The short answer. BESCOM's fast track covers LT1 domestic and LT3 commercial connections for loads below 18 kW, applied for online or at sub-division offices. It excludes premises requiring an occupancy certificate, buildings over 15 metres high with plinth area over 500 sq m, unauthorised, revenue and abandoned layouts, and premises needing line extension. KERC's Conditions of Supply list the documents for any application and say arrears on a terminated connection are collected from a fresh applicant. The trade-off: a house in an approved layout with clear papers gets the quicker route, while a cheaper property in an unauthorised layout may face a slower, uncertain path to power.

What is BESCOM's fast track for new connections?

A simplified route for smaller loads. BESCOM's eligibility page says Janasnehi Vidyuth Sevegalu applications can be registered online or offline at BESCOM sub-division offices, and that the service applies only to LT1 domestic and LT3 commercial tariff for loads up to 18 kW, excluding 18 kW. It covers new connections, both single and multiple, tapping connections for existing buildings, load enhancement and load reduction, and also name change and tariff change.

For online applications, the page says photocopies of documents prescribed under Clause 4.02(ii) of KERC's regulations must be submitted with originals for verification during a spot inspection by the field officer. The application is completed only after ID and address proof are verified by visiting the concerned sub-divisional officer.

Which properties cannot use the fast track?

BESCOM lists seven categories. The page says the following applications are not eligible under Janasnehi Vidyuth Sevegalu: premises attracting line extension or modification of the electrical network; buildings with height exceeding 15 metres and total plinth area exceeding 500 sq m; premises requiring an occupancy certificate; buildings attracting Clause 9 of the conditions of power supply; connections in unauthorised, revenue and abandoned layouts; HT category; and premises where wiring, meter board or service main cable is incomplete.

For a buyer, the layout and occupancy certificate exclusions matter most. They do not on their own say a connection is impossible through the regular process, but they mean the quick route is closed. Our explainer on occupancy certificate vs commencement certificate in Bengaluru sets out what these approvals mean and why they matter before possession.

What must be completed before the connection is given?

Paperwork, payments and the installation itself. BESCOM's page says the fast track service is provided only after any temporary connection taken for a new building is surrendered; for an existing building, any arrears and additional demand charges found during spot inspection are paid; all applicable deposits and charges are paid under Clause 4.03 of the KERC conditions; a power supply agreement is executed under Clause 32; and the contractor's completion-cum-test report with wiring diagram is submitted.

The page also says an undertaking must be furnished, before registration, for having installed a solar water heating system in new residential buildings with built-up area of 600 sq ft and above constructed on sites of 1,200 sq ft. The KERC Conditions of Supply list the same category: residential buildings of 600 sq ft and above built-up on sites of 1,200 sq ft and above within municipalities, corporations and Bangalore Development Authority sectors.

Which documents does an application need?

Proof that you are entitled to the premises, among others. Clause 4.02 of the KERC Conditions of Supply of Electricity published on BESCOM's website says an application is filed by the owner or occupier at the licensee's local office, with attested or photocopies of applicable documents. The document says the conditions were notified in the Karnataka Gazette dated 17 June 2006, with amendments notified in 2008 and 2010, and BESCOM links it from its site as its rules and regulations. The table below lists the items most relevant to a home buyer.

Document under Clause 4.02(ii)When it applies
Proof of ownership of the premises or proof of occupancyEvery application
General licence from the local authorityIf such a licence is provided for
Indemnity bondIf the applicant is not the owner of the premises
Proof of permanent residential address and PAN, if anyEvery application, with changes to be intimated later
Name and address of the licensed electrical contractorIndicated in the application form

The application must also contain the full address, a location sketch and the name of a nominee. Clause 4.09 adds that for domestic installations, the owner's consent is not necessary where the owner is not the occupant; proof of occupancy such as a valid power of attorney, latest rent receipt or valid lease deed is enough, with an indemnity bond if the applicant is not the owner. It also says unauthorised occupants of premises shall not be given a power supply connection for any purpose.

Can old arrears become the buyer's problem?

They can. Clause 4.09 says that if a person wants electricity for premises where the power supply agreement has been terminated, whether or not the service line is dismantled, that person is treated as a fresh applicant, and the licensee shall collect the outstanding arrears for those premises from that person before giving a connection.

BESCOM's fast track page similarly says that for an existing building, arrears and additional demand charges found during spot inspection must be paid. That is why the last bill and a no-dues confirmation belong in every resale file. PropNewz reported on a consumer commission dispute about electricity dues carried to a new house, which shows how such bills surface after a sale.

What if your flat is supplied through the builder's connection?

The regulations allow it, with conditions. The Conditions of Supply say that where a commercial, office or residential complex takes power originally in the name of the builder or promoter, who later transfers ownership of the flats, the supply may continue on set terms. The builder in whose name the supply continues may extend power to individual flat owners or lessees through sub-meters and collect the amount from them on a no profit, no loss basis, which is described as sharing the electricity bill and not treated as unauthorised extension or resale of energy.

If the builder does not wish to keep any stake after completing the complex, the regulations say the original service connection may be transferred to an association or society formed and registered in the complex, which may then extend supply to owners through sub-meters on the same no profit, no loss basis. For a flat buyer, this means asking at the time of booking whether each flat will get its own BESCOM connection or a sub-meter on a common supply, and who will hold that connection after handover. The answer affects how your bill is calculated and who you deal with when something goes wrong.

What happens to deposits if the application fails?

Some come back, some do not. BESCOM's page says that if an application is rejected for not meeting the eligibility criteria, or because of a requested change in load, tariff or name, registration and GST amounts are not refunded, deposits such as MSD and AISD and non-revenue charges such as SLC and ASLC are refunded, and other charges are forfeited. If an applicant decides not to take supply and has not executed the agreement, it says refunds are made after deducting 10 percent of the total amount. Use this checklist before you buy or apply.

  1. Confirm whether the building needs an occupancy certificate and whether it has one.
  2. Check that the layout is approved and not listed as unauthorised, revenue or abandoned.
  3. Ask the seller for the latest BESCOM bill and confirm there are no arrears on the premises.
  4. Keep proof of ownership or occupancy and address proof with PAN ready for the application.
  5. Install the solar water heater if your house falls in the 600 sq ft on 1,200 sq ft category, and keep the undertaking ready.
  6. Have the licensed electrical contractor's completion-cum-test report and wiring diagram ready.
  7. Check the demand letter from the sub-divisional officer for the actual charges before paying.

Frequently asked questions

Which new connections can use BESCOM's fast track service?

BESCOM's eligibility page says Janasnehi Vidyuth Sevegalu applies only to LT1 domestic and LT3 commercial tariff for loads up to 18 kW, excluding 18 kW, for new connections, tapping connections, load enhancement and load reduction, along with name and tariff changes. Applications can be registered online or at BESCOM sub-division offices.

Which premises are not eligible for the fast track?

BESCOM lists premises needing line extension or network modification, buildings over 15 metres high with plinth area over 500 sq m, premises requiring an occupancy certificate, buildings attracting Clause 9 of the conditions of supply, unauthorised, revenue and abandoned layouts, HT category, and premises with incomplete wiring.

What documents does an applicant for a new connection need?

Clause 4.02 of KERC's Conditions of Supply, published on BESCOM's website, lists proof of ownership or occupancy, a general licence from the local authority where provided for, an indemnity bond if the applicant is not the owner, and proof of permanent residential address with PAN if any, among other items.

Can old electricity arrears be collected from a new buyer?

Clause 4.09 of the Conditions of Supply says a person seeking electricity for premises where the power supply agreement has been terminated is treated as a fresh applicant, and the licensee shall collect outstanding arrears for those premises from that person before giving a connection. Check dues before you buy.

Last updated 2026-11-25. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.