Builder in Insolvency? What IBBI's October 2026 Rules Change for Homebuyers
IBBI's Fifth Amendment Regulations, notified on 30 October 2026, require project-wise bank accounts and disclosures for builders in insolvency, an independent cost-to-complete study, a 66 percent CoC vote to recommend excluding projects, and resolution plans that spell out possession or refund for each allottee.
66 percent. That is the voting share the Committee of Creditors now needs to recommend that a particular real estate project be taken out of a builder's insolvency process, under rules the Insolvency and Bankruptcy Board of India notified on 30 October 2026. The Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) (Fifth Amendment) Regulations, 2026 were announced the next day in IBBI press release No. IBBI/PR/2026/18, which says the changes aim to strengthen the interests of homebuyers in the corporate insolvency resolution process.
For a Mumbai family whose builder has been admitted into insolvency, the process can feel like a black box run by bankers. The Fifth Amendment changes what the resolution professional must disclose, how a buyer's representative is chosen and heard, and what a resolution plan must promise. This guide explains the changes in buyer terms, based on IBBI's press release.
The short answer. Under regulations IBBI notified on 30 October 2026, a builder in insolvency must run a separate bank account for each real estate project, the resolution professional must put project-wise data before creditors, and an independent cost-to-complete assessment goes into the information memorandum. Resolution plans must state, project by project, how allottees' claims will be treated through possession, conveyance, refund or other means, with completion timelines. The trade-off: buyers get far better information and a stronger voice through their authorised representative, but the committee can also vote, with at least 66 percent, to recommend excluding projects, so you need to know where your project stands.
What did IBBI change on 30 October 2026?
IBBI's press release lists nine groups of changes to the regulations that govern corporate insolvency. Several are aimed squarely at builders with real estate projects. In plain terms:
Money must be tracked project by project. A separate bank account must be operated for each real estate project of the corporate debtor, and the resolution professional must place project-wise statements of receipts and payments before the Committee of Creditors at intervals the committee considers appropriate. Compliance with the fund utilisation requirements of the Real Estate (Regulation and Development) Act, 2016 must be ensured during the process. IBBI says this is meant to ensure that funds contributed for a project are used for that project.
Projects can be looked at one by one. Where a builder has several projects, the resolution professional must place project-wise information before the committee in its first meeting, including RERA registration details, stage of completion, status of possession and occupancy, and details of completed and incomplete units.
| Change | What the regulations now require | Why it matters to a buyer |
|---|---|---|
| Project bank accounts | Separate account for each real estate project; project-wise receipts and payments placed before the CoC | Your project's money can be traced separately |
| Project exclusion | CoC may, with at least 66 percent voting share, recommend excluding a project, with recorded reasons | Completed or occupied projects can be kept out of the process |
| Cost-to-complete study | Independent project-wise technical and cost assessment before expressions of interest | Bidders work from a common estimate of cost and time |
| Information memorandum | Project-wise disclosures, including the RERA account balance and allottees who have not filed claims | Buyers who missed filing still appear in the data |
| Resolution plan | Project-wise treatment of allottees' claims and timelines for completion and possession | You can see what the plan promises for your unit |
What happens to a project that is already complete or occupied?
This is the change most likely to matter to buyers who already live in their flats. Based on the project-wise information placed at the first meeting, the committee may, with at least 66 percent voting share, recommend to the Adjudicating Authority that any real estate project be excluded from the process, with recorded reasons. The resolution professional then files an application before the Adjudicating Authority with those reasons.
IBBI says this enables project-wise treatment and minimises disruption to completed and occupied projects, so that resolution efforts focus on projects that genuinely need intervention. Note the steps: the committee recommends, and the application goes to the Adjudicating Authority. A recommendation alone is not the final word, so a buyer in a completed tower should follow what happens to that application.
How will buyers know what it really costs to finish their tower?
Through a new independent assessment. With the committee's prior approval, the resolution professional must appoint one or more suitably qualified and independent professionals to carry out a project-wise technical and cost-to-complete assessment before inviting expressions of interest. It covers the physical status of construction, regulatory approvals, sold and unsold inventory, estimated completion costs, funding requirements, timelines and risks affecting completion.
The assessment forms part of the information memorandum given to prospective resolution applicants, and its cost forms part of the insolvency resolution process costs. IBBI's stated aim is a common and credible baseline on the cost and time needed for completion, which should lead to more realistic bids.
The information memorandum itself must now carry detailed project-wise data: sanctioned, completed and under-construction units; sold and unsold inventory; construction progress, including common areas and amenities; statutory approvals; permissible development area; encumbrances and lender-wise charges; pending litigation and statutory dues; regulatory status including pending RERA proceedings, penalties and complaints; and the balance in the designated RERA bank account.
What if you never filed a claim with the resolution professional?
You are not invisible. The press release says the information memorandum must include details of allottees whose claims are reflected in the builder's books of accounts or in RERA records but who have not submitted claims to the resolution professional. It must also disclose, project by project, the allottees seeking possession, refund, conveyance or other relief, and the number who have not indicated any preference.
Every resolution plan must then provide for the treatment of allottees who have not submitted claims but whose details are included in the information memorandum. That is a real protection, but it is not a reason to stay silent. Filing a claim and stating your preference, possession or refund, puts your choice on record. If your builder is delayed but not yet in insolvency, our guide on your options under RERA Section 18 when possession is delayed covers the remedies before it gets that far.
How does the amendment strengthen the homebuyers' representative?
The press release refers to authorised representatives of creditors in a class, such as homebuyers. Under the amendment, the choice of authorised representatives offered to a class must come with their brief profiles and information on their roles and duties. Authorised representatives must submit minutes of their meetings with creditors to the resolution professional, who places them before the committee at its next meeting. The minutes of committee meetings must also record the views, concerns and opinions expressed by the representatives on behalf of the class.
After a plan is approved, the monitoring committee that oversees its implementation must, where the builder has real estate projects, include the class's authorised representative or another representative of allottees chosen by majority vote. It must also include representatives of the concerned RERA and the competent authority, wherever applicable and subject to their agreement.
Can you get possession of your flat during insolvency?
The amendment makes it easier. The committee may approve homebuyers' requests for handover of possession of their plots, apartments or buildings, and for facilitation of registration under Regulation 4E, either one by one or through an in-principle approval that authorises the resolution professional to process all such requests as and when they are received during the process. IBBI says this avoids seeking fresh committee approval for each request.
Every resolution plan must also set project-wise, phase-wise or tower-wise timelines for completion and delivery of possession, as applicable, with periodic progress reporting to the monitoring committee. The plan must specify treatment of allottees' claims through possession, execution of conveyance deeds, registration or transfer of title, refund or other appropriate means.
Insolvency is not the only route by which a home changes hands under financial stress; if you are considering a bank auction instead, our guide to SARFAESI auction deadlines explains a different set of rules.
What should a Mumbai homebuyer do if the builder enters insolvency?
- Track your builder's insolvency status and note the resolution professional's contact details.
- Submit your claim to the resolution professional with your agreement and payment proof.
- State clearly whether you want possession, refund or conveyance of your unit.
- Check your project's RERA registration and the stage of completion recorded for it.
- Choose the authorised representative after reading the profiles now provided with the options.
- Ask your representative for the minutes of meetings and the committee's views on your project.
- Read the resolution plan's project-wise timelines and the treatment proposed for your unit.
Frequently asked questions
When did IBBI notify the Fifth Amendment to the CIRP Regulations?
IBBI notified the Insolvency Resolution Process for Corporate Persons (Fifth Amendment) Regulations, 2026 on 30 October 2026, according to its press release No. IBBI/PR/2026/18 dated 31 October 2026. The release says the amended regulations are available on the Board's website at www.ibbi.gov.in for anyone who wants the full text.
Can a completed housing project be excluded from a builder's insolvency?
The Committee of Creditors may, with at least 66 percent voting share, recommend to the Adjudicating Authority that a real estate project be excluded from the process, with recorded reasons. The resolution professional then files an application with those reasons. IBBI says this minimises disruption to completed and occupied projects.
What happens to homebuyers who did not file a claim in insolvency?
The information memorandum must include allottees whose claims appear in the builder's books or RERA records but who did not submit claims, and every resolution plan must provide for their treatment. Filing a claim and stating your preference for possession or refund still puts your choice on record and is the safer course.
Can a homebuyer get possession during the insolvency process?
Yes, with the committee's approval. Under the amendment, the Committee of Creditors may approve homebuyers' requests for handover of possession and facilitation of registration under Regulation 4E individually, or grant in-principle approval authorising the resolution professional to process all such requests as they arrive during the process.
This guide summarises IBBI's press release on the Fifth Amendment Regulations, 2026 and is not legal advice. Read the notified regulations and take advice on your own claim.
Last updated 2026-11-23. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.