Can Buyers Be Made to Pay a Bankrupt Builder's Penalties? The Supreme Court's Lotus Ruling
In Civil Appeal No. 3132 of 2026, decided on 3 September 2026, the Supreme Court set aside directions to treat NOIDA's time extension charges for the Lotus projects as insolvency costs, holding homebuyers and the resolution applicant could not be penalised for the developer's delay, in the case's peculiar facts.
A decade. The Lotus Boulevard and Lotus Panache projects in Noida were meant to be completed in 2016, the Supreme Court noted on 3 September 2026, and "despite another decade having passed, the homebuyers are still left in the lurch." The buyers had pooled their own money to keep building after the developer went into insolvency. Then the land-owning authority, NOIDA, sealed three towers over unpaid time extension charges and sought to have those charges treated as insolvency process costs. The Supreme Court's judgment in Civil Appeal No. 3132 of 2026 said no.
The case is from Noida, but its lesson travels. Some projects anywhere are built on land leased or allotted by a public body, with obligations attached, and when a builder fails, someone has to decide who bears the penalties it ran up. This guide explains what the Court decided, how narrowly it framed the ruling, and what a Bengaluru buyer can take from it.
The short answer. On 3 September 2026, Justices J.B. Pardiwala and K. Vinod Chandran held that NOIDA's time extension charges, penalties for the developer's delay, could not validly be imposed on the homebuyers and the successful resolution applicant, and set aside the direction to treat them as insolvency process costs. NOIDA's claim for charges up to the tenth year was also rejected. The trade-off: the ruling protects buyers from paying for a defaulting developer's penalties, but the Court expressly decided it "in the peculiar facts and circumstances of the case", so it is not a blanket rule for every project or authority.
What happened in the Lotus case?
The judgment records that the developer, Granite Gate Properties Private Limited, took two plots on perpetual lease from the New Okhla Industrial Development Authority at a high premium and advertised two projects, Lotus Boulevard in Sector 100 and Lotus Panache in Sector 110. The developer ran into trouble and was declared a corporate debtor. The Committee of Creditors was made up of the homebuyers, as a class of financial creditors, and a resolution plan by SMV Agencies Private Limited was approved.
The homebuyers' authorised representative told the Court that during the insolvency process, buyers pooled their own resources as advance payment of the balance sale consideration and carried on construction under a "Pool and Build" mechanism approved by the committee. NOIDA sealed three towers of Lotus Panache on 16 October 2024, pending a decision on the time extension charges.
What were the time extension charges?
Penalties for delay under the lease. The judgment notes that the original lease deed set time extension charges at 4, 5 and 6 percent in the first, second and third years of delay, with cancellation of the lease after three years. NOIDA relied on an office order of 18 October 2019, read with one of 18 June 2015, which provided for extensions up to the tenth year, at 7, 8, 9 and 10 percent for the first four years and 1 percent of the total premium a year thereafter.
The NCLAT had directed that the charges be treated as insolvency process costs for up to three years. NOIDA wanted more; the homebuyers wanted none. The resolution plan itself recorded that, unless judicially held to be process costs, any cost above a Rs 3 crore estimate would first be recovered from allottees of towers 17, 18 and 19 of Lotus Panache as a super area charge. That is how the developer's delay penalty threatened to land on buyers.
The arguments on each side are worth knowing, because similar disputes can arise elsewhere. The homebuyers' representative argued that the charges were not insolvency process costs under section 5(13)(c), as the judgment records the argument, since they were neither incurred by the resolution professional nor related to continuing the project. It said NOIDA had claimed them as dues of the developer for three years, from December 2016 up to the insolvency commencement date of 10 January 2019, and that the charges were penal in nature, so buyers should not be saddled with the defaulting developer's liability.
NOIDA argued that without payment of the charges the project could not continue, so they had to be treated as process costs. It pointed out that the lease was governed by the Uttar Pradesh Industrial Area Development Act, 1976 and the rules and directions under it. The resolution applicant adopted the buyers' arguments, noting that the plan capped contingent protection at the overlap period balance.
| Issue | Position put to the Court | What the Supreme Court decided |
|---|---|---|
| Time extension charges as CIRP costs | NCLAT had allowed them for up to three years | Directions set aside |
| Charges beyond three years, up to the tenth year | NOIDA sought them under its 2019 office order | NOIDA's appeal rejected |
| Who caused the delay | The developer, now a corporate debtor | Neither the homebuyers nor the resolution applicant |
| NOIDA's role | Commercial lessor collecting premium | A local authority whose essential purpose is development, not mere profit |
| Scope of ruling | Homebuyers sought relief from penalties | Decided in the peculiar facts and circumstances of the case |
Why did the Court refuse to pass the penalty to buyers?
Three strands run through the reasoning. First, purpose: the Court said the lease and acquisition were for development of an urban and industrial township, including housing, and that while NOIDA is involved in a commercial venture, it cannot be divorced from the welfare purpose every local authority pursues, "without a mere profit motive."
Second, who caused the delay: in paragraph 15, the Court said it was proper that NOIDA waive the penalty charges "since it is neither the default of the homebuyers nor the default of the SRA, which led to the delay," and that the homebuyers and the resolution applicant were being "penalised for past sins of the Corporate Debtor, which cannot be allowed."
The Court also looked at who had kept the project alive. In paragraph 13 it observed that the homebuyers had pooled money to carry on the project during the insolvency, that a resolution applicant had come in, and that the plan was approved by a committee made up of the homebuyers alone. It said the essential purpose of development would fail if NOIDA insisted on default charges.
Third, the point of the penalty: paragraph 14 says time extension charges are meant to penalise a defaulting developer and deter delay, but here the defaulting developer was out of the picture and the half-built project could be completed only if the resolution plan was carried out.
How narrow is the ruling?
Narrow on its face. Paragraph 16 orders that "in the peculiar facts and circumstances of the case", the penalty imposed by NOIDA for delay, now sought from the resolution applicant and the homebuyers, cannot be validly imposed. The Court did not declare a general rule that all authority dues are excluded from insolvency costs, and it did not decide what happens to other kinds of land dues.
For a buyer, that means two things. The reasoning is persuasive support in a similar dispute, especially where buyers have funded completion themselves. But each project will turn on its own lease terms, authority rules and resolution plan.
What does this mean for a Bengaluru buyer?
Ask about the land before you book. If a project sits on land leased or allotted by a public authority, the lease may carry completion deadlines and charges for delay, as the NOIDA lease did. Ask the builder whether such terms exist, and read the RERA filings for the land title and encumbrances. Our guide to the declarations a promoter files with RERA explains where to look.
If your builder does go into insolvency, read the resolution plan's fine print on costs. In the Lotus case, a clause would have recovered costs above Rs 3 crore from specific towers' allottees as a super area charge unless a court held otherwise. Our guide to filing your claim in the revised Form CA covers the first step in that process.
Work through your authorised representative. In this case, it was the homebuyers' authorised representative who carried the appeal to the Supreme Court and won it.
What should you check if your project is on authority land?
- Ask the builder whether the land is leased or allotted by a public authority.
- Ask for the completion deadline and any delay charges in that lease or allotment.
- Check the RERA filing for land title, encumbrances and the declared completion date.
- If insolvency begins, file your claim and follow the authorised representative's updates.
- Read the resolution plan for clauses that pass costs on to specific allottees.
- Ask whether authority dues are being claimed as insolvency process costs.
- Take legal advice early if a cost is being shifted to buyers.
Frequently asked questions
What did the Supreme Court decide on 3 September 2026 about NOIDA's charges?
In Civil Appeal No. 3132 of 2026, the Court set aside directions to treat NOIDA's time extension charges for the Lotus Boulevard and Lotus Panache projects as insolvency process costs, held the penalty could not validly be imposed on homebuyers and the resolution applicant, and rejected NOIDA's appeal for charges up to the tenth year.
Why did the Court say homebuyers should not bear the penalty?
The Court said the delay was neither the homebuyers' default nor the resolution applicant's, and that they were being penalised for past sins of the corporate debtor, which cannot be allowed, especially as the local authority's essential concern is development of its area rather than mere profit.
Does the ruling apply to every project in insolvency?
Not automatically. The Court said it was deciding in the peculiar facts and circumstances of the case. Its reasoning may help buyers in similar disputes, especially where they funded completion, but each case will depend on the lease terms, the authority's rules and the resolution plan.
What was the Pool and Build mechanism in the Lotus projects?
According to the homebuyers' representative, buyers pooled their own resources as advance payment of the balance sale consideration during the insolvency process and carried on construction under a Pool and Build mechanism approved by the Committee of Creditors, which was made up of the homebuyers.
This guide summarises a Supreme Court judgment and is not legal advice. Consult an advocate about your own project.
Last updated 2026-11-23. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.