How Power Reaches a Bengaluru Apartment Project: KERC Clause 9 Explained for Buyers

Under KERC's Conditions of Supply published by BESCOM, buildings with requisitioned load of 25 kW or more, or built-up area above 500 sq m, follow Clause 9: sanctioned plan, BESCOM NOC, transformer space free of cost, and supply through a common bus bar to individual meters. Here is what Bengaluru flat buyers should ask their builder.

Buying Guides
Updated on
November 25, 2026
12 min read

Picture twenty floors, two hundred flats, one transformer yard behind the clubhouse. When a Bengaluru buyer walks through a show apartment, the electrical room is not on the tour. Yet how power reaches the building is decided long before possession, under rules that require the builder to obtain a BESCOM NOC for plan sanction, give transformer space free of cost, and arrange metering for each flat.

Those rules sit in Clause 9 of the KERC Conditions of Supply of Electricity, published on BESCOM's website. Clause 9.00 applies to commercial and residential buildings, complexes and multi-storied buildings where the requisitioned load is 25 kW or more, or the built-up area is more than 500 square metres. Multi-storey apartment buildings will often cross one of these lines, so it is worth asking.

The short answer. For buildings above 500 sq m or 25 kW, the owner or promoter applies with the sanctioned plan, ownership proof, a BESCOM NOC used for plan sanction and a route sketch, provides transformer space free of cost as shown in the BESCOM-approved layout, and lays supply to a common bus bar from which each flat is metered. The trade-off: these steps protect buyers from improvised connections, but they also mean your flat's power depends on the builder completing works that BESCOM must inspect and take over, which is one more item that can delay handover.

Which projects follow Clause 9?

Larger buildings. Clause 9.00 applies where the requisitioned load is 25 kW or more, or the built-up area of the building is more than 500 sq m. The general procedure under Clause 4.00 and the KERC Recovery of Expenditure for Supply of Electricity Regulations, 2004, as amended, apply wherever relevant. Separately, BESCOM's fast track new connection page says buildings over 15 metres high with plinth area over 500 sq m are not eligible for its fast track service.

For a buyer, that means the electrical arrangement for an apartment project is a project-level process run by the developer, not something each flat owner applies for from scratch. PropNewz explained the single-home side in today's guide to BESCOM new connections for a Bengaluru home.

What does the builder have to file?

Four documents, plus an as-built plan if construction deviated. Clause 9.01 says the owner, promoter or occupier registers the application at the jurisdictional sub-division office with a copy of the sanctioned plan showing built-up area, proof of ownership, GPA or occupancy, the NOC issued by the licensee to obtain plan sanction wherever applicable, and a route sketch.

The notes add two points that interest buyers. For new buildings, if construction deviates from the sanctioned plan, an architect's or civil engineer's plan as per actual, showing built-up area and certified by a registered architect or engineer, must be furnished along with the sanctioned plan. And if the applicant fails to produce a plan showing the built-up area of the entire building, the application shall be rejected. In other words, the power application puts the building's actual size on record.

Who gives up space for the transformer?

The builder, free of cost. Clause 9.01 says the applicant shall not deviate from the condition of providing space at the premises free of cost for erection of the transformer, as indicated in the layout plan approved by the licensee at the time of issuing the NOC. Clause 9.02 says space for the transformer is provided as specified in the KERC Recovery of Expenditure regulations.

Clause 9.07 adds that the transformer's capacity is based on the requisitioned load and must be a standard rating. Its example: a 75 kW requisitioned load, divided by a 0.85 power factor, gives about 88 kVA, so a 100 kVA transformer, the next standard rating, is fixed. Where the owner executes the works, the clause says supervision charges are paid at 10 percent of the estimated cost subject to a maximum of Rs 15 lakh, the work is done by licensed contractors to BESCOM's specifications, and after a joint inventory the lines and transformers are taken over by the licensee without payment, with a one year guarantee from the consumer on materials and workmanship.

How does each flat get its own meter?

Through a common bus bar. Clause 9.07 says supply to the building shall be through a common service main cable terminating in a common bus bar, and supply to individual consumers shall be tapped from the bus bar through individual meters. It says suitable, easily accessible space near the main entrance must be provided at ground floor level, 0.6 to 1.6 metres above ground, for the licensee's metering equipment. MCCBs and ELCBs are to be installed for individual installations, with the ELCB at the entrance of each premises.

The clause also provides for two runs of cables for alternate supply with a change-over switch and master metering, and says multi-storied buildings get an "M.S." prefix on their RR number. The table below summarises what Clause 9 requires and what a buyer can ask to see.

Clause 9 requirementWhat a buyer can ask the builder
BESCOM NOC used for plan sanctionWas a BESCOM NOC obtained, and does the approved layout show the transformer location?
Transformer space free of costIs the transformer space on the approved layout, and is it outside the area sold to buyers?
Sanctioned plan or certified as-built planDid the power application use the sanctioned plan, or an as-built plan because of deviation?
Common bus bar with individual metersWill each flat have its own BESCOM meter, and where is the metering room?
Works taken over by BESCOM after inspectionHave the lines and transformer been inspected and taken over, and when?

How are common areas and mixed-use buildings billed?

By building classification, under Clause 9.09. For purely residential apartments and complexes, the clause says LT supply shall be arranged at the applicant's request with LT metering to individual installations, subject to the KERC Recovery of Expenditure regulations. Power to common areas such as lifts, water supply and staircase lighting, if metered separately, is billed under residential or commercial tariff according to the building's classification under those regulations.

For buildings with combined residential and commercial requisitioned load below 100 kW, the clause says supply is arranged on LT basis with individual meters for each installation, whether commercial or domestic, billed at the appropriate tariff. In residential buildings on HT supply with some commercial area, a bulk LT sub-meter records the commercial portion, which is billed at LT commercial tariff and deducted from the main HT meter, with the balance billed at the HT tariff for residential apartments. If your project mixes shops and flats, ask how the common-area and commercial loads will be metered, because that affects how electricity for lifts and pumps is charged. Clause 9.08 adds that buildings with partial industrial loads are assessed on the entire building's requisitioned load.

What changes if the building is demolished and rebuilt?

The old connection goes. Clause 9.05 says that on demolition and reconstruction of a building, the existing installation shall be surrendered, the agreement terminated and the meter and service mains removed. Only a fresh service is arranged for the reconstructed building, treating it as a new building, and temporary power supply from the existing RR number is not arranged for construction in such cases.

This matters to owners in joint development or redevelopment deals for an independent house or small building. The old meter cannot be used to power the construction site, and the new building goes through the new connection process from the start. Clause 9.06 adds that developers, promoters, owners or occupiers can be sanctioned additional load later, subject to Clause 9 conditions.

Where does this fit with the project's other approvals?

Alongside them. A BESCOM NOC for plan sanction and a power sanction are part of the approval chain, just as the building plan and occupancy certificate are. Our explainer on approvals a builder has taken and those still pending under RERA explains how to read a project's approval list. Use this checklist when you visit.

  1. Ask whether the project's built-up area exceeds 500 sq m or its load is 25 kW or more, which brings it under Clause 9.
  2. Ask to see the BESCOM NOC used for plan sanction and the approved layout showing the transformer.
  3. Confirm the transformer space is part of the approved layout and not part of any area sold to buyers.
  4. Ask whether each flat will have an individual BESCOM meter from a common bus bar.
  5. Locate the metering room near the main entrance at ground floor level.
  6. Ask whether BESCOM has inspected and taken over the lines and transformer before possession.
  7. For redevelopment of an existing building, plan for surrendering the old connection and applying afresh.

Frequently asked questions

Which buildings fall under Clause 9 of the KERC Conditions of Supply?

Clause 9.00 applies to commercial or residential buildings, complexes and multi-storied buildings where the requisitioned load is 25 kW or more, or where the built-up area of the building is more than 500 square metres. Ask your builder whether the project crosses either threshold, because if it does, the builder follows this procedure.

What documents does the builder file for power supply under Clause 9?

Clause 9.01 lists a copy of the sanctioned plan showing built-up area, proof of ownership, GPA or occupancy, the NOC issued by the licensee to obtain plan sanction where applicable, and a route sketch. If the building deviates from the sanctioned plan, a certified as-built plan must also be furnished.

Who provides space for the transformer in an apartment project?

The applicant does. Clause 9.01 says the applicant shall not deviate from the condition of providing space at the premises free of cost for erection of the transformer, as indicated in the layout plan approved by the licensee when it issued the NOC. Clause 9.02 says the space is provided as specified in KERC regulations.

How do individual flats get electricity under Clause 9?

Clause 9.07 says supply to the building shall be through a common service main cable ending in a common bus bar, and supply to individual consumers is tapped from that bus bar through individual meters. Metering space is to be provided near the main entrance at the ground floor, between 0.6 and 1.6 metres above ground.

Last updated 2026-11-25. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.