BESCOM Inspection of a New Bengaluru Home: What the Wiring Must Pass Before Power

KERC's Conditions of Supply, published by BESCOM, say no power connection is made until the applicant's installation is inspected and tested and found satisfactory. The work must be done by a licensed electrical contractor, and the rules set standards for insulation, earthing, sockets, switches and load limiters. Here is what Bengaluru buyers of new homes should check.

Buying Guides
Updated on
November 25, 2026
12 min read

The painting is done, the modular kitchen is fitted, and the owner of a new Bengaluru home is waiting for one thing: the BESCOM engineer's visit. Under the rules BESCOM publishes, that visit is not a formality. KERC's Conditions of Supply say no power connection shall be made until the applicant's installation has been inspected and tested by the licensee and found satisfactory.

The KERC Conditions of Supply of Electricity on BESCOM's website set out who may do the wiring, how it is tested, and what standards it must meet. For buyers of new independent houses, and for flat buyers checking a builder's work at handover, those rules double as a checklist.

The short answer. Wiring must follow Central Electricity Authority rules and be done by a licensed electrical contractor, who submits a completion-cum-test report with a wiring diagram. BESCOM's engineer then inspects and tests, and power is connected only if the installation is satisfactory. The first test is free; repeat tests caused by faults or absence are charged. The trade-off: insisting on a properly licensed contractor and a clean first test can cost more up front, but a failed test delays your move and adds fees.

Who is allowed to wire a new home?

A licensed electrical contractor. Clause 4.06 says that for the safety of the applicant and the public, wiring on the premises shall conform to rules framed by the Central Electricity Authority under Section 53 of the Electricity Act, 2003, and that the work shall be carried out by a qualified licensed electrical contractor, who provides a completion and test report.

It adds that no electrical installation work, including additions, alterations, repairs and adjustments, other than replacement of lamps, fans, fuses, low voltage domestic appliances and fittings that do not alter the capacity and character of the installation, shall be carried out except by a qualified contractor licensed by the government and under the direct supervision of a holder of a certificate of competency. The clause says breaches are punishable with fine under the CEA rules. For a buyer, that means asking the builder or seller for the contractor's licence number and the completion report.

If you are buying a resale home where the previous owner added circuits or rewired rooms, ask who did the work and whether a completion report exists. Clause 15.01 expects changes within the sanctioned load to be intimated to BESCOM's engineer with the contractor's report, so missing paperwork is worth a question before you sign. Keep whatever records you receive with your title documents.

How does BESCOM's inspection work?

On a notified date, with the contractor present. Clause 4.06 says that once the contractor's completion-cum-test report and actual wiring diagram are received, and the applicant has intimated completion of the service main work, the licensee notifies the day and time of inspection. The applicant must ensure the contractor's supervisor is present to give the engineer information about the installation.

If the supervisor is absent on the notified date, the licensee notifies another date; on that second date, the installation is tested and serviced even if the supervisor is absent, provided the results are satisfactory, but the consumer pays the fee for the second or later inspection. Clause 4.07 says the engineer notifies the applicant in writing, under acknowledgement, of any defects noticed at the spot, and supply commences only when those defects are rectified and the wiring matches the completion and test report.

What does the insulation test require?

A finished installation and a minimum reading. Clause 4.06 says that before the insulation test, the wiring must be complete in all respects including the service main; all fittings, lamps, fans, motors, heating, cooking and other apparatus must be connected; all fuses must be in place; and all switches must be on. Temporary wires, fittings or dead ends are not to be included, and no part of the work is to be left incomplete.

For low voltage installations, the clause says that at 500 volts applied between each live conductor and earth for one minute, insulation resistance shall be at least 1 megohm, or as specified by the Indian Standards Institution from time to time, and resistance between phases shall be at least half that from phase to earth. A house where electricians are still working on some rooms is not ready for this step, so schedule the inspection only when everything is genuinely complete.

What wiring standards apply inside the home?

Clause 13.01 lists them. The table below summarises the general wiring conditions most relevant to a home. These are the published conditions; your contractor should also follow current CEA rules.

Item under Clause 13.01Published requirement
Main switch and fusesLinked quick break main switch and fuse or load limiter on each conductor except neutral, near the meter board
Single pole switchesIn the phase wire, not the neutral, for lamps, fans, apparatus and plugs
EarthingGas or water pipes shall not be used; minimum earth wire No. 14 SWG or 3.0 sq mm
Appliance circuitsThree-pin plugs with earth pin; two-pin plugs or lighting sockets not allowed; all appliances effectively earthed
Meter enclosureStrong teakwood or metal waterproof box, ventilated, lockable, with a caution board in Kannada and Hindi or English

The clause also says LT consumers provide current limiters within one metre of the licensee's meter board or another approved position, with no fuses on the neutral, and that all domestic consumers provide sealed load limiters of required capacity. Clause 9.07 separately requires MCCBs and ELCBs for individual installations in multi-storied buildings, with the ELCB at the entrance of each premises.

What does a failed test cost?

Time, and a fee. Clause 4.06 says no charge is made for the first test. Subsequent inspections or tests needed because of faults disclosed at the first test, the contractor's supervisor not attending at the appointed time, facilities for inspection not being arranged, or the installation not being complete are charged under Clause 30.12. Clause 30.12 confirms that the first inspection or test for a new installation, extension or alteration carries no charge.

The larger cost is delay. The time limits for supply in the Duty to Supply regulations, covered in today's explainer on BESCOM connection time limits, assume a ready installation. A failed inspection resets your practical timeline. Ask your contractor to share the readings from their own completion test before the BESCOM visit, so that any problem is fixed before the engineer arrives.

What are the owner's duties after the meter is installed?

Protecting BESCOM's equipment, and getting changes approved. Clause 14.01 says the meter, meter boards, service mains, main cutouts and load limiters must on no account be handled or removed by anyone who is not an authorised employee of the licensee, that seals on meters, load limiters and the licensee's apparatus must on no account be broken, and that the consumer is responsible for the safe custody of the licensee's equipment and seals within the premises. Clause 14.04 says that if the licensee's equipment is damaged through the consumer's act, neglect or default, the consumer pays the cost claimed at the schedule or market rates.

Later changes follow the same discipline. Clause 15.03 says that where a consumer wants to increase connected load beyond the sanctioned load, the additional load must be sanctioned and the contractor's completion-cum-test report furnished, after which the licensee's representatives inspect the alterations. Clause 15.01 says that changes within the sanctioned load must be intimated to the engineer with the contractor's report and any local authority licence required. For an owner planning interiors work after possession, this means the electrician who rewires a kitchen or adds a circuit should be licensed, and the paperwork should be kept, because the meter seals and load limiter must stay intact through the work.

How should a buyer use these rules at handover?

As a checklist for the builder or seller. Even in an apartment where the developer arranges the connection, the same standards apply to your flat's wiring. Our guide to BESCOM new connections for a Bengaluru home covers the application side. Use this checklist.

  1. Ask for the licensed electrical contractor's name, licence number and completion-cum-test report.
  2. Ask for the actual wiring diagram submitted with the report.
  3. Check that appliance points use three-pin sockets and that no two-pin sockets are used on those circuits.
  4. Confirm the earthing does not use gas or water pipes.
  5. Check that switches for lights, fans and plugs are on the phase wire, and ask the contractor to confirm it.
  6. Look for a lockable meter enclosure with a caution board, and an ELCB at the entrance in a multi-storied building.
  7. Ensure the contractor's supervisor attends the BESCOM inspection to avoid a charged retest.

Frequently asked questions

Will BESCOM connect a new home before inspecting the wiring?

No. Clause 4.06 of the KERC Conditions of Supply says no power connection shall be made until the applicant's installation has been inspected and tested by the licensee and found satisfactory. Clause 4.07 says power supply commences only after any defects notified in writing are rectified and wiring matches the completion and test report.

Who is allowed to do the electrical wiring in a new home?

The conditions say wiring must conform to rules framed by the Central Electricity Authority under Section 53 of the Electricity Act, 2003, and be carried out by a qualified licensed electrical contractor under the supervision of a certificate of competency holder, except simple replacements such as lamps, fans, fuses and low voltage appliances.

Does BESCOM charge for testing a new installation?

Clause 4.06 says no charge is made for the first test. Subsequent inspections or tests needed because of faults found at the first test, the contractor's supervisor not attending, facilities not being arranged or the installation being incomplete are charged under Clause 30.12. Ask your contractor to be present on the notified date.

What earthing and socket rules apply to domestic wiring?

Clause 13.01 says gas or water pipes shall not be used for earthing, appliance circuits must use three-pin plugs with an earth pin, two-pin plugs are not allowed on those circuits, all appliances must be effectively earthed, and the minimum earth wire size is No. 14 SWG or 3.0 sq mm.

Last updated 2026-11-25. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.