Agreement Date or RERA Date? How Bengaluru Buyers Should Read Two Possession Dates
The RERA Act uses two dates: the possession date in your agreement for sale under Section 13(2), which drives refunds and delay interest under Section 18(1), and the completion period the builder declares under Section 4(2)(l)(C). Here is how a Bengaluru buyer should read and check both.
A buyer in a Yeshwanthpur tower compares two documents on a Sunday afternoon. The agreement for sale promises possession in December 2026. The project's RERA page shows a completion date of June 2027. The builder's customer care says June is the date that counts. Is it?
This mismatch is common enough to be worth understanding before it becomes a dispute. The RERA Act uses two different dates for two different purposes: the possession date in your agreement, and the completion period the builder declared when registering the project. This guide explains where each comes from, what each controls, and what to check.
The short answer. Under the RERA Act, 2016, Section 13(2) says the agreement for sale shall specify the date on which possession is to be handed over, and Section 18(1)(a) ties refunds and delay interest to failure to give possession in accordance with the agreement or by the date specified in it. Separately, Section 4(2)(l)(C) requires the builder to declare, on affidavit, the time within which it will complete the project, and Section 19(3) lets you claim possession as per that declaration. The trade-off: the declared completion date is public and easy to check, but your strongest remedies under Section 18 are written around the agreement, so do not let a later registration date quietly replace the date you signed for.
Where does the possession date in my agreement come from?
From the agreement for sale itself. Section 13(2) says the agreement for sale shall be in the prescribed form and shall specify, among other things, the particulars of development, the dates and manner of payments, the date on which possession of the apartment is to be handed over, and the rates of interest payable by the promoter to the allottee, and by the allottee to the promoter, in case of default.
That date is a contractual promise made to you. It is the date the Act refers back to when things go wrong. Section 18(1) says that if the promoter fails to complete or is unable to give possession of an apartment in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein, it shall be liable on demand to return the amount received with interest and compensation if the allottee wishes to withdraw. Its proviso says that where the allottee does not intend to withdraw, the promoter shall pay interest for every month of delay till the handing over of possession, at the prescribed rate.
Where does the RERA completion date come from?
From the builder's registration filing. Section 4(2)(l)(C) requires the promoter's application to include a declaration, supported by an affidavit, stating the time period within which it undertakes to complete the project or phase. Section 11(1) then requires the promoter to enter the project's registration details on the Authority's website for public viewing, along with quarterly updates on the status of the project.
Section 19(3) gives this declared date a role of its own. It says the allottee shall be entitled to claim possession of the apartment, and the association of allottees shall be entitled to claim possession of the common areas, as per the declaration given by the promoter under Section 4(2)(l)(C).
So the Act gives you two anchors. One is the date in your contract. The other is the completion period the builder swore to the regulator. They can be the same. When they are not, you need to know which one a particular right depends on.
The table below maps the two dates.
| Date | Where it comes from | Section | What it is used for |
|---|---|---|---|
| Possession date in the agreement for sale | The agreement, which must specify the date of handover | 13(2) | The contractual promise to you |
| Agreement date as a trigger | Failure to give possession as per the agreement or by the date specified in it | 18(1)(a) and proviso | Refund with interest, or monthly delay interest if you stay |
| Declared completion period | The promoter's affidavit in the registration application | 4(2)(l)(C) | The completion commitment made to the regulator |
| Possession as per declaration | The allottee's right to claim possession as per the declaration | 19(3) | Your right to claim possession of your unit |
| Extended registration | An extension granted by the Authority for force majeure or reasonable circumstances | 6 | Keeps the registration valid; check its effect on your agreement separately |
What if the builder's registration is extended?
Section 6 says registration may be extended by the Authority on the promoter's application due to force majeure, which the Explanation defines as war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the project. A proviso allows the Authority, in reasonable circumstances and without default on the part of the promoter, to extend registration for such time as it considers necessary, not exceeding one year in aggregate, for reasons recorded in writing. Another proviso says no extension application shall be rejected without a hearing.
The section speaks of extending the registration. It does not say that an extension rewrites the possession date in an agreement for sale. That question can matter a great deal when delay interest is calculated, and it is one on which you should take advice for your own case. Our piece on how a regulator's extension interacts with the agreement's possession date looks at the same issue through a recent Telangana order.
How can a Bengaluru buyer check both dates?
It takes a few minutes and is worth doing every quarter. If you want a project page to practise on, look up a registered project such as Assetz 22 and Crest in Yeshwanthpur and note how its details are presented.
- Find the possession date in your agreement for sale and note the exact clause.
- Note the interest rates for default by either side, which Section 13(2) requires the agreement to state.
- Look up your project on the K-RERA website and note the declared completion date.
- Check whether the registration has been extended and, if so, on what grounds and until when.
- Compare the latest quarterly status on the project page with what you see on site.
- If the dates differ, ask the builder in writing which date it considers binding and why.
- Keep the reply and, if the possession date in your agreement passes, decide whether to stay and claim interest or withdraw and claim a refund.
What should I do when the agreement date passes?
Decide whether you want to stay or leave, because the Act treats the two differently. Under Section 18(1), a buyer who wishes to withdraw is entitled, on demand, to the return of the amount received for the apartment, with interest at the prescribed rate and compensation as provided under the Act. Section 19(4) gives the allottee a matching right to claim that refund. A buyer who does not intend to withdraw is entitled, under the proviso to Section 18(1), to interest for every month of delay till possession is handed over.
Whichever you choose, put it in writing to the builder, citing the agreement clause and the date. If the builder does not respond satisfactorily, Section 31(1) says any aggrieved person may file a complaint with the Authority or the adjudicating officer, as the case may be, for any violation of the Act or the rules and regulations.
What happens once the occupancy certificate arrives?
Your own clock starts. Section 11(4)(b) makes the promoter responsible for obtaining the completion certificate or occupancy certificate, or both, and making it available to allottees. Section 19(10) then says every allottee shall take physical possession of the apartment within a period of two months of the occupancy certificate being issued for it. Keep an eye on the project page and your inbox once construction nears completion, so that a missed notice does not put you on the wrong side of that two-month window.
Can the builder ask me to sign a new date?
It can ask. Whether you agree is your choice. If a revised date is presented as part of an addendum, a consent form or a takeover proposal, read it carefully, because signing may change the date the Act refers back to under Section 18(1). Our explainer on your rights and duties under Section 19 covers the other entitlements that sit alongside possession.
Before you sign anything that moves a date, ask what you are being offered in return, and take advice from a lawyer who handles RERA matters. A date in a signed agreement is one of the most valuable things a buyer holds.
Frequently asked questions
Which possession date counts for a Bengaluru flat under RERA?
Two dates appear in the Act. Section 13(2) says the agreement for sale shall specify the date on which possession is to be handed over, and Section 18(1)(a) ties refund and delay interest to the agreement. Section 19(3) lets an allottee claim possession as per the promoter's declaration under Section 4(2)(l)(C).
What is the completion date in a RERA registration?
Under Section 4(2)(l)(C), the promoter's registration application includes a declaration, supported by an affidavit, stating the time period within which it undertakes to complete the project or phase. Section 19(3) entitles the allottee to claim possession as per that declaration.
Does an extension of RERA registration change my agreement's possession date?
Section 6 lets the Authority extend registration for force majeure, or for up to one year in total in reasonable circumstances without the promoter's default. The section speaks of extending registration; it does not say it amends the date in an agreement for sale, so read both and take advice.
When does delay interest start under RERA?
Section 18(1) applies if the promoter fails to complete or give possession in accordance with the agreement for sale or by the date specified in it. Its proviso says an allottee who stays in the project shall be paid interest for every month of delay till handing over of possession, at the prescribed rate.
Last updated 2026-11-17. PropNewz Team.