Reading a RERA project page in Bengaluru: registration timeline, validity and quarterly updates
A RERA project page is more than a registration number. Section 5 sets a 30 day decision and deemed registration, ties validity to the promoter's declared completion period, and Section 11(1) requires quarterly updates on bookings, approvals and status. Here is how Bengaluru buyers can read it.
Open a registered project's page on a RERA portal and one of the dates you will see is the registration validity: valid till a certain month and year. It is tempting to read that as the promised possession date. Under the Real Estate (Regulation and Development) Act, 2016, it is something more specific, and the page around it is meant to change every quarter.
This guide explains how registration is granted under Section 5, what the validity date actually reflects, and what Section 11(1) requires the promoter to keep updating on the project's web page. For a Bengaluru buyer comparing an under construction project with a few years left to run, those quarterly updates are the closest thing to an official progress report.
The short answer. Section 5(1) of the RERA Act requires the authority to grant or reject a registration application within 30 days, and Section 5(2) says that if it does neither, the project is deemed registered and a registration number and login must be provided within seven days after that period. Section 5(3) makes the registration valid for the completion period the promoter declared in its Section 4 affidavit. Section 11(1) then requires the promoter to create a web page on the authority's website and update, every quarter, the number and types of units booked, garages booked, approvals taken and pending after the commencement certificate, and the status of the project. The trade-off: these pages give you regular, regulator hosted data, but they depend on the promoter's own entries, so treat them as a starting point and verify on site.
How quickly must a RERA authority decide on registration?
According to the Gazette of India text of the RERA Act, Section 5(1) says the authority shall, within 30 days of receiving an application under Section 4(1), either grant registration and provide a registration number with a login ID and password for the promoter to create the project web page, or reject the application for reasons recorded in writing. Its proviso says no application shall be rejected unless the applicant has been given an opportunity of being heard.
Section 5(2) covers the case where the authority does neither. The project is then deemed to have been registered, and the authority must, within seven days of the expiry of the 30 day period, provide a registration number and login details. Deemed registration is a fallback for regulatory delay, and either way the project ends up with a registration number. For buyers, the practical point is simple: a project marketed as "RERA applied" is not the same as a registered project, and Section 3(1) bars a promoter from advertising, marketing, booking or selling in a planning area without registration.
What does the registration validity date actually mean?
Section 5(3) says the registration shall be valid for the period declared by the promoter under Section 4(2)(l)(C), which is the time period within which the promoter undertakes to complete the project or phase. So the validity date is tied to the promoter's own declared completion timeline.
When can the registration be extended?
Section 6 allows the authority to extend the registration on the promoter's application due to force majeure, in the form and on payment of the fee specified by regulations. The explanation defines force majeure narrowly, as a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the project.
The first proviso to Section 6 adds a separate power. The authority may, in reasonable circumstances, without default on the part of the promoter, based on the facts of each case and for reasons recorded in writing, extend the registration for such time as it considers necessary, which shall in aggregate not exceed one year. The second proviso says no extension application shall be rejected without giving the applicant an opportunity of being heard.
If you see an extended validity date on a project page, ask the promoter what the extension was granted for, and check how it lines up with the possession date in your agreement for sale. An extension of registration is a regulatory step, and your possession date and remedies are set by your agreement for sale and the Act, so check both.
What if a registration is revoked?
Section 7(1) allows the authority, on a complaint, suo motu or on the recommendation of the competent authority, to revoke a registration if it is satisfied that the promoter has defaulted on anything required under the Act, rules or regulations, violated the terms of the competent authority's approval, or is involved in unfair practices or irregularities. The explanation lists examples of unfair practice, including falsely representing that the promoter has an approval or affiliation it does not have, and making false or misleading representations about the services offered.
Revocation is one more reason to check the project page periodically rather than once. A registration that was valid at booking can change status later, and the page is where that change should show.
What must the promoter update on the project page every quarter?
Section 11(1) requires the promoter, on receiving its login under Section 5, to create a web page on the authority's website and enter all details of the project provided under Section 4(2), for public viewing. It specifically includes details of the registration granted; a quarterly up to date list of the number and types of apartments or plots booked; a quarterly up to date list of the number of garages booked; a quarterly up to date list of approvals taken and approvals pending after the commencement certificate; the quarterly up to date status of the project; and other information specified by regulations.
| Section | What the Act requires | How a buyer can use it |
|---|---|---|
| 5(1) and 5(2) | Grant or rejection within 30 days; deemed registration if neither, with number and login within seven days | Ask for the registration number, not an application reference |
| 5(3) and 6 | Validity equals the declared completion period; extension on force majeure application | Compare validity and any extension with your agreement's possession date |
| 11(1)(b) and (c) | Quarterly list of units and garages booked | Gauge how much of the project is sold |
| 11(1)(d) | Quarterly list of approvals taken and pending after the commencement certificate | Spot approvals still outstanding |
| 11(1)(e) | Quarterly status of the project | Track progress over several quarters, not just one |
What must advertisements and the sales office show?
Section 11(2) says the promoter's advertisement or prospectus shall prominently mention the website address of the authority where the registered project's details are entered, and include the registration number. If a hoarding or a social media post shows neither, ask why before you visit.
The advertisement also matters later. Section 12 says that a person who makes an advance or deposit on the basis of information in a notice, advertisement or prospectus, or on the basis of a model apartment, and sustains loss or damage because of an incorrect or false statement in it, shall be compensated by the promoter as provided under the Act. Keep copies of the advertisements and brochures you relied on, with the dates you saw them.
Section 11(3) adds what the promoter must make available at the time of booking and issue of the allotment letter: the sanctioned plans, layout plans and specifications approved by the competent authority, by display at the site or another place specified by regulations, and the stage wise time schedule of completion, including provisions for civic infrastructure such as water, sanitation and electricity. Ask to see both at the site office, and photograph them for your records.
How do you read the quarterly updates sensibly?
One quarter's figures tell you little. Several quarters, read in sequence, tell you whether bookings are moving, whether pending approvals are being cleared and whether reported construction status is advancing. If the status has barely changed across several updates while the completion date stays fixed, that is a question to put to the promoter in writing. Keep your own dated copies of each update, since the page itself changes over time.
The entries are made by the promoter. A site visit, a conversation with existing buyers and the documents in the registration file are the natural cross checks. Our guide to what a RERA registration file must contain covers those documents, and our explainer on promoter declarations under Section 4 explains the completion period affidavit behind the validity date.
- Record the registration number and the registration validity date shown on the project page.
- Check whether the validity has been extended, and ask the promoter for the reason.
- Download the last four quarterly updates and compare the bookings and status entries.
- List any approvals shown as pending after the commencement certificate.
- Confirm that the project's advertisements carry the registration number and the authority's website.
- At the site office, ask to see the displayed sanctioned plans and the stage wise schedule.
- Compare the registration validity with the possession date in your agreement for sale.
Frequently asked questions
How long does a RERA authority take to register a project?
Section 5(1) of the RERA Act requires the authority to grant or reject a registration application within 30 days of receipt. If it does neither, Section 5(2) says the project is deemed registered, and a registration number and login must be provided within seven days after the 30 day period.
Is the RERA registration validity date the possession date?
Not exactly. Section 5(3) of the RERA Act makes registration valid for the completion period the promoter declared under Section 4(2)(l)(C). Section 6 allows extension on force majeure. Your possession date is in your agreement for sale, so compare the two.
What must a builder update on the RERA website every quarter?
Section 11(1) of the RERA Act requires quarterly up to date lists of apartments or plots booked and garages booked, approvals taken and pending after the commencement certificate, and the status of the project, along with registration details and other information specified by regulations.
Must a project advertisement show the RERA registration number?
Yes. Section 11(2) of the RERA Act requires the promoter's advertisement or prospectus to mention prominently the website address of the authority where all the project's details are entered, and to include the registration number obtained from the authority. Check both before visiting.
Last updated 2026-11-26. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.