Did Your Older Hyderabad Project Need TG-RERA Registration? What the Vasavi GP Trends Order Says

On 10 November 2026, TG-RERA closed a suo motu case on Vasavi GP Trends without a penalty, citing an ambiguity in the old Telangana rule that excluded projects with building permission before 1 January 2017. The rule was amended in March 2025, and the test now turns on the occupancy or completion certificate as on 1 May 2017.

Legal & Documentation
Updated on
November 16, 2026
12 min read

The building permission was issued by GHMC on 27 December 2016. The occupancy certificate came on 8 June 2022. Between those two dates sat 1 May 2017, the day the registration provisions of the RERA Act took effect. On 10 November 2026, the Telangana Real Estate Regulatory Authority had to decide what those three dates meant for a Nanakramguda project called Vasavi GP Trends, and its answer is a useful lesson for anyone buying into an older Hyderabad building.

In Suo Motu Case No. 858 of 2025, TG-RERA found that the project had not obtained an occupancy certificate when the Act commenced. But it declined to impose a penalty, because the Telangana rule in force at the time, and TG-RERA's own published FAQ, had pointed the other way. The rule has since been amended, and the test is now clearer.

The short answer. Under the order, Section 3(1) of the RERA Act requires registration of ongoing projects that had no occupancy certificate or completion certificate on 1 May 2017. Telangana's erstwhile Rule 2(1)(j) excluded projects with building permission approved before 1 January 2017, and TG-RERA said that created an ambiguity. G.O.Ms. No. 60 dated 4 March 2025 amended the rule so that the occupancy or completion certificate date decides, irrespective of when building permission was granted. The trade-off for buyers: the clarified test brings more older projects within RERA on paper, but this order shows a pre-2017 permission project may still have no TG-RERA record, so your own document checks carry more weight.

What did TG-RERA decide on 10 November 2026?

It closed the case without a penalty. The proceedings began under Section 35(1) of the Act, after a representation dated 4 April 2025 against M/s Vasavi GP Infra about the project. The order records that the matter was finally heard on 22 September 2026 and decided by Member K. Srinivasa Rao.

The Authority found that the building permission was granted by GHMC on 27 December 2016 and the occupancy certificate was issued on 8 June 2022. So, as on 1 May 2017, the project had not obtained an occupancy certificate. It then noted that Section 3(1) requires registration of ongoing projects that had not obtained an occupancy or completion certificate on commencement.

But it also found that the erstwhile Rule 2(1)(j) of the Telangana Real Estate (Regulation and Development) Rules, 2017 excluded projects whose building permissions were approved before 1 January 2017, and that the FAQ then published on TG-RERA's website indicated the same position. Given that specific ambiguity, and the later occupancy certificate, the Authority said the circumstances did not warrant a penalty.

What was the old Telangana rule, and what changed in 2025?

The old rule looked at the building permission date. The order says the erstwhile Rule 2(1)(j) excluded projects in respect of which building permissions had been approved before 1 January 2017. A promoter with a 2016 permission could read that as taking the project outside the definition of an ongoing project.

The change came on 4 March 2025. The order records that the position was clarified through TG-RERA Circular No. 607/2025/TGRERA dated 4 March 2025, following the amendment to Rule 2(1)(j) notified by G.O.Ms. No. 60 of the Municipal Administration and Urban Development Department, of the same date. In the order's words, the amended provision clarifies that applicability is to be determined with reference to whether an occupancy certificate or completion certificate had been issued as on 1 May 2017, irrespective of the date of grant of building permission.

That is the same date test the Ministry of Housing and Urban Affairs describes nationally. Its FAQ on the RERA Act says Sections 3 to 19 were notified for commencement with effect from 1 May 2017. We explained the national rule for Bengaluru buyers in our guide to buying into a project that began before RERA.

How does the date test sort older Hyderabad projects?

The table applies the test described in the order to five illustrative buildings. The dates are hypothetical, except the last row, which is the Vasavi GP Trends timeline as recorded by TG-RERA.

Building permissionOC or CC dateOld Rule 2(1)(j) readingTest after G.O.Ms. No. 60 of 2025What a buyer should check
March 2015January 2017Excluded, permission before 1 January 2017Not ongoing, certificate before 1 May 2017The certificate and its date
June 20162019Excluded, permission before 1 January 2017Ongoing, no certificate on 1 May 2017Whether a TG-RERA record exists
February 20172020Within the ruleOngoing, no certificate on 1 May 2017TG-RERA registration number
2021Not yet issuedWithin the ruleNew project, registration before saleRegistration before any payment
27 December 20168 June 2022Relied on by the promoterNo certificate on 1 May 2017; no penalty given ambiguityTitle papers, as TG-RERA made no title finding

The middle rows are the ones to watch. A building in the second row looks old and was never on the register under the old reading, but under the clarified test it had no certificate on 1 May 2017.

Did TG-RERA rule on the land allegations?

No, and the order is explicit about it. The representation had alleged that permissions were obtained by suppressing pending proceedings and attachment orders concerning the land. The promoter disputed the case and raised objections on jurisdiction and on the petitioner's standing.

The Authority said its suo motu proceedings were not intended to determine title to the property, the subsistence or effect of the alleged attachment orders, or the merits of the civil and criminal proceedings referred to by the parties. It recorded no finding on the allegations of suppression and said those matters fall within the domain of the competent courts. Readers should treat the allegations as unproven claims, which is how the order treats them.

The order also dealt with standing. The promoter argued the petitioner was not an allottee and so not an aggrieved person under Section 31. The Authority said the case was an independent inquiry under Section 35(1), not a complaint under Section 31, so that objection did not affect its jurisdiction. This is one of several 10 November orders; we covered others in our report on TG-RERA's 10 November suo motu orders.

What does this mean if you are buying a flat in an older building?

It means the absence of a TG-RERA record is not, by itself, an answer. A building that received its permission in 2016 may have had no registration under the old reading of the rule, and TG-RERA has now said that a promoter who relied on that reading at the time will not necessarily be penalised. For a resale buyer, the practical effect is that RERA disclosures may simply not exist for the project.

The order also shows how the question can surface years later. The project received its occupancy certificate in 2022, yet the registration question was examined only after a representation filed in April 2025 and an order in November 2026. A buyer cannot assume that a completed, occupied building has already been through that scrutiny.

So the paperwork has to do the work. Ask for the occupancy certificate and its date, the building permission, and the title chain. If there were disputes about the land, the RERA route will not settle them, as this order shows, so a lawyer's title search matters more than usual. If you are comparing an older tower with a newer launch in the same area, such as My Home Vyoma in Nanakramguda, run the same date test on both and look each one up on the TG-RERA project search.

What should a Hyderabad buyer check in an older project?

  1. Ask for the building permission and note its date and issuing authority.
  2. Ask for the occupancy certificate or completion certificate and note its date of issue.
  3. Compare that certificate date with 1 May 2017, when the registration provisions took effect.
  4. Search the project and promoter on the TG-RERA portal, whatever the permission date.
  5. If there is no TG-RERA record, ask the seller to explain in writing why none exists.
  6. Commission a title search that covers court cases and attachments on the survey number.
  7. Read any TG-RERA order on the project, noting what it decided and what it left to courts.

Is the clarified rule better for buyers?

On paper, yes, because the test now turns on a single dated document rather than on when a permission was granted. That matches the national approach and makes it harder to argue that a building still under construction in mid-2017 was outside RERA. But this order is also a reminder of its limits. TG-RERA chose not to penalise conduct that followed the old rule, and it left questions about land and title to the courts. The safer habit is to treat RERA registration as one check among several, not as a substitute for reading the certificates and the title yourself.

Frequently asked questions

What did TG-RERA decide in Suo Motu Case No. 858 of 2025?

In an order dated 10 November 2026, TG-RERA closed the case on Vasavi GP Trends without a penalty. It found the project had no occupancy certificate on 1 May 2017, but said an ambiguity in the erstwhile Rule 2(1)(j) and TG-RERA's own FAQ at the time meant a penalty was not warranted.

Which older Telangana projects needed RERA registration?

According to the order, Section 3(1) requires registration of ongoing projects that had not obtained an occupancy or completion certificate when the Act commenced on 1 May 2017. After the amendment by G.O.Ms. No. 60 dated 4 March 2025, that test applies irrespective of the date of building permission.

What was the old Rule 2(1)(j) in Telangana?

The order says the erstwhile Rule 2(1)(j) of the Telangana RERA Rules, 2017 excluded projects whose building permissions were approved before 1 January 2017, and TG-RERA's FAQ then pointed the same way. The rule was amended by G.O.Ms. No. 60 and clarified by TG-RERA Circular No. 607/2025 dated 4 March 2025.

Did TG-RERA rule on the land allegations in the Vasavi case?

No. The order says the proceedings were not intended to decide title, the alleged attachment orders, or the civil and criminal cases mentioned by the parties, and that no finding was recorded on the allegations of suppression. Those matters, the Authority said, fall within the domain of the competent courts.

Last updated 2026-11-16. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.