Two Months After the OC: A Bengaluru Buyer's Duties on Possession, Association and Conveyance

Section 19 of the RERA Act asks allottees to take physical possession within two months of the occupancy certificate, participate in forming the association and participate in registering the conveyance deed.

Buying Guides
Updated on
October 18, 2026
12 min read
Timeline of a Bengaluru buyer's RERA deadlines after the occupancy certificate, from possession to conveyance

The email from the builder's customer care team is cheerful. The occupancy certificate for the tower has been received, the flat is ready, and the buyer is invited to complete the final payment and collect the keys. For a Bengaluru family that has waited years, it is good news. It is also the start of a new set of deadlines, some of which fall on the buyer rather than the builder.

Much of the Real Estate (Regulation and Development) Act, 2016 is about what promoters must do. But section 19 also sets out duties of allottees, and three of them apply around the time the occupancy certificate is issued: taking possession, joining the association and participating in the conveyance. This guide reads those duties as published in the Gazette of India and explains how a Bengaluru buyer can plan for them.

The short answer. Section 19(10) of the RERA Act says every allottee shall take physical possession of the apartment, plot or building within a period of two months of the occupancy certificate issued for it. Section 19(9) says every allottee shall participate towards the formation of an association or society or cooperative society of the allottees, and section 19(11) says every allottee shall participate towards registration of the conveyance deed under section 17(1). The trade-off: taking possession promptly starts the clock on the promoter's five year defect liability and lets the handover move forward, but a buyer who rushes may miss defects that are easier to raise before moving in, so a careful inspection should come first.

What does section 19(10) require?

The Gazette of India copy of the RERA Act sets out section 19(10) in one sentence. Every allottee shall take physical possession of the apartment, plot or building, as the case may be, within a period of two months of the occupancy certificate issued for the said apartment, plot or building.

Two points stand out. The trigger is the occupancy certificate for the unit, not the builder's invitation letter or a marketing date. And the duty is to take physical possession, which is the act that starts several other clocks under the Act.

The Act's text does not itself list a consequence for missing the two month window, so the practical effect will depend on the agreement for sale and the facts. A buyer who cannot take possession within two months should say so in writing with reasons, and keep a record.

Infographic of what taking possession sets running for a Bengaluru buyer, from defect liability to documents
Possession starts the five year defect window and entitles you to the necessary documents and plans.

Why does the date of possession matter so much?

Physical possession is the reference point for several rights and duties in the Act. Section 14(3) makes the promoter liable to rectify structural defects and defects in workmanship, quality or provision of services brought to its notice within five years from the date of handing over possession, without further charge, within thirty days. Our guide on the five year defect liability under section 14 explains that protection.

Section 19(5) entitles the allottee to have the necessary documents and plans, including those of common areas, after physical possession is handed over. And section 11(4)(g) requires the promoter to pay all outgoings until it transfers physical possession of the real estate project to the allottees or the association of allottees.

The table below sets out how possession and the occupancy certificate connect to other provisions.

ProvisionWhat it saysLinked to
Section 19(10)Allottee to take physical possession within two monthsOccupancy certificate for the unit
Section 14(3)Five year defect liability, rectify within thirty daysDate of handing over possession
Section 19(5)Allottee entitled to necessary documents and plansAfter physical possession
Section 11(4)(g)Promoter pays all outgoingsUntil physical possession is transferred
Section 17(1) provisoConveyance within three months, absent local lawDate of issue of occupancy certificate

What should you inspect before taking possession?

Because possession starts the defect liability clock, and because some problems are easier to raise before furniture goes in, a careful inspection is worth the time. Walk through every room with the agreement for sale and its specifications schedule in hand. Check walls, ceilings and floors for cracks and damp, test doors and windows, run every tap and drain, and switch on every electrical point.

Compare what you see with what you were promised. Section 14(1) says the project shall be developed and completed in accordance with the sanctioned plans, layout plans and specifications approved by the competent authorities. If the flat does not match, raise it in writing before signing a possession letter that says otherwise.

Look beyond your own front door as well. Lifts, staircases, fire escapes, water tanks, open parking areas and other common areas listed in section 2(n) of the Act will pass to the association in due course, and defects there affect every owner. Note anything that looks incomplete or faulty and share it with other buyers in the tower, so that one clear written list can go to the promoter. A defect recorded in writing before possession gives everyone a dated record to work from.

Photograph everything on the day of possession and keep the dated possession letter. Our possession handover checklist for Bengaluru flats sets out what to collect.

Illustration of a house representing the association of allottees a Bengaluru buyer joins under RERA section 19(9)
The association takes over maintenance and receives the common areas, so each allottee is asked to help form it.

What does section 19(9) ask of you on the association?

Section 19(9) says every allottee of the apartment, plot or building shall participate towards the formation of an association or society or cooperative society of the allottees, or a federation of the same.

The promoter has a matching duty. Section 11(4)(e) requires the promoter to enable the formation of an association or society or cooperative society of the allottees, or a federation of the same, under the laws applicable. Its proviso says that in the absence of local laws, the association of allottees shall be formed within a period of three months of the majority of allottees having booked their plot or apartment or building in the project.

The association matters because the Act hands it important things. Section 11(4)(d) makes the promoter responsible for providing and maintaining essential services, on reasonable charges, till the taking over of the maintenance of the project by the association of the allottees. Section 17 provides for the common areas and building documents to be handed to the association. A buyer who stays out of the association has less say in how those handovers are checked.

What does section 19(11) ask of you on conveyance?

Section 19(11) says every allottee shall participate towards registration of the conveyance deed of the apartment, plot or building, as provided under section 17(1).

Section 17(1) places the main duty on the promoter: to execute a registered conveyance deed in favour of the allottee, along with the undivided proportionate title in the common areas to the association, and to hand over physical possession, within the period specified as per sanctioned plans under local laws. Its proviso says that in the absence of any local law, the conveyance deed shall be carried out by the promoter within three months from the date of issue of the occupancy certificate.

Participation, in practice, means being ready: arranging the funds for stamp duty and registration charges that fall on you under the agreement, keeping identity and loan documents available, and attending the registration when called. Section 19(6) separately says the allottee shall pay at the proper time and place the share of registration charges, municipal taxes, water and electricity charges, maintenance charges, ground rent and other charges.

Diagram of four steps a Bengaluru buyer can plan in the two months after the occupancy certificate is issued
Get the certificate, line up funds, inspect carefully and then take possession within the two months.

How should a Bengaluru buyer plan the two months after the OC?

Two months can pass quickly when final payments, loan disbursements and inspections all have to line up. A short plan helps. Use this checklist:

  1. Ask the promoter for a copy of the occupancy certificate for your unit.
  2. Note the date it was issued and count two months from it.
  3. Arrange the final payment and any loan disbursement in good time.
  4. Inspect the flat against the specifications and list defects in writing.
  5. Take possession, keep the dated possession letter and photograph the flat.
  6. Join or help form the association of allottees.
  7. Prepare documents and funds for registration of the conveyance deed.

If you have a home loan, speak to your lender early. The final disbursement may need the occupancy certificate, a demand letter and other documents, and the bank's own processing time counts against your two months. Starting that paperwork as soon as the certificate is issued leaves room for the inspection and any repairs.

If something outside your control delays possession, such as a defect the promoter has not fixed, write to the promoter before the two months end and keep the reply. Section 31 allows any aggrieved person to file a complaint with the Authority or the adjudicating officer for any violation or contravention of the Act.

What do Bengaluru buyers ask about taking possession under RERA?

How soon must I take possession after the occupancy certificate?

Section 19(10) of the RERA Act says every allottee shall take physical possession of the apartment, plot or building within a period of two months of the occupancy certificate issued for it. Ask the promoter for a copy of the certificate so that you know the date from which the two months run.

Does taking possession affect my defect liability rights?

Yes. Section 14(3) makes the promoter liable for structural and other defects brought to its notice within five years from the date of handing over possession, to be rectified without further charge within thirty days. The possession date therefore starts that five year window, so record it carefully.

Do I have to join the association of allottees?

Section 19(9) says every allottee shall participate towards the formation of an association or society or cooperative society of the allottees, or a federation of the same. Section 11(4)(e) requires the promoter to enable its formation, within three months of majority booking where there is no local law.

When must the builder register the conveyance deed?

Section 17(1) requires the promoter to execute a registered conveyance deed within the period specified under local laws. In the absence of local law, its proviso says it must be done within three months from the date of issue of the occupancy certificate. Section 19(11) asks allottees to participate in that registration.

Last updated 2026-10-18. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.