Due in 2017, Still Waiting in 2026: What MahaRERA's Vasai Orders Mean for Delayed Buyers

Two Vasai buyers promised flats by December 2017 won MahaRERA orders on 18 November 2026 directing handover within 60 days. The Authority rejected a Covid plea because the deadline expired in 2018. Here is what delayed buyers in the Mumbai region can take from it.

Legal & Documentation
Updated on
November 28, 2026
12 min read

December 2017. That was when Amruta and Mayur Kate were promised their flat in the Ekta Parksville layout at Vasai, under an agreement for sale dated 11 May 2016 and registered five days later. The price was Rs 30 lakh. They paid Rs 28,99,000, including Rs 1,80,200 in stamp duty, and their bank disbursed Rs 28,10,000 of a Rs 29 lakh home loan. Eight more months of grace came and went. On 18 November 2026, nearly nine years after the original date, MahaRERA ordered the developer to hand over the flat within 60 days, the Free Press Journal reported on 21 November.

The short answer. MahaRERA Member Ravindra Deshpande passed two orders on 18 November directing Ekta Parksville Homes Pvt Ltd to hand over two flats at Vasai within 60 days, with statutory interest for delay. The Authority rejected the Covid-19 argument because the agreed possession period, including an eight month extension, expired in August 2018. For delayed buyers, the useful lesson is that the possession date in your agreement is the yardstick, and long lists of project extensions do not automatically move it. The trade-off is that staying in the project gets you the flat and monthly interest, but it can mean years of waiting, as these buyers found.

What did MahaRERA decide in the two Vasai orders?

Handover within 60 days in both. According to the report, the first order covers the Kate couple, whose flat was promised for December 2017 with a further eight month extension. The developer blamed the delay on the change of planning authority from CIDCO to the Vasai Virar City Municipal Corporation, stop-work notices, sand shortages, incomplete infrastructure by HDIL, delayed approvals and occupancy certificate, and Covid-19. It cited MahaRERA extensions totalling 79 months. MahaRERA rejected the contention and ordered handover with statutory interest for the delay.

The second order concerns Susan and Krishnarajan Nedungadi, who booked in October 2010 and paid Rs 17,69,978 before any agreement, with possession promised for December 2017. The developer said it obtained the occupancy certificate on 15 May 2019 and offered possession on 21 May. The report says MahaRERA directed handover within 60 days, with interest at SBI's highest MCLR plus 2% for the period from 1 July 2018 to 21 May 2019.

Why did the Covid plea fail?

Because the deadline had already passed. The report quotes MahaRERA as saying the agreed possession period, including the eight month extension, expired in August 2018, much before Covid-19. A pandemic that began more than a year after a missed deadline could not explain that miss.

That logic is worth carrying into any dispute. When a developer lists reasons for delay, line each one up against your agreed date. Events that came after the date has already lapsed are unlikely to help the developer's case on that delay, as this order shows.

Does a project extension move your possession date?

The Act treats the two as different things. The text of the RERA Act as published in the Gazette says in Section 6 that the Authority may extend a project's registration on an application by the promoter due to force majeure. Its proviso allows extension in reasonable circumstances without default by the promoter, for reasons recorded in writing, which shall in aggregate not exceed one year. The Explanation defines force majeure as war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting regular development.

Section 18(1)(a), by contrast, measures the promoter's failure to complete or give possession against the terms of the agreement for sale or the date specified in it. In the Vasai case, the developer pointed to 79 months of extensions, and the Authority still ordered handover with interest. PropNewz looked at this distinction in detail in our report on MahaRERA's four month force majeure extension.

What interest can a delayed buyer claim?

Monthly interest at the prescribed rate, if you stay. The proviso to Section 18(1) says that where an allottee does not intend to withdraw from the project, the promoter shall pay interest for every month of delay till the handing over of possession, at such rate as may be prescribed. The rate comes from state rules, and in the second Vasai order the report puts it at SBI's highest MCLR plus 2%.

If you would rather exit, the main part of Section 18(1) says the promoter is liable on demand to return the amount received with prescribed interest, including compensation, where the allottee wishes to withdraw. That route ends the wait but returns money, not a home. For the full comparison, see our guide to choosing between a refund and delay interest.

DetailKate orderNedungadi orderSource
Booking or agreementAgreement dated 11 May 2016Booked October 2010Free Press Journal, 21 November 2026
Promised possessionDecember 2017 plus eight monthsDecember 2017Free Press Journal, 21 November 2026
Amount paidRs 28,99,000 including stamp dutyRs 17,69,978 before agreementFree Press Journal, 21 November 2026
Developer's key pleaCovid-19 and 79 months of extensionsOC on 15 May 2019, offer on 21 MayFree Press Journal, 21 November 2026
OutcomeHandover in 60 days, statutory interestHandover in 60 days, interest 1 July 2018 to 21 May 2019Free Press Journal, 21 November 2026

Why did the second buyer's interest stop in May 2019?

Because that is when possession was offered with an occupancy certificate, according to the developer's account in the report. The interest period the report describes runs from 1 July 2018 to 21 May 2019, the date of the offer. The proviso to Section 18(1) ties delay interest to the period till possession is handed over, and an offer made with an occupancy certificate is what the developer relied on as the end point.

The Act also places a duty on the buyer at this stage. Section 19(10) says every allottee shall take physical possession within two months of the occupancy certificate being issued. If you receive a valid offer of possession with an OC, read it carefully and respond in writing, because the date can affect both your interest claim and your own obligations.

What should a delayed Mumbai region buyer do now?

Build the record the Vasai buyers needed. Both orders turned on dates: the agreed possession date, the grace period, the date of the occupancy certificate and the date possession was offered.

  1. Find your agreement for sale and write down the possession date and any grace period it allows.
  2. Check the registration date of the agreement, as the Kate agreement was registered on 16 May 2016.
  3. List every reason the developer has given for delay and note whether each event came before or after your agreed date.
  4. Track any MahaRERA registration extensions separately, since Section 6 deals with registration, not your agreement date.
  5. Keep a payment ledger showing each instalment, stamp duty and loan disbursement, as the order figures did.
  6. Decide whether you want possession with monthly interest or a refund with interest under Section 18(1).
  7. If an offer of possession arrives, check that it comes with an occupancy certificate and respond within the two months Section 19(10) mentions.

What does a long delay cost a buyer with a home loan?

More than the wait. The Kate couple's bank had disbursed Rs 28,10,000 by the time of the complaint, according to the report. As an illustration only, a loan of that size at an assumed 8.5% a year over 20 years carries an EMI of about Rs 24,386, or roughly Rs 2.93 lakh a year, before any rent the family pays while waiting. The report does not give the actual loan rate or EMI, so treat these as round numbers for planning, not figures from the case.

This is why the choice under Section 18(1) matters. Monthly delay interest at the prescribed rate helps offset that outflow if you stay, while a refund with interest returns money that can go towards the loan but ends your claim on the flat. Before choosing, set the interest you expect under the state rate against your EMI and rent, and talk to your lender about how either outcome affects the loan account.

After the order: tracking the 60 day deadline

An order is only as good as compliance, and the Kate complaint was filed on 14 December 2024, almost two years before this order. Buyers should calendar the 60 day deadline from the order date and be ready to return to MahaRERA if the handover does not happen. For readers of our possession delay guide, this is the stage where the paperwork you gathered earlier does the work.

Frequently asked questions

What did MahaRERA order in the Ekta Parksville Vasai cases?

According to the Free Press Journal report of 21 November 2026, MahaRERA Member Ravindra Deshpande passed two orders on 18 November directing Ekta Parksville Homes Pvt Ltd to hand over two flats in its Vasai project within 60 days, with statutory interest for the delay in the first order.

Why did MahaRERA reject the developer's Covid argument?

The report quotes MahaRERA as saying the agreed possession period, including the eight month extension, expired in August 2018, much before Covid-19. Because the deadline had already passed before the pandemic, the delay could not be attributed to it in that order, according to the Free Press Journal account.

Does a RERA registration extension change my possession date?

The RERA Act treats them separately. Section 6 lets the Authority extend a project's registration on force majeure grounds, up to one year in aggregate under its proviso. Section 18(1)(a) measures a promoter's failure against the terms of the agreement for sale or the date specified in it.

Can I claim delay interest and still take the flat?

Yes. The proviso to Section 18(1) of the RERA Act says that where an allottee does not intend to withdraw from the project, the promoter shall pay interest for every month of delay till the handing over of possession, at the rate prescribed under the state rules.

The Kate family signed in 2016 for a flat they were told would be ready in 2017. The order gives them a date at last. The documents that won it were ordinary ones, the agreement, the receipts and the loan statement, and every delayed buyer can start gathering them today.

Last updated 2026-11-28. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.