When a Builder Hands Your Project to Another Developer: RERA Section 15 for Bengaluru Buyers
RERA Section 15 bars a builder from transferring its majority rights in a project without two-thirds of allottees' written consent and the Authority's approval. Allotments stay intact, and the incoming developer must meet all pending obligations without extra time. Here is what Bengaluru buyers should check.
A letter arrives at a Bengaluru buyer's home: the developer of a half-built project proposes to hand over the project to another company, and asks allottees to sign a consent form within two weeks. The new company is bigger and promises to finish. Should you sign? And what happens to your agreement if you do, or do not?
The RERA Act has a specific provision for this situation. Section 15 sets out when a promoter can transfer its majority rights and liabilities in a project to a third party, who must agree, and what the incoming developer inherits. This guide walks through it so that a consent form does not become a blank cheque.
The short answer. Section 15(1) of the RERA Act, 2016 bars a promoter from transferring or assigning its majority rights and liabilities in a project to a third party without prior written consent from two-thirds of the allottees, excluding the promoter, and prior written approval of the Authority. Such a transfer does not affect existing allotments or sales. Under Section 15(2), the new promoter must independently comply with all pending obligations under the Act and under the earlier promoter's agreements for sale, and gets no extension of time to complete the project. The trade-off: a takeover by a stronger developer can revive a stalled project, but your consent is one of the few points of leverage buyers have, so read what you are agreeing to before you sign.
What does Section 15 require before a project changes hands?
Two approvals, both in advance. Section 15(1) says the promoter shall not transfer or assign its majority rights and liabilities in respect of a real estate project to a third party without obtaining prior written consent from two-thirds of the allottees, except the promoter, and without the prior written approval of the Authority.
The words matter. The consent must be prior and written. The count is two-thirds of allottees other than the promoter. And the Authority's approval is a separate requirement, not a formality that follows automatically once buyers have signed.
The Explanation to Section 15(1) adds a counting rule. An allottee is considered one, irrespective of the number of apartments or plots booked by that person or in the name of the family. Companies, firms and associations are also counted as one together with their associated entities or related enterprises. This is the same counting rule the Act uses for plan changes under Section 14(2)(ii), which our guide to plan changes and the two-thirds rule explains with a worked example.
Here is a second illustration. Suppose a Bengaluru project has 300 booked units. Ten are held by one investor's family, and twenty by a company and its group entities. Under the Explanation, those 30 units count as two allottees, so 300 units represent 272 allottees for this purpose. Two-thirds of 272 is about 181.3, so at least 182 written consents would be needed, alongside the Authority's approval. This is arithmetic only; the real count depends on your project's bookings, which is why it is reasonable to ask how the promoter has done the count.
What happens to my allotment and agreement?
They continue. The proviso to Section 15(1) says that such a transfer or assignment shall not affect the allotment or sale of the apartments, plots or buildings in the project made by the erstwhile promoter. The flat you were allotted remains yours under the same allotment.
Section 15(2) then says that on the transfer or assignment being permitted by the allottees and the Authority, the intending promoter shall be required to independently comply with all the pending obligations under the provisions of the Act or the rules and regulations, and the pending obligations as per the agreement for sale entered into by the erstwhile promoter with the allottees.
So the incoming developer steps into the earlier promoter's shoes, both under the Act and under your agreement. It cannot pick only the obligations it likes.
This also matters if you bought your allotment from an earlier buyer. Section 2(d) defines an allottee to include the person who subsequently acquires the allotment through sale, transfer or otherwise. A resale buyer in an under-construction project is therefore an allottee whose allotment the proviso to Section 15(1) protects, and whose agreement the incoming promoter must honour under Section 15(2). Make sure the project's records show your name before the transfer goes through.
Does the new developer get more time?
Not because of the transfer. The proviso to Section 15(2) says that any transfer or assignment permitted under the section shall not result in extension of time to the intending promoter to complete the project. It adds that the intending promoter shall comply with all the pending obligations of the erstwhile promoter, and in case of default, shall be liable to the consequences of breach or delay under the Act, rules and regulations.
That proviso protects buyers in a practical way. A takeover cannot reset the clock on your possession date. If the new developer needs more time, it has to seek it through the routes the Act provides, such as an extension of registration under Section 6, rather than relying on the transfer itself.
The table below summarises Section 15.
| Requirement or effect | What the Act says | Section | What a buyer should check |
|---|---|---|---|
| Allottee consent | Prior written consent from two-thirds of allottees, except the promoter | 15(1) | The consent count and how allottees were counted |
| Regulator approval | Prior written approval of the Authority | 15(1) | Whether the Authority has approved the transfer |
| Existing allotments | Transfer does not affect allotments or sales by the earlier promoter | Proviso to 15(1) | That your allotment letter and agreement remain valid |
| Pending obligations | New promoter must independently comply with all pending obligations under the Act and agreements for sale | 15(2) | A written undertaking from the new promoter |
| Completion time | Transfer does not extend time; new promoter liable for breach or delay | Proviso to 15(2) | The completion date on the register after transfer |
Should I sign the consent form?
That is your decision, and it depends on the project and the incoming developer. The Act does not tell you how to vote. It does give you reasons to ask questions before you do.
Start with what the form actually says. A consent under Section 15(1) is a consent to transfer the promoter's majority rights and liabilities. If the form also asks you to accept a new possession date, a price change, revised specifications or a waiver of delay interest, those are separate matters. Changes to your apartment's plans or specifications need your previous consent under Section 14(2)(i), and changes to the building or common areas need two-thirds of allottees under Section 14(2)(ii). Do not let one signature cover more than you intend.
Then look at the incoming developer. Its own project filings on the RERA register include details of projects launched in the past five years, with delays and pending cases, under Section 4(2)(b). That is a useful starting point for judging whether a takeover is likely to help. If the incoming developer's own record shows long delays or many pending cases, ask how it plans to fund and staff your project before you consent.
What should a Bengaluru buyer do when a transfer is proposed?
Use the checklist below before signing anything.
- Ask for the full proposal in writing, including the name of the incoming developer and the reasons for transfer.
- Read the consent form and check that it covers only the transfer, not a new date, price or specification.
- Look up the incoming developer's other projects on the RERA register and note any delays.
- Ask the incoming developer for a written undertaking to honour your agreement for sale and pending obligations.
- Ask how allottees are being counted for the two-thirds threshold.
- Speak to other buyers and, if an association exists, ask it to coordinate a collective response.
- After the transfer, check the K-RERA register to confirm the Authority's approval and the completion date.
How is this different from a project that is revoked?
A Section 15 transfer is voluntary: the promoter proposes it, buyers and the Authority consent. Revocation under Section 7 is a regulatory action after default, which can lead to completion by the competent authority or the association under Section 8. Our explainer on what happens if K-RERA revokes a project's registration covers that route. Both are ways a project can change hands, but the buyer's role differs: under Section 15 your written consent is required for the transfer to go ahead.
For advice on a specific consent form or takeover proposal, speak to a lawyer who handles RERA matters before signing.
Frequently asked questions
Can a Bengaluru builder hand over my project to another developer?
Only with consent and approval. Section 15(1) of the RERA Act says the promoter shall not transfer or assign its majority rights and liabilities in a project to a third party without prior written consent from two-thirds of the allottees, excluding the promoter, and prior written approval of the Authority.
Does a project transfer cancel my allotment?
No. The proviso to Section 15(1) says such a transfer or assignment shall not affect the allotment or sale of apartments, plots or buildings in the project made by the erstwhile promoter. Your allotment and agreement continue, and the new promoter takes on the pending obligations.
Does the new developer get extra time to finish?
No. The proviso to Section 15(2) says a permitted transfer shall not result in extension of time to the intending promoter to complete the project. The new promoter must comply with all pending obligations of the earlier promoter and is liable for the consequences of breach or delay under the Act.
How are allottees counted for the two-thirds consent?
The Explanation to Section 15(1) says an allottee is counted as one, irrespective of the number of apartments or plots booked by that person or in the family's name. Companies, firms and associations are counted as one together with their associated entities or related enterprises.
Last updated 2026-11-17. PropNewz Team.