What a New Bengaluru House Pays BESCOM for the Power Line: KERC Regulation 3.1
When a new independent house in Bengaluru applies for an LT connection, KERC's Recovery of Expenditure regulations, published with BESCOM's conditions of supply, set what the owner pays towards the electric line up to the terminal pole. The published slabs start at nil up to 3 kW. Here is how the charges and the owner's own wiring obligations work.
Picture a new two-storey house on a 30 by 40 site in a Bengaluru layout, wired for two air conditioners, an induction cooktop and a geyser, with a requisitioned load of 7 kW. Before the meter is fixed, BESCOM sends a power sanction stating an amount towards the expenses of providing the electric line or plant. That figure is not arbitrary. It comes from a slab table in the KERC Recovery of Expenditure for Supply of Electricity Regulations, 2004, published with BESCOM's conditions of supply.
The KERC Conditions of Supply of Electricity on BESCOM's website carry those regulations as Annex 2. Regulation 3.1.1 sets the charge for LT supply up to the point of connection, which it defines as a terminal pole carrying the LT or HT line within 30 metres outside the applicant's premises.
The short answer. Under the published slabs, a domestic connection up to 3 kW pays nil towards the line, 3 to 15 kW pays Rs 650 per kW above 3 kW, and 15 to 25 kW pays Rs 7,800 plus Rs 1,300 per kW above 15 kW. In the Bangalore Metropolitan Area, an additional Rs 1,000 per kW above 3 kW is collected. The owner separately pays for the service line from the pole into the house. The trade-off: asking for a higher load than you need raises these one-time charges, while asking for too little means applying again for additional load later.
How are line charges calculated for a house?
By requisitioned load, in slabs. Regulation 3.1.1 says the licensee recovers the cost of the electric line and plant up to the point of connection from the applicant, for all installations clubbed together in a premises in the name of one or more persons. For domestic, commercial and mixed loads below 25 kW, the published table is as follows.
| Requisitioned load | Published line charge |
|---|---|
| Up to and including 3 kW | Nil |
| Above 3 kW up to and including 15 kW | Rs 650 per kW for load above 3 kW |
| Above 15 kW and below 25 kW | Rs 7,800 plus Rs 1,300 per kW for load above 15 kW |
| Additional charge in Bangalore Metropolitan Area | Rs 1,000 per kW for load above 3 kW |
| 25 kW or more, or built-up area above 500 sq m | Applicant provides line, dedicated transformer and space under Regulation 3.1.5 |
The regulation's notes add that fractions of a kW are rounded up to the next higher kW, and that the metropolitan charge applies in the Bangalore Mahanagara Palike area, several named city and town municipal council areas including Yelahanka, Krishnarajapura, Mahadevapura and Bommanahalli, and BDA areas, towards underground or aerial bunched cable systems. These are the figures as published on BESCOM's site; charges can be revised, so rely on your demand letter.
What does that mean for a 7 kW or 10 kW house?
The arithmetic is simple. Using the published slabs for an illustrative 7 kW domestic load in the metropolitan area: 4 kW above the 3 kW threshold at Rs 650 per kW is Rs 2,600, plus 4 kW at Rs 1,000 per kW is Rs 4,000, giving Rs 6,600 towards the line. For an illustrative 10 kW load, 7 kW at Rs 650 is Rs 4,550 and 7 kW at Rs 1,000 is Rs 7,000, giving Rs 11,550. Your demand letter remains the final word on the amount payable.
These are line charges only. The power sanction also lists the initial security deposit, the meter security deposit and other charges, which are set separately. PropNewz explains how those deposits earn interest and are refunded in today's guide to BESCOM deposits on a Bengaluru home.
What must the owner build at their own cost?
The last stretch into the house. Regulation 3.1.3 says the applicant executes at their own cost the LT service line from the terminal pole outside the premises to the point of commencement of supply in the premises, through an appropriate class of licensed electrical contractor. Regulation 3.1.2 says the licensee executes the works up to and including the terminal pole after collecting the charges in Regulation 3.1.1.
An applicant can also choose to build the line extension itself. Regulation 3.1.2 says that if the applicant opts to execute the extension work to the licensee's estimate, drawings and specifications, this shall be granted, the applicant pays supervision charges of 10 percent of the estimated cost, excluding employees' cost, up to Rs 15 lakh, and the licensee shall not collect the slab charges in that case. Regulation 3.1.4 says supply is then provided within the time frame in the Duty to Supply regulations, which today's explainer on BESCOM connection time limits covers.
What if you later add load?
You pay for the extra at the slab for the new total. The note to Regulation 3.1.1 says that where additional load is requisitioned for an existing installation, the line cost is collected for the additional load only, at the slab rate arrived at from the total of existing and additional load. The Rs 1,000 per kW metropolitan charge is also collected for the additional load sought.
Clause 34.01 of the conditions says the procedure for sanction of additional power is the same as for a new installation, except that dues must be cleared first. If you are planning an extra floor, a home office or an EV charger in the next few years, it may be simpler to size the original requisition sensibly, while remembering that a higher requisitioned load also raises the one-time charges.
What changes for a large house or a small building?
A dedicated transformer and space. Regulation 3.1.5 says that where the requisitioned load is 25 kW or more, or the built-up area of the premises exceeds 500 sq m, the applicant provides the required space and, at their own cost, the electric line, a distribution transformer dedicated to the premises and associated equipment.
The space can be an electrical room with an RCC roof of 5 metres by 4 metres clear floor area, 2.75 metres high, lockable, with exhaust fans and a cable duct, at ground floor near the main entrance, for a floor mounted transformer; or a clear 3 metres by 5 metres space open to the sky, preferably at the main entrance, for a structure mounted transformer. A note sets separate charges for applicants whose building plans were sanctioned before 25 August 2005 and who cannot provide such space. For a buyer of a large independent house or a small building, ask whether this space was provided in the approved plan, and ask the architect to show it on the drawings.
How are apartment and mixed-use buildings classified?
By the share of commercial load. The notes to Regulation 3.1.1 say that where residential apartments or complexes have a requisitioned load of 100 kW or more, LT supply to individual houses can be arranged at the applicant's request, subject to the other conditions. For commercial or mixed loads, the maximum total requisitioned load for this LT route is below 100 kW.
For buildings with both domestic and commercial or mixed loads, the notes say that if the commercial share, treating power load as commercial, is 25 percent or less of the total combined load of the entire building, irrespective of ownership, the building is treated as residential for the tariff on common area loads and for arranging HT supply. If the commercial share exceeds 25 percent, the building is treated as commercial for those purposes. For a buyer of a flat in a building with shops on the ground floor, this classification affects how common area electricity, such as lifts and pumps, is billed, so it is worth asking the builder which side of the 25 percent line the building falls on.
How should a buyer of a new house plan for these charges?
Treat them as part of the move-in budget. Our guide to BESCOM new connections for a Bengaluru home covers the documents. Use this checklist for the charges.
- Work out the load you need with your electrical contractor, rounding fractions up to the next kW.
- Check whether the property is in the Bangalore Metropolitan Area, where an extra Rs 1,000 per kW above 3 kW applies.
- Calculate the expected line charge from the published slabs and compare it with the sanction letter.
- Budget separately for the service line from the terminal pole to the house.
- Ask whether a terminal pole exists within 30 metres of the premises.
- If the load is 25 kW or more, or built-up area exceeds 500 sq m, plan transformer space.
- Keep the power sanction letter and receipts with your property documents.
Frequently asked questions
What does a new house pay BESCOM towards the power line?
Under Regulation 3.1.1 of the KERC Recovery of Expenditure regulations published with BESCOM's conditions of supply, domestic loads up to 3 kW pay nil, loads above 3 kW up to 15 kW pay Rs 650 per kW above 3 kW, and loads above 15 kW and below 25 kW pay Rs 7,800 plus Rs 1,300 per kW above 15 kW.
Is there an extra charge in Bengaluru?
Yes. The published note says an additional Rs 1,000 per kW for loads above 3 kW is collected in the Bangalore Metropolitan Area, covering the city corporation, several named city and town municipal councils and BDA areas, towards underground or aerial bunched cable systems. Check the current figure in your demand letter.
Who lays the cable from the pole to the house?
Regulation 3.1.3 says the applicant executes at their own cost the LT service line from the terminal pole outside the premises to the point of commencement of supply, through an appropriate class of licensed electrical contractor. The note to Regulation 3.1.1 defines the point of connection as a terminal pole within 30 metres outside the premises.
What changes for loads of 25 kW or more?
Regulation 3.1.5 says that where the requisitioned load is 25 kW or more, or built-up area exceeds 500 sq m, the applicant provides space and, at their own cost, the electric line, a dedicated distribution transformer and associated equipment, either in a 5 by 4 metre electrical room or a 3 by 5 metre open space.
Last updated 2026-11-25. PropNewz Team.