Your right to know: construction schedule, plans and handover documents under RERA

Bengaluru buyers have specific RERA rights to information: approved plans and specifications, the stage wise construction schedule including water and power, plans displayed at booking, and documents after possession. Here is what Sections 19 and 11(3) say and how to ask.

Buying Guides
Updated on
November 26, 2026
12 min read

Eighteen months into an under construction purchase in Bengaluru, the site looks busy but the tower is no higher than it was at Diwali. You email the builder's customer care asking for the construction schedule and an update on the water connection. The reply is a cheerful photo of the lobby mock-up. Is that all you are entitled to?

It is not. The Real Estate (Regulation and Development) Act, 2016 gives allottees specific rights to information, some at the time of booking, some during construction and some after possession. This guide sets out what Sections 19(1) to 19(3), 19(5) and 11(3) say, and how to ask for that information in a way that leaves a useful paper trail.

The short answer. Section 19(1) of the RERA Act entitles an allottee to information on sanctioned plans, layout plans and specifications approved by the competent authority, and other information provided in the Act, rules, regulations or the agreement for sale. Section 19(2) entitles the allottee to know the stage wise time schedule of completion, including provisions for water, sanitation, electricity and other agreed amenities. Section 11(3) requires the promoter to make the sanctioned plans and the stage wise schedule available at booking, and Section 19(5) entitles the allottee to the necessary documents and plans, including of common areas, after possession. The trade-off: these rights are clear, but they work best when you ask early, in writing, and keep the answers.

What information can a buyer ask for during construction?

According to the Gazette of India text of the RERA Act, Section 19(1) says the allottee shall be entitled to obtain information relating to sanctioned plans, layout plans along with specifications approved by the competent authority, and such other information as provided in the Act, the rules and regulations, or the agreement for sale signed with the promoter.

Section 19(2) adds that the allottee shall be entitled to know the stage wise time schedule of completion of the project, including the provisions for water, sanitation, electricity and other amenities and services as agreed between the promoter and the allottee under the agreement for sale. A lobby photograph is not a stage wise schedule. If you ask for one, ask for it by reference to Section 19(2).

What must the promoter give you at booking?

Section 11(3) says the promoter, at the time of booking and issue of the allotment letter, shall be responsible to make available to the allottee the sanctioned plans, layout plans and specifications approved by the competent authority, by display at the site or such other place as specified by regulations, and the stage wise time schedule of completion, including provisions for civic infrastructure such as water, sanitation and electricity.

This is the baseline for everything that follows. If you photograph the displayed plans and keep a copy of the stage wise schedule at booking, you will be able to tell later whether the project is on track and whether any change has been made. Our guide to reading a RERA project page explains the quarterly updates that complement these documents.

Right or dutyProvisionWhen it appliesWhat to ask for
Plans and specifications at bookingSection 11(3)(a)Booking and allotment letterSight of the displayed sanctioned plans and specifications
Stage wise schedule at bookingSection 11(3)(b)Booking and allotment letterA copy of the schedule, including water, sanitation and electricity
Information on approved plansSection 19(1)Any time as an allotteeSanctioned and layout plans with specifications
Completion scheduleSection 19(2)During constructionThe current stage wise schedule and amenities timeline
Documents after possessionSection 19(5)After physical possessionNecessary documents and plans, including of common areas

What about possession and documents after handover?

Section 19(3) says the allottee shall be entitled to claim possession of the apartment, and the association of allottees to claim possession of the common areas, as per the declaration given by the promoter under Section 4(2)(l)(C), which is the promoter's declared completion timeline. Section 19(5) says the allottee shall be entitled to have the necessary documents and plans, including those of common areas, after the promoter hands over physical possession.

Section 17(2) places the matching duty on the promoter to hand over the necessary documents and plans, including common areas, to the association of allottees or the competent authority, as per local laws. In practice, individual owners and the association should both keep track of what has been received. Once you have the keys, Section 14(3) also gives you five years from possession to notify structural or workmanship defects, which the promoter must rectify without further charge within 30 days.

What if the plans change after you book?

The documents you receive under Sections 11(3) and 19(1) become the reference point for any change. Section 14(2)(i) says that once the sanctioned plans, layout plans, specifications and the nature of fixtures, fittings, amenities and common areas have been disclosed to a buyer, the promoter shall not make additions or alterations to them in respect of that buyer's apartment without the buyer's previous consent. Minor changes requested by the allottee, or needed for architectural and structural reasons and verified by an authorised architect or engineer, are allowed after proper declaration and intimation to the allottee.

Section 14(2)(ii) requires the previous written consent of at least two thirds of the allottees, other than the promoter, for other alterations or additions to the sanctioned plans of the buildings or common areas. If you never received or kept the original plans, it is much harder to show that something has changed.

Can you ask how project money is being used?

The Act builds in financial checks that sit behind your information rights. Section 4(2)(l)(D) requires the promoter to declare that 70 percent of amounts realised from allottees will be deposited in a separate account in a scheduled bank to cover construction and land cost, with withdrawals in proportion to the percentage of completion and certified by an engineer, an architect and a chartered accountant in practice. As TG RERA's circular of 18 March 2025 summarises, the same clause requires the promoter's accounts to be audited within six months after the end of every financial year, with verification that collections for a project were used for that project.

In Telangana, for example, that circular requires promoters to submit quarterly progress reports and an annual audit report on the statement of accounts in Form 7, with delay fees for late filing. For a Bengaluru project, ask the promoter which equivalent filings it makes to the Karnataka regulator, and ask your association to track whether they are up to date.

How should you ask, and what if the builder does not answer?

Write, rather than call, so that there is a dated record of what you asked and when. A short email or letter that names the provision, lists the specific documents you want, and asks for a reply by a reasonable date creates a record. Keep the promoter's reply, or note the absence of one.

If the promoter does not respond, Section 31(1) lets any aggrieved person file a complaint with the authority or adjudicating officer for any violation of the Act, rules or regulations, and its explanation says a person includes an association of allottees. Section 35(1) separately lets the authority, on a complaint or suo motu, call on a promoter to furnish information or explanations. A complaint that attaches your unanswered requests is easier to act on than one that relies on memory.

Why does the stage wise schedule matter so much?

The stage wise schedule links the information rights to the money. Section 19(6) requires an allottee who has signed an agreement for sale to make payments in the manner and within the time specified in that agreement. Where your payment plan is tied to construction stages, knowing where the project stands against its schedule helps you check that each demand matches real progress.

It also helps you judge delay. If the stage wise schedule shows the structure should be complete by a certain quarter and it is not, you have an early warning, long before the possession date in your agreement. Our explainer on the buyer's side of RERA under Section 19 covers the payment duties that run alongside these rights.

  1. At booking, photograph the displayed sanctioned plans and ask for a copy of the stage wise schedule.
  2. File both with your allotment letter and agreement for sale.
  3. Every quarter, compare the schedule with the project's RERA updates and a site visit.
  4. Before paying a stage linked demand, ask for confirmation that the stage is complete.
  5. Request information in writing, citing Section 19(1) or 19(2), and keep the replies.
  6. After possession, ask for the documents and plans covered by Section 19(5).
  7. If requests go unanswered, consider a complaint under Section 31, ideally through your association.

Frequently asked questions

Can I ask my builder for the construction schedule under RERA?

Yes. Section 19(2) of the RERA Act entitles an allottee to know the stage wise time schedule of completion of the project, including provisions for water, sanitation, electricity and other amenities and services agreed in the agreement for sale. Ask for it in writing and keep the reply.

What must a builder show me at the time of booking?

Section 11(3) of the RERA Act requires the promoter, at booking and issue of the allotment letter, to make available the sanctioned plans, layout plans and specifications approved by the competent authority, by display at the site or as specified, and the stage wise time schedule of completion.

Am I entitled to building documents after possession?

Yes. Section 19(5) of the RERA Act says the allottee is entitled to have the necessary documents and plans, including those of common areas, after the promoter hands over physical possession. Section 17(2) separately requires handover of documents and plans to the association.

What can I do if the builder ignores my information request?

Section 31(1) of the RERA Act lets any aggrieved person, including an association of allottees, complain to the authority or adjudicating officer about violations. Section 35(1) lets the authority call on a promoter to furnish information. Attach your written requests to any complaint.

Last updated 2026-11-26. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.