Supertech's Micasa, Bengaluru and NBCC: What the Supreme Court's Order Means for Buyers

On 5 February 2026 the Supreme Court upheld an NCLAT order entrusting 16 stalled Supertech projects, including Micasa in Bengaluru, to NBCC, with no cost escalation for subsisting allottees beyond agreement dues, 70 percent of receivables for construction, project-wise accounts and court committees.

Projects
Updated on
November 23, 2026
12 min read

Micasa, Bengaluru. It is item eleven on a list of 16 unfinished Supertech Limited projects that the Supreme Court, on 5 February 2026, left in the hands of NBCC India Ltd., a Government of India entity, to complete. The other fifteen are in Noida, Greater Noida, Gurugram, Meerut and Rudrapur. The judgment in Apex Heights Pvt. Ltd. v. Ram Kishor Arora, Civil Appeal No. 2626 of 2025, upheld an NCLAT order that set out how the projects would be finished and how buyers would be protected while that happened.

If you are one of the Micasa buyers, or you are watching any stalled Bengaluru project caught in insolvency, the directions in this case show what protections a tribunal can build around homebuyers. This guide sets out what the judgment says, and what it leaves for you to check.

The short answer. The Supreme Court upheld the NCLAT's order bringing NBCC in to complete 16 Supertech projects, including Micasa in Bengaluru. Among the NCLAT directions it reproduced: allottees whose allotments subsist shall not face any escalation of cost beyond dues payable under their builder buyer agreements; 70 percent of project receivables go to construction; each project has its own account; and Apex and project-wise court committees oversee spending. The Court also directed that no court or tribunal pass interim orders stopping any project started by NBCC. The trade-off: buyers gain a completion route and price protection, but other creditors' claims are only deferred, not erased, and the judgment does not report the current status of any individual project.

What did the Supreme Court decide on 5 February 2026?

Chief Justice Surya Kant and Justice Joymalya Bagchi dismissed a batch of appeals against the NCLAT's order and upheld it, except as modified or clarified. The insolvency began when Union Bank of India filed under section 7 of the Insolvency and Bankruptcy Code, admitted by the NCLT, New Delhi, on 25 March 2022, and the dispute concerned completion of 16 projects launched mostly between 2010 and 2012.

The Court said the primary consideration was to protect the interests of homebuyers and ensure they could secure the units they had been waiting for for more than two decades. It said competing claims of secured creditors, operational creditors and land owners, including Noida, Greater Noida and Yamuna Expressway authorities, would for the time being be secondary, with any surplus distributed later on a pari passu basis or another fair mechanism decided by the tribunal. It described the arrangement as deserving protection under Article 142 of the Constitution, given the peculiar facts of the case.

The scale is large. The judgment records that, according to Supertech's management, the 16 projects had about 40,000 residential units, while counsel for the homebuyers put the figure at over 51,000. It notes that some units had been completed and handed over before the insolvency began in 2022, and more during the appeals, and that the NCLAT order had been stayed by the Supreme Court on 21 February 2025 until this judgment.

How NBCC came in is also recorded. Paragraph 16 says the homebuyers, finding their projects incomplete for an indefinite period, approached NBCC or suggested that a Government of India entity be brought in, and that the project management consultant and the interim resolution professional supported this after discussions with NBCC. The Court held that bringing NBCC on record was neither unfair nor contrary to any express provision of the Code.

Which protections did the NCLAT order give homebuyers?

The judgment reproduces the salient NCLAT directions. The ones that matter most to a buyer are set out below.

DirectionWhat it saysWhy it matters to a buyer
No cost escalationAllottees with subsisting allotments face no escalation of cost, except dues payable under the builder buyer agreementYour price is held to your agreement
70 percent for construction70 percent of a project's amount is used for construction; the balance may go to repayments as decided by the Apex Court CommitteeMost collections stay in building the project
Project-wise accountAll receivables of a project go into its own account, debited only with committee approval and operated jointly by the IRP and an NBCC nomineeMoney from your project is tracked separately
Court committeesAn Apex Court Committee and a project-wise court committee for each project, with an NBCC member on eachSpending is supervised project by project
No exemption from lawNBCC cannot be exempted from building regulations and the RERA Act, 2016Approvals and RERA duties still apply

The NCLAT also directed statutory authorities to decide on renewal or grant of building plans and project registrations within 30 days of the IRP's application, and the Supreme Court said those directions must be complied with within four weeks, with expired sanctions or permissions renewed or revived within that period. Ask the project-wise committee for the latest statement of your project's account and approvals, since the judgment itself does not report balances or sanction status.

How will NBCC be paid and funded?

The NCLAT directions say NBCC is to arrange finance of Rs 100 crore to be deposited in a designated account, "NBCC (I) Ltd. Supertech Unfinished Project", operated by NBCC with the IRP's joint signature and under the Apex Court Committee's control. On fees, the NCLAT held that a 1 percent marketing fee would be included within an 8 percent project management consultancy fee, with no separate marketing fee.

The Supreme Court recorded NBCC's assurance that pending works would be undertaken on a war footing and completed within the stipulated timeline, and directed NBCC to deploy its resources accordingly. It noted NBCC's objections to some NCLAT conditions and gave it liberty to seek clarification from the NCLAT, without expressing a view.

The NCLAT had also set a timetable: certain conditions were to be completed by 31 March 2025, NBCC was to start awarding work before that date and complete the award within a month, and construction was to commence from 1 May 2025. Because the Supreme Court had stayed the NCLAT order in February 2025, those dates should be read as the tribunal's original plan; ask the committees for the current schedule.

Can anyone stop the work through another court?

Not by an interim order. Paragraph 19 says that to ensure there is no impediment to completion, no tribunal or court, including a High Court, shall pass any interim order or direction stopping any project being commenced by NBCC. Any entity with a grievance may approach the Supreme Court directly.

The Court also appointed Senior Advocate Rajiv Jain and advocate Amarendra Kumar as amicus curiae to assist the tribunal and monitor the projects, and directed that the non-residential parts of integrated projects also be completed by NBCC, not by Supertech.

What does this mean for other creditors and land authorities?

Their claims are deferred, not cancelled. Paragraph 18 says completing the residential projects and handing units to buyers will not prejudice the claims of the land authorities, any other housing authority or creditors, including operational creditors, which the tribunal will decide in due course. The NCLAT directions say repayment to land authorities, banks and financial institutions shall begin simultaneously as decided by the Apex Court Committee, and that land cost can be paid from the 70 percent amount, with reference to section 4(2) of the RERA Act.

For buyers, the protection is that those claims cannot be loaded on to them as a cost escalation while their agreements subsist. It is a similar instinct to the one in the Supreme Court's later Lotus ruling on a failed developer's penalties.

What should a Micasa or other affected buyer do?

  1. Confirm your allotment subsists and keep your builder buyer agreement and payment proofs ready.
  2. Check the IRP's website for the constitution of the Apex and project-wise court committees.
  3. Ask the project-wise committee for the construction schedule for your tower.
  4. Pay only dues payable under your agreement, and question any escalated demand.
  5. Keep track of approvals and RERA registration renewals for your project.
  6. Take grievances to the forum the judgment specifies, not to a new court for a stay.
  7. File or update your claim as instructed by the IRP and keep copies.

If you bought in a different Supertech project, outside the 16, note paragraph 26. It says several applications filed by homebuyers and others about projects other than the 16 were disposed of with liberty to approach the NCLT or NCLAT in the pending proceedings for appropriate directions.

For the general claim process in any builder insolvency, our guide to filing a claim in the revised Form CA explains the form homebuyers now use.

Frequently asked questions

Is a Bengaluru project covered by the Supreme Court's NBCC order?

Yes. The judgment in Apex Heights Pvt. Ltd. v. Ram Kishor Arora, decided on 5 February 2026, lists Micasa, Bengaluru as one of the 16 Supertech Limited projects whose completion the NCLAT entrusted to NBCC India Ltd., an order the Supreme Court upheld except as modified.

Can buyers in these projects be charged more than their agreement price?

The NCLAT direction reproduced in the judgment says homebuyers and commercial unit holders whose allotments by the corporate debtor subsist shall not be subjected to any escalation of cost, except the dues they must pay under their builder buyer agreements. The Supreme Court upheld the NCLAT order.

Can another court stop NBCC's work on these projects?

Not through interim orders. The Supreme Court directed that no tribunal or court, including a High Court, shall pass any interim order or direction stopping any project being commenced by NBCC, and that any entity with a grievance may approach the Supreme Court for directions instead.

What happens to the money buyers pay for these projects?

Under the NCLAT directions, all receivables of a project go into a project-wise account, operated jointly by the IRP and an NBCC nominee and debited only with committee approval. Seventy percent of the amount is used for construction, and the balance may be used for repayments as the Apex Court Committee decides.

This guide summarises a Supreme Court judgment and is not legal advice. It does not report the current construction status of any project; check with the IRP and the court committees.

Last updated 2026-11-23. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.