OC Is Not a Formality: Casa Grande Lorenza Ruling and Delay Interest for Bengaluru Buyers
The Karnataka Real Estate Appellate Tribunal held that an occupancy certificate is not a mere formality, awarded a Casa Grande Lorenza buyer interest at SBI MCLR plus 2 percent from July 2022 to August 2025, and rejected the developer's default claim. What Bengaluru buyers should check.

On 7 May 2019, a buyer signed for flat C-305 at Casa Grande Lorenza in Bengaluru for Rs 67,20,532 and went on to pay Rs 71,52,237. The developer obtained an occupancy certificate from BBMP on 28 January 2022, then sent a termination notice claiming Rs 4,97,164 was unpaid. BBMP cancelled the certificate in July 2023, the High Court set that aside in August 2025, and on 3 October 2026 the Karnataka Real Estate Appellate Tribunal settled what the certificate's dates mean for the buyer's delay interest.
The short answer. As reported by LiveLaw, the Tribunal held that "the issuance of an occupancy certificate by the competent authority is not a mere procedural formality", recognised the certificate's benefit only from 5 August 2025, and awarded interest at SBI MCLR plus 2 percent a year on Rs 71,52,237 from 16 July 2022 to 5 August 2025. The developer must pay the interest, execute the sale deed and hand over possession within 30 days. The trade-off: the buyer won three years of interest and rejection of the default claim, but the Tribunal started the interest from the extended deadline of 15 July 2022 rather than the original October 2020 date.
What did the Tribunal decide in the Casa Grande Lorenza case?
It dismissed the developer's appeal and partly allowed the buyer's. In M/s Casa Grande Garden City Builders Pvt. Ltd. versus Virupakshappa Irappa Bagewadi and a connected appeal, numbered K-REAT 30/2026 and 36/2026, the bench of Chairperson Justice J.M. Khazi and Judicial Member Santhosh Kumar Shetty N. rewrote the interest period that K-RERA had set, LiveLaw reports.
K-RERA had directed delay interest from 15 October 2020 to 28 January 2022, the date the certificate was first issued, and possession. The Tribunal instead awarded interest from 16 July 2022 to 5 August 2025, at SBI MCLR plus 2 percent a year on the full Rs 71,52,237 paid. Within 30 days, the developer must pay the interest, execute the registered sale deed and hand over possession; if payment is not made, further interest at the same rate runs on the principal from the judgment date until realisation.
The rate is worth understanding. SBI MCLR plus 2 percent is a floating benchmark, so the interest due changes as SBI's MCLR changes over the period. If you are working out what a similar award might be worth, use the rate applicable for each stretch of the period rather than a single figure, or ask your lawyer to prepare the calculation.
The Tribunal rejected the developer's claim that the buyer had defaulted. It relied on payment receipts and a 2 February 2021 email, produced by the developer itself, stating that no balance was due.
Why does the date of an occupancy certificate matter so much?
Because it marks when lawful occupation becomes possible, and therefore when the delay ends. The Tribunal recognised the certificate's benefit for lawful, compliant possession only from 5 August 2025, not from 28 January 2022, LiveLaw reports, quoting the order: "In the absence of any material establishing that the violations had been rectified prior to 05.08.2025".
The 5 August 2025 date comes from the certificate's history. BBMP cancelled the certificate on 1 July 2023 after the buyer's brother approached it. On 23 August 2025, the Karnataka High Court set aside the cancellation, noting BBMP's 5 August 2025 affidavit that there were no deviations at that point.
The Real Estate (Regulation and Development) Act, 2016 defines the document in Section 2(zf) as a certificate issued by the competent authority permitting occupation of any building under local laws, which has provision for civic infrastructure such as water, sanitation and electricity. A certificate that exists on paper while violations remain unrectified did not, in the Tribunal's view, end the buyer's delay.
| Date | Event, as reported | Effect on the buyer |
|---|---|---|
| 28 January 2022 | BBMP issues occupancy certificate | Benefit not recognised from this date |
| 15 July 2022 | Final extended possession date | Interest starts the next day |
| 1 July 2023 | BBMP cancels the certificate | Lawful occupation in question |
| 5 August 2025 | BBMP affidavit of no deviations | Interest period ends |
| 3 October 2026 | Tribunal order | Pay interest, sale deed and possession in 30 days |
Why did the interest start in July 2022, not October 2020?
Because the possession deadline had been extended. LiveLaw reports that possession was due by 15 October 2020 and was extended to a final date of 15 July 2022: a nine-month COVID-19 extension, followed by a 12-month extension at the developer's request. The Tribunal's award runs from the day after that final date.
That is the trade-off for this buyer. K-RERA's order had counted interest from 15 October 2020; the Tribunal's counting starts later but runs much longer, to 5 August 2025. Buyers should check the extensions recorded for their own project, because they can move the start date of any interest claim.
Extensions come from different places: a regulator's general relief, an application by the developer, or a clause in the agreement. Ask which applies to your project and whether you were told at the time. Where an extension was granted at the developer's request, the reasons recorded in it may matter later if you need to argue about who caused the delay.
The Tribunal also drew a line on other litigation: according to LiveLaw, it asked whether proceedings before other forums directly and legally affected the promoter's obligation to complete and hand over the unit before letting them shape the delay-interest period. That principle cuts against developers who point to unrelated litigation to excuse delay.
What does this ruling mean for Bengaluru buyers waiting on possession?
It means the certificate's validity, not just its existence, can decide your claim. If an occupancy certificate is cancelled, challenged or issued while deviations remain, ask when the building actually became lawfully occupiable, because that is the date the Tribunal used here.
It also means a termination notice is not the last word. The Act limits when a promoter can cancel. Section 11(5) says the promoter may cancel the allotment only in terms of the agreement for sale, and its proviso lets the allottee approach the Authority for relief if aggrieved by a cancellation that is not in accordance with the agreement, unilateral and without sufficient cause. In this case, the developer's claim of Rs 4,97,164 unpaid did not survive scrutiny of its own records.
It also means paper trails win cases. The developer's own email saying no balance was due defeated its termination notice. Keep every statement of account, receipt and email in which the developer confirms what you owe.
A related Bengaluru ruling this month shows the same theme from another angle: our report on the Raffles Park occupancy certificate cancellation covers a case where the High Court upheld cancelled certificates. Our explainer on OC versus CC under RERA sets out the definitions.
What should you check if your building's OC is disputed?
Build a clear timeline and keep the documents that support each date. The checklist below follows the issues the Tribunal weighed.
- Note the original possession date in your agreement and every extension, with the reason and the document that records it.
- Get a copy of the occupancy certificate and its date of issue, and ask whether it has ever been suspended, cancelled or challenged.
- If the certificate was cancelled or restored, collect the orders and any affidavit that states when deviations were cleared.
- Keep every receipt and statement of account, especially any message from the developer confirming no balance is due.
- Respond in writing to any termination or demand notice you dispute, attaching your payment proof.
- Calculate the interest period from the day after the final possession date to the date lawful possession became possible.
- File your complaint with copies of all these documents, since the Tribunal relied on them to set the dates.
What duties does the buyer have once a valid OC is in place?
Take possession within two months. Section 19(10) of the RERA Act, which the Tribunal cited, says every allottee shall take physical possession of the apartment within a period of two months of the occupancy certificate issued for it.
That duty interacts with disputes like this one. If the certificate is in question, the date from which the two months run may itself be disputed, which is another reason to keep the certificate's history documented. Our guide on taking possession within two months of the OC explains the rule.
Section 19(11) adds that every allottee shall participate towards registration of the conveyance deed. In this case, the Tribunal directed the developer to execute the registered sale deed within 30 days, so the buyer's role is to be ready with the documents and stamp duty for registration.
Thirty days passes quickly. Line up your identity documents, the agreement, payment proofs and any loan sanction papers now, and ask your lender in advance what it needs for registration and disbursal. If the developer misses the 30-day window, the order provides for further interest on the principal from the judgment date until realisation, as reported.
Frequently asked questions
What did the Karnataka Tribunal decide in the Casa Grande Lorenza case?
As reported by LiveLaw, the Tribunal dismissed the developer's appeal, partly allowed the buyer's, and awarded interest at SBI MCLR plus 2 percent a year on Rs 71,52,237 from 16 July 2022 to 5 August 2025, with the sale deed and possession to follow within 30 days.
Is an occupancy certificate a mere formality?
No, according to the Tribunal. LiveLaw quotes it as holding that the issuance of an occupancy certificate by the competent authority is not a mere procedural formality, and it recognised the certificate's benefit only from 5 August 2025, when BBMP stated there were no deviations.
Why did the buyer's default claim fail?
The Tribunal rejected the developer's claim that the buyer owed Rs 4,97,164, relying on payment receipts and a 2 February 2021 email produced by the developer itself stating that no balance was due, as reported by LiveLaw. The buyer had paid Rs 71,52,237 in total.
When must a buyer take possession under RERA?
Section 19(10) of the RERA Act says every allottee shall take physical possession of the apartment, plot or building within a period of two months of the occupancy certificate issued for it. The Tribunal cited this provision in the Casa Grande Lorenza case.
Last updated 2026-10-22. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.