A Shamirpet Flat That Was Never Built: What the Rs 22.22 Lakh TG RERA Refund Teaches Buyers

A Shamirpet buyer paid Rs 22.22 lakh for a pre-launch flat that was never registered or built. TG RERA ordered a full refund with 10.85% interest. Here is what the order means for Hyderabad buyers weighing a discounted pre-launch deal.

Legal & Documentation
Updated on
November 28, 2026
12 min read

Rs 20.79 lakh. That was the price on the agreement Vinukonda Ravi signed on 11 October 2021 for a flat in Happy Homes 2 at Shamirpet, sold under what the developer called a limited pre-launch offer. The promise was possession within 36 months plus a six-month grace period, and rent of Rs 10 per square foot every month until handover. When the developer moved him to a different flat, he paid another Rs 1.43 lakh. Five years later, the total stood at Rs 22.22 lakh and there was no building. On 17 November 2026, Siasat reported that TG RERA had ordered every rupee returned, with interest at 10.85% a year.

The short answer. TG RERA ordered Bhuvanteza Infra Projects Pvt Ltd to refund the full Rs 22.22 lakh with interest at 10.85% a year from the date of each payment, which the report describes as SBI MCLR of 8.85% plus 2% under Rule 15 of the Telangana RERA Rules. The developer has 60 days to comply or face penalties under Section 63. The project was never registered, had no statutory approvals and no lawful construction, according to the Authority's findings as reported. The trade-off for every buyer looking at a pre-launch discount is stark: the lower price comes with the risk that your money sits in a project that legally should not have been sold, and recovering it can take years even when you win.

What exactly happened to the Shamirpet buyer?

The buyer paid for a flat in a project that never got off the ground. According to the Siasat report, which cites Newsmeter, the agreement for sale for flat 514-F in Happy Homes 2 (Phase 2) at Shamirpet was signed on 11 October 2021 at Rs 20.79 lakh. The developer later reassigned him to flat 507-C in Happy Homes Phase 1, citing COVID-19, and collected an extra Rs 1.43 lakh for the change.

The agreement promised possession within 36 months with a six-month grace period, and a monthly rent of Rs 10 per square foot until handover. The buyer alleged that the developer dropped the rent clause without his consent. TG RERA found that the developer had neither obtained statutory approvals nor begun lawful construction, and concluded that possession could not be given. The developer did not appear before the Authority and did not contest the allegations, the report says.

This is not the first time this developer has come before a forum. PropNewz earlier covered a Telangana High Court matter involving Bhuvanteza flat buyers and an arbitration notice. The Siasat report adds that the company had already been penalised over an unregistered project in Complaint No. 286 of 2024 and declared a defaulter in Complaint No. 264 of 2024.

Why did TG RERA order a full refund instead of delay interest?

Because there was nothing to wait for. Under the RERA framework, a buyer whose possession is delayed can choose to stay in the project and receive interest for every month of delay, or withdraw and take a refund. The TG RERA FAQ explains the first route: where a promoter fails to meet the time schedule, the promoter pays an allottee who does not intend to withdraw interest as specified in the Rules on all amounts paid, for every month of delay, till possession.

In the Shamirpet case, the Authority held that possession could not be given at all because the project had no approvals, no registration and no construction. The Siasat report says the refund was allowed under Section 18(1)(a), the provision covering a promoter's failure to complete or give possession. For the buyer, that turns a long wait into a money claim with a fixed deadline.

How is the 10.85% interest worked out?

The rate is tied to a public benchmark, not to what the agreement says. The TG RERA FAQ states that under Rule 15, the interest rate is the State Bank of India highest Marginal Cost of Lending Rate plus 2%. The FAQ describes it in the context of an allottee's late payment to the promoter, and the Siasat report says the same Rule 15 formula, SBI MCLR of 8.85% plus 2%, produced the 10.85% rate applied to this refund.

The interest runs from the date of each payment, not from the date of the order. That matters for anyone who paid in instalments. As simple arithmetic, every Rs 10 lakh held for one full year at 10.85% works out to Rs 1,08,500 of interest. Rs 22.22 lakh held for a year at the same rate is about Rs 2,41,087. The real figure in this case depends on when each tranche was paid, which the report does not give.

Because the benchmark moves, the rate in your own order may differ. PropNewz explained the formula in more detail in our guide to the TG RERA late payment interest rule.

Which projects in Hyderabad must be registered before they sell?

Most apartment and plotted projects of any real size. The TG RERA FAQ says a project with land area above 500 square metres needs registration even if it has fewer than eight apartments, and a project on less than 500 square metres needs registration if it has more than eight apartments. The Siasat report notes that Happy Homes 2 exceeded the 500 square metre threshold and was never registered.

Timing is the other half. The FAQ says a promoter has to register the project before starting any form of advertising, marketing, booking, selling, offering for sale or inviting people to purchase plots, apartments or buildings. It also says building or layout permission from the competent local authority must be obtained before applying for registration. A pre-launch offer, by its nature, usually arrives before one or both of these steps.

What penalty does a builder face for selling without registration?

A heavy one on paper. The TG RERA FAQ states that a promoter who fails to register is liable to a penalty of up to 10% of the estimated cost of the project under Section 59, and on continued violation, imprisonment of up to three years or a further fine of up to 10% of the estimated cost, or both. The Siasat report says the Authority flagged liability under Section 59 in this case.

A penalty paid to the state does not put money back in a buyer's account, though. The refund order is what does that, and its enforcement depends on the developer complying within 60 days or the Authority acting under Section 63.

IssueWhat the buyer was toldWhat TG RERA found or orderedSource
Price and paymentsRs 20.79 lakh pre-launch priceRs 22.22 lakh paid in total, full refund orderedSiasat, 17 November 2026
Possession36 months plus six-month gracePossession could not be givenSiasat, 17 November 2026
RegistrationSold as a limited offerNever registered despite exceeding 500 sq mSiasat; TG RERA FAQ on thresholds
InterestRs 10 per sq ft monthly rent clause10.85% a year from each payment dateSiasat; TG RERA FAQ on Rule 15
DeadlineNone given to buyer60 days, else Section 63 penaltiesSiasat, 17 November 2026

What should you check before paying for a pre-launch flat?

Check that the project legally exists before you check the price. A pre-launch discount is only worth something if the project can be registered, built and delivered. Use this list before you hand over a token, a cheque or a transfer.

  1. Search the project name and the promoter's name on the TG RERA website, which the FAQ says displays all registered projects.
  2. Ask for the building or layout permission number and the approving body, since the FAQ says local authority permission must come before registration.
  3. Check whether the land area is above 500 square metres or the project has more than eight units, the thresholds the FAQ uses for mandatory registration.
  4. Read the agreement for the exact possession date and grace period, and note them in writing.
  5. Treat any rent or assured payment clause as a contract term you may have to enforce, as the Shamirpet buyer alleged his was dropped.
  6. Keep a dated record of every payment, because Rule 15 interest in a refund runs from the date of each payment.
  7. Search the promoter's name in reported TG RERA orders and court news before committing, since past complaints are public.

Where do Hyderabad buyers file if a project stalls?

With TG RERA, and the FAQ explains why the route matters. It says civil courts are barred under Section 79 from matters the Authority or the Appellate Tribunal can decide. It also says Section 71 allows a complainant to withdraw a complaint on matters under Sections 12, 14, 18 and 19 from the consumer forum and file it with the Authority. The FAQ adds that complaints should be disposed of as expeditiously as possible and not later than sixty days from filing, and where that is not possible, the Authority must record its reasons.

The same FAQ says an allottee whose agreement was executed before an ongoing project was registered can still file a complaint about a registered project. For an unregistered project like Happy Homes 2, the Shamirpet order shows the Authority will still hear a buyer and order a refund, with Section 3 and Section 59 in play.

Frequently asked questions

How much interest did TG RERA order on the Shamirpet refund?

According to the Siasat report of 17 November 2026, TG RERA ordered the full Rs 22.22 lakh refunded with interest at 10.85% a year from the date of each payment. The report says this equals SBI MCLR of 8.85% plus 2%, applied under Rule 15 of the Telangana RERA Rules.

Which Hyderabad projects must be registered with TG RERA?

The TG RERA FAQ says a project with land area above 500 square metres must register even with fewer than eight apartments, and a project on less than 500 square metres must register if it has more than eight apartments. Search the project and promoter on the TG RERA website before paying.

How long does the builder have to pay the Shamirpet refund?

The Siasat report says the developer was given 60 days to comply, failing which it faces penalties under Section 63 of the RERA Act. The complaint was disposed of with no order as to costs. If a refund order is not honoured in time, the buyer can return to TG RERA.

Can I appeal or go to consumer court instead of TG RERA?

The TG RERA FAQ says an appeal against a TG RERA order lies to the Appellate Tribunal within sixty days under Section 43(5). It also says Section 71 lets a complainant withdraw a complaint on matters under Sections 12, 14, 18 and 19 from the consumer forum and file it with the Authority.

The Shamirpet buyer did everything a hopeful buyer does: signed an agreement, paid on schedule, accepted a changed flat. What he could not see from the brochure was that the project had no registration and no approvals. Those two facts take minutes to check on the TG RERA portal, and they are worth checking before any discount looks attractive.

Last updated 2026-11-28. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.