Builder responsibility till the last conveyance: RERA Section 11(4)(a) for Bengaluru owners
Section 11(4)(a) of the RERA Act keeps the promoter responsible for all obligations until every unit and the common areas are conveyed, and its proviso keeps five year defect liability alive after that. Here is how the timeline works for Bengaluru flat owners and associations.
In a 400 apartment project in Whitefield, the first families might move in years before the last flat is sold. Between those two moments, someone has to answer for the lifts, the water supply, the unfinished clubhouse and the paperwork for the common areas. Under the Real Estate (Regulation and Development) Act, 2016, that someone is the promoter, and the Act says how long that responsibility lasts.
Section 11(4)(a) is a short clause that many buyers never read. It sets the end point of the promoter's obligations at the conveyance of all apartments to allottees and of the common areas to the association, and then carves out a longer tail for defects. This guide explains what that means at each stage of a Bengaluru purchase.
The short answer. Section 11(4)(a) of the RERA Act makes the promoter responsible for all obligations under the Act, the rules and regulations, and the agreement for sale, until the conveyance of all apartments, plots or buildings to allottees and of the common areas to the association of allottees or the competent authority. Its proviso keeps the promoter responsible for structural and other defects for the five year period in Section 14(3) even after all conveyance deeds are executed. The trade-off: your protection does not end when you get your keys or your sale deed, but enforcing it depends on you and your association keeping records and raising issues in writing within the statutory windows.
What does Section 11(4)(a) say?
According to the Gazette of India text of the RERA Act, the promoter shall be responsible for all obligations, responsibilities and functions under the Act or the rules and regulations, or to the allottees as per the agreement for sale, or to the association of allottees, till the conveyance of all the apartments, plots or buildings to the allottees, or the common areas to the association of allottees or the competent authority.
The proviso then says that the promoter's responsibility for structural defects or any other defect, for the period referred to in Section 14(3), shall continue even after the conveyance deeds of all the apartments, plots or buildings are executed. In other words, there are two clocks. One stops at the last conveyance. The other runs for five years from handing over possession.
Does the promoter's responsibility end when you take possession?
No. Possession and conveyance are different events. Section 19(10) says every allottee shall take physical possession within two months of the occupancy certificate issued for the apartment. Section 17(1) requires the promoter to execute a registered conveyance deed in favour of the allottee, along with the undivided proportionate title in the common areas to the association, and hand over physical possession and other title documents within the period specified under local laws. In the absence of a local law, its proviso sets three months from the date of issue of the occupancy certificate.
Because Section 11(4)(a) ties the promoter's general obligations to the conveyance of all apartments and the common areas, a promoter whose project is partly sold, or whose common areas have not been conveyed, remains answerable under the Act for the project as a whole.
What other duties run alongside Section 11(4)(a)?
The same sub-section lists specific duties. Clause (b) makes the promoter responsible for obtaining the completion certificate or occupancy certificate, or both, and making it available to allottees individually or to the association. Clause (c) applies where a project is on leasehold land: the promoter must obtain a lease certificate specifying the lease period and certifying that all dues and charges for the land have been paid, and make it available to the association. Clause (d) requires the promoter to provide and maintain essential services, on reasonable charges, until the association takes over maintenance. Clause (e) requires the promoter to enable formation of an association, and, in the absence of local laws, provides for it within three months of a majority of allottees booking.
Clause (g) requires the promoter to pay all outgoings collected from allottees until physical possession is transferred, including land cost, ground rent, municipal taxes, water and electricity charges, maintenance charges, and mortgage loans and interest related to the project. If it fails to pay them before transfer, the promoter continues to be liable even after the transfer. Our guide to common areas and the residents association looks at clauses (d), (e) and (g) in more detail.
| Stage | Provision | What the Act says | What it means for you |
|---|---|---|---|
| Occupancy certificate | Section 11(4)(b) | Promoter obtains the OC or completion certificate and makes it available | Ask for a copy before taking possession |
| Possession | Section 19(10) | Allottee takes possession within two months of the OC | Plan your move and payments around this window |
| Conveyance | Section 17(1) | Registered conveyance as per local law, or within three months of the OC if no local law | Track when your sale deed is executed |
| Until last conveyance | Section 11(4)(a) | Promoter answers for all obligations until all units and common areas are conveyed | Raise project issues with the promoter, not only the association |
| Five years from possession | Section 14(3) | Defects notified within five years rectified free within 30 days | Report defects in writing and keep proof |
How long does the defect liability last after conveyance?
Section 14(3) says that if any structural defect, or any other defect in workmanship, quality or provision of services, or any other obligation of the promoter under the agreement for sale, is brought to the promoter's notice by the allottee within five years from the date of handing over possession, the promoter shall rectify it without further charge within 30 days. If the promoter fails to do so, the aggrieved allottees are entitled to appropriate compensation as provided under the Act.
The proviso to Section 11(4)(a) confirms that this five year responsibility survives the execution of all conveyance deeds. So a seepage problem you notice in year three is still the promoter's to fix, even if your sale deed was registered in year one and the common areas have been handed over.
What happens after the common areas are handed over?
Section 17(2) provides that after obtaining the occupancy certificate and handing over physical possession, it shall be the promoter's responsibility to hand over the necessary documents and plans, including common areas, to the association of allottees or the competent authority, as the case may be, as per local laws. We covered that handover in our explainer on documents and plans after the occupancy certificate.
For buyers, the practical point is to keep the promoter in the loop until both clocks have stopped. If your association is still waiting for the common areas to be conveyed, the promoter's general obligations under Section 11(4)(a) continue. If the common areas have been conveyed but you are within five years of possession, the defect liability under Section 14(3) continues.
What can you do if the promoter does not meet these obligations?
Section 18(3) says that if the promoter fails to discharge any other obligations imposed on it under the Act, the rules or regulations, or the terms of the agreement for sale, it shall be liable to pay such compensation to the allottees in the manner provided under the Act. That is the general remedy behind the duties described above.
Two routes follow from the Act. Section 31(1) lets any aggrieved person file a complaint with the authority or the adjudicating officer for any violation of the Act or its rules and regulations, and its explanation says a person includes an association of allottees. Section 71(1) provides for adjudicating officers, who are or have been District Judges, to decide compensation under Sections 12, 14, 18 and 19. Section 71(2) says such an application shall be disposed of within 60 days of receipt, and if it cannot be, the adjudicating officer must record reasons in writing.
For associations, this matters because many issues in a large project are collective. A complaint about unconveyed common areas, unpaid outgoings or a defect in a shared structure can carry more weight when filed by the association with minutes and correspondence attached, rather than by one owner alone.
What should Bengaluru buyers and associations do?
The Act gives allottees and associations a long window, but it rewards those who document. The list below is a simple record keeping routine for owners and association committees.
- Keep a copy of the occupancy certificate the promoter makes available under Section 11(4)(b).
- Record the date you were handed possession, since the five year defect period runs from it.
- Track the date your conveyance deed was registered and when the common areas were conveyed.
- Report every defect to the promoter in writing and note the date of the notice.
- Follow up if a notified defect is not rectified within 30 days.
- Ask the promoter for proof that outgoings collected from allottees have been paid.
- Keep association minutes showing which issues were raised with the promoter and when.
Frequently asked questions
Until when is a builder responsible under Section 11(4)(a) of RERA?
Section 11(4)(a) makes the promoter responsible for all obligations under the RERA Act, its rules and regulations, and the agreement for sale, until all apartments, plots or buildings are conveyed to allottees and the common areas are conveyed to the association of allottees or the competent authority.
Does defect liability end once my sale deed is registered?
No. The proviso to Section 11(4)(a) says the promoter's responsibility for structural and other defects, for the period in Section 14(3), continues even after the conveyance deeds of all apartments are executed. Section 14(3) covers defects notified within five years from the date of handing over possession.
How quickly must a builder fix a defect I report?
Under Section 14(3) of the RERA Act, a defect brought to the promoter's notice within five years of handing over possession must be rectified without further charge within 30 days. If the promoter fails, the aggrieved allottees are entitled to appropriate compensation as provided under the Act.
When must the conveyance deed be executed?
Section 17(1) of the RERA Act requires a registered conveyance deed within the period specified under local laws. Where there is no local law, its proviso requires conveyance within three months from the date of issue of the occupancy certificate. Check which timeline applies to your project.
Last updated 2026-11-26. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.