Septic Tanks, Generators and a Rs 1,000 a Day Penalty: Defects After Handover in Hyderabad
In its November 2026 orders, TG RERA directed a Hyderabad builder to fix a septic tank, drainage lines and generator backup, and kept a Rs 1,000 a day penalty running on another. Here is what the RERA Act says about defects after you move in.
A septic tank that was never built properly. Drainage pipelines left incomplete. Generator backup that could not carry the load. Those were the problems residents of two blocks built by Ayyappa Builders took to TG RERA, and on 18 November 2026 Siasat reported the result: the Authority directed the promoter to construct a proper septic tank, finish the drainage lines and provide adequate generator backup, at its own expense, within 60 days. The Authority also said that an occupancy certificate or a handover to the residents' association does not release the promoter from liability. In the same batch, another promoter was carrying a continuing penalty of Rs 1,000 a day for missing deadlines to fix defects and finish amenities.
The short answer. Under Section 14(3) of the RERA Act, a Hyderabad owner who reports a structural defect or a defect in workmanship, quality or services within five years of possession is entitled to have it fixed free within thirty days, and to compensation if it is not. That liability survives the conveyance deed under the proviso to Section 11(4)(a). If the builder then ignores a TG RERA order, Section 63 allows a penalty for every day of default, up to five per cent of the project's estimated cost. The trade-off is time: a daily penalty pressures the builder, but it is paid to the state, and the repair still depends on compliance or on further enforcement.
What did TG RERA order in the November cases?
Practical repairs with deadlines. According to the Siasat report, Ayyappa Builders was directed to build a proper septic tank, complete incomplete drainage pipelines and provide adequate generator backup at the promoter's expense within 60 days, with Section 63 penalties if it does not comply. The Authority stated that an occupancy certificate or the handover of the project to the residents' association does not release the promoter's liability.
In a separate matter, the report says TG RERA had imposed a continuing penalty of Rs 1,000 per day on RDB Hyderabad Infrastructures Pvt Ltd starting 2 June 2025, which had reached Rs 5.34 lakh by 17 November 2026. The promoter had missed deadlines to fix construction defects, finish amenities and register the project, and was directed to provide proof of compliance and start project registration within 15 days. Recovery steps were also ordered on an earlier unpaid penalty of Rs 6 lakh.
PropNewz covered another set of orders from this batch in our guide to what a Hyderabad property advertisement must show.
How long is your builder responsible for defects?
Five years from the date you get possession. The text of the RERA Act as published on the TG RERA website says in Section 14(3) that if any structural defect, or any other defect in workmanship, quality or provision of services, or any other obligation of the promoter under the agreement for sale, is brought to the promoter's notice by the allottee within five years from the date of handing over possession, the promoter must rectify it without further charge within thirty days.
The wording is wider than cracks in a column. It covers workmanship, quality and provision of services, and obligations under your agreement for sale. A septic tank, a drainage line or a generator promised in the agreement can fall within that language, which is how the Ayyappa residents framed their complaint.
Does the clock stop when the association takes over?
No, and this is the point most owners miss. The proviso to Section 11(4)(a) says the promoter's responsibility for structural or other defects, for the period referred to in Section 14(3), continues even after the conveyance deeds of all the apartments, plots or buildings have been executed in favour of the allottees. The Ayyappa order applied the same idea to an occupancy certificate and an association handover, according to the Siasat report.
Before handover, the Act puts more on the promoter. Section 11(4)(b) makes the promoter responsible for obtaining the completion or occupancy certificate and making it available to allottees or their association, and Section 11(4)(d) makes the promoter responsible for providing and maintaining essential services, on reasonable charges, until the association takes over maintenance. If your association took over a building with a half-built drainage line, the defect clock started for each owner at possession, not at the handover of maintenance.
For a broader explanation of these duties, see our explainer on builder responsibility till conveyance, written for Bengaluru buyers but based on the same central Act.
What does a Rs 1,000 a day penalty actually achieve?
It raises the cost of ignoring an order. Section 63 of the Act says a promoter who fails to comply with, or contravenes, any order or direction of the Authority is liable to a penalty for every day the default continues, which may cumulatively extend up to five per cent of the estimated cost of the project as determined by the Authority. The RDB penalty ran from 2 June 2025 to 17 November 2026 to reach Rs 5.34 lakh, as reported.
For owners, the limitation is that a penalty is not a repair. Section 40(1) of the Act says that interest, penalty or compensation imposed by the Authority, adjudicating officer or Appellate Tribunal that is not paid is recoverable as an arrears of land revenue, in the prescribed manner. That is an enforcement route for money, but the defect itself still needs the promoter to act or the owners to seek compensation.
| Situation | What the Act or order says | Time limit | Source |
|---|---|---|---|
| Defect reported after possession | Promoter must rectify without charge | Notice within five years, fix within 30 days | RERA Act, Section 14(3) |
| Defect not fixed in time | Allottees entitled to appropriate compensation | After the 30 days lapse | RERA Act, Sections 14(3) and 71 |
| Conveyance deeds executed | Defect liability continues | For the Section 14(3) period | RERA Act, Section 11(4)(a) proviso |
| Septic tank, drainage, generator | Promoter to fix at own expense | 60 days | TG RERA order reported by Siasat |
| Order ignored | Daily penalty up to 5% of project cost | Each day the default continues | RERA Act, Section 63 |
How should a Hyderabad owner raise a defect claim?
In writing, with dates, before the five years run out. Section 14(3) turns on the defect being brought to the promoter's notice within five years from possession, so the date and proof of that notice matter more than anything else you do.
- Find your possession letter or handover document and note the date, because the five year period runs from handing over possession.
- Photograph each defect with the date visible and list it room by room or system by system.
- Match each defect to a clause in your agreement for sale, since Section 14(3) covers obligations under the agreement as well as workmanship and quality.
- Send a written notice to the promoter by email and registered post and keep the acknowledgement.
- Count thirty days from receipt, the period Section 14(3) gives the promoter to rectify without charge.
- If the association is pursuing common area defects, ask it to file jointly and attach individual owners' notices.
- If the defect is not fixed, file a complaint with TG RERA and, for compensation, seek adjudication under Section 71.
What about the Rs 8.24 lakh penalty for paperwork?
It shows that documents count too. The Siasat report says Sudheesha Constructions was ordered to refund Rs 10 lakh with 10.85% annual interest and pay a penalty of Rs 8,24,585 at its Sudheesha Dimple Valley project in Puppalguda, for failing to supply home loan documents and for an unauthorised deviation from the standard agreement for sale format, with 60 days to comply.
The Act explains why the format matters. Section 13(2) says the agreement for sale shall be in such form as may be prescribed and shall specify particulars including specifications, internal and external development works, payment dates, the possession date and the interest rates payable both ways on default. A buyer who signs a non-standard agreement may find it harder to show what was promised when a defect appears later.
What should you collect at possession to protect a later claim?
The documents that prove what you were promised and when you got the keys. Section 19(5) of the Act says the allottee is entitled to have the necessary documents and plans, including those of common areas, after the promoter hands over physical possession. Ask for them in writing at handover, not years later when a defect appears.
Timing also runs the other way. Section 19(10) says every allottee shall take physical possession within two months of the occupancy certificate being issued. A buyer who delays taking possession may find the paperwork trail harder to reconstruct. Keep the occupancy certificate copy, the possession letter, the approved plans and the agreement for sale together, because a Section 14(3) claim will lean on all four.
Frequently asked questions
How long is a builder liable for defects in a Hyderabad flat?
Section 14(3) of the RERA Act says that if a structural defect or any other defect in workmanship, quality or provision of services is brought to the promoter's notice within five years from the date of handing over possession, the promoter must rectify it without further charge within thirty days.
Does the builder's liability end after the conveyance deed?
No. The proviso to Section 11(4)(a) of the RERA Act says the promoter's responsibility for structural or other defects, for the period referred to in Section 14(3), continues even after conveyance deeds of all the apartments, plots or buildings have been executed in favour of the allottees.
What happens if a builder ignores a TG RERA order?
Section 63 of the RERA Act makes a promoter who fails to comply with orders or directions of the Authority liable to a penalty for every day the default continues, which may cumulatively extend up to five per cent of the estimated cost of the project. Siasat reported a Rs 1,000 a day penalty on one Hyderabad promoter.
Who decides compensation for unrepaired defects?
Section 71 of the RERA Act provides for an adjudicating officer, a person who is or has been a District Judge, to adjudge compensation under Sections 12, 14, 18 and 19. Section 14(3) itself says allottees are entitled to appropriate compensation if the promoter fails to rectify defects within thirty days.
The Ayyappa residents did not need a new law. They needed the five year window, a written record and the patience to take the complaint to TG RERA. If you moved into a Hyderabad flat in the last five years and something basic still does not work, the first step is the same: write it down and send it to the promoter today.
Last updated 2026-11-28. PropNewz Team.