An Extra Rs 5.75 Lakh Demand and a TG RERA Interim Order: Lessons for Hyderabad Buyers
On October 30, 2026, TG RERA passed an interim order under Section 36 restraining Pacifica Constructions from cancelling a buyer's flat in Aavas Hyderabad, Bachupally, solely over a disputed Rs 5,75,731 demand, and from creating third-party rights in it, until a December 3 hearing. Here is what the RERA Act says about cancellation, extra charges and interim relief.
Bondili Saritha signed an agreement of sale for a flat in Bachupally on May 25, 2018. The agreed price for Flat No. AW4-909 in Pacifica Constructions' Aavas Hyderabad project was Rs 18,00,795, excluding taxes. By her account she has paid Rs 18,89,895. The possession deadline, she says, passed on November 25, 2023. Then came a fresh demand of Rs 5,75,731, and with it a fear every buyer in a delayed project recognises: pay up, or risk losing the flat.
On October 30, 2026, the Telangana Real Estate Regulatory Authority stepped in with an interim order. It is not a final ruling. But it shows Hyderabad buyers exactly which part of the RERA Act protects an allotment while a payment dispute is being heard.
The short answer. According to NewsMeter's report, TG RERA used Section 36 of the RERA Act to restrain the developer from cancelling the allotment solely over the disputed Rs 5,75,731, and from alienating, transferring, encumbering or creating third-party rights in the flat, until the next hearing on December 3, 2026. Under the Act as published in the Gazette, a promoter may cancel an allotment only in terms of the agreement for sale. The trade-off: interim protection keeps your flat safe while you contest a demand, but it does not decide whether the demand is valid, so you still need documents showing what your agreement does and does not allow.
What happened in the Aavas Hyderabad case?
NewsMeter, reporting on October 31, 2026, set out the buyer's side of the dispute. The agreement of sale was signed on May 25, 2018 and required possession within 60 months plus a six-month grace period. The contractual deadline expired on November 25, 2023, and the complainant alleges possession had still not been handed over.
The disputed amount of Rs 5,75,731 was levied under various heads, which the report does not list. The complainant said the builder insisted on payment of this amount as a condition for completing the registration and handing over the flat. She feared the developer might cancel her allotment or sell the flat to someone else. The report presents that as her fear, not as an explicit threat by the builder.
The report also notes that the developer's counsel repeatedly sought time to file a counter affidavit and none had been filed. The authority said that failure would not, by itself, be treated as an admission of the allegations, and found the complainant had made out sufficient grounds for protecting the allotment pending a further hearing.
| Date | Event, as reported | Why it matters to a buyer |
|---|---|---|
| May 25, 2018 | Agreement of sale for Flat AW4-909 at Rs 18,00,795 plus taxes | The agreement fixes the price and the charges you owe |
| 60 months plus 6 months grace | Possession period in the agreement | The grace period is part of the promised timeline |
| November 25, 2023 | Contractual possession deadline expired | Delay interest questions start from the agreed date |
| October 30, 2026 | TG RERA interim order under Section 36 | Cancellation solely over the disputed demand restrained |
| December 3, 2026 | Next hearing; respondents to file counter affidavit | Protection runs to this date, subject to further orders |
What power did TG RERA use, and how far does it go?
Section 36 of the Act. It says that where, during an inquiry, the authority is satisfied that an act in contravention of the Act, rules or regulations has been committed, continues to be committed or is about to be committed, it may by order restrain any promoter, allottee or real estate agent from carrying on that act until the inquiry ends or until further orders. It can do so without giving notice to the party where it deems that necessary.
The limits matter as much as the power. The report stresses that the order is not a final ruling on the allegations or on the disputed demand. The restraint was framed narrowly: no cancellation solely over the Rs 5,75,731, and no transfer or third-party rights in the flat. It does not say the money is not owed. The order also directed the respondents to file a counter affidavit on or before the next hearing date, and said any violation would be dealt with according to law.
When can a builder cancel an allotment under RERA?
Section 11(5) answers this in one line: the promoter may cancel the allotment only in terms of the agreement for sale. Its proviso adds that the allottee may approach the authority for relief if aggrieved by a cancellation that is not in accordance with the terms of the agreement, is unilateral and is without any sufficient cause.
So the first document to read when a cancellation is threatened is your own agreement for sale. Find the cancellation clause, note what default it requires, how much notice it gives and what it says about refund of money already paid. A cancellation that skips those steps is the kind the proviso to Section 11(5) lets you challenge before TG RERA.
Do I have to pay every extra charge the builder raises?
You have to pay what your agreement requires, on time. Section 19(6) says every allottee who has entered into an agreement for sale shall make necessary payments in the manner and within the time specified in that agreement, and pay at the proper time and place the share of registration charges, municipal taxes, water and electricity charges, maintenance charges, ground rent and other charges, if any.
Late payment has a cost. Section 19(7) makes the allottee liable to pay interest at the prescribed rate for any delay. TG RERA's official FAQ says that under Rule 15 the allottee pays interest equal to the State Bank of India's highest marginal cost of lending rate plus 2 percent on amounts due under the agreement. Section 19(8) says these obligations may be reduced when mutually agreed between promoter and allottee.
The practical line is simple. A charge your agreement lists is a debt you should plan for. A charge it does not list is a claim the builder must justify. Ask for the clause, in writing, before you pay or refuse.
What about the delay on the builder's side?
It is a separate claim and runs in the other direction. The proviso to Section 18(1) says that where an allottee does not intend to withdraw from the project, the promoter shall pay interest for every month of delay until possession is handed over, at the prescribed rate. TG RERA's FAQ adds that such interest is in accordance with the agreement and should be paid automatically, and that a buyer may have to file a complaint if there is a grievance.
Buyers in long delayed projects often set the two claims side by side: the builder's extra demand against the interest owed for delay. Whether one can be set off against the other depends on your agreement and on what the authority decides; the report does not say this was argued in the Aavas case. What the report does record is that the complainant alleges the agreed deadline passed on November 25, 2023, almost three years before the interim order.
Has TG RERA dealt with this project before?
Yes. In July 2025, Telangana Today reported that TG RERA had directed Pacifica Constructions to set up a dedicated grievance redressal cell for Aavas Hyderabad within five days, open at the project site at least five days a week, with an official email ID and helpline. Grievances were to be acknowledged within 48 hours and resolved or responded to within 15 days. Buyers had complained of failure to complete the project and deliver possession under the agreement for sale.
What should a Hyderabad buyer do if a builder threatens cancellation over a disputed demand?
Interim relief is available, but it is discretionary and depends on the record you bring. Section 31(1) lets any aggrieved person file a complaint with the authority for any violation of the Act, rules or regulations. These steps keep your file strong.
- Ask the builder for a written, itemised breakdown of the demand, head by head.
- Match each head against the price, charges and taxes clauses of your agreement for sale.
- Pay undisputed amounts that your agreement clearly requires, and keep the receipts.
- Reply in writing to any charge you dispute, citing the clause or its absence.
- Read your agreement's cancellation clause and note the default and notice it requires.
- If cancellation is threatened, file a complaint with TG RERA and ask for interim protection under Section 36.
- Track your possession date and record the months of delay, since Section 18(1) interest is a separate claim.
For the wider picture of TG RERA's enforcement this month, see our report on TG RERA's November 2026 orders. Our explainer on late payment interest under the TG RERA FAQ covers the Rule 15 rate in more detail. When you compare projects, including those on our pages such as Hallmark Altus in Kondapur, read the charges schedule before you book.
Frequently asked questions
What did TG RERA order in the Pacifica Aavas case?
According to NewsMeter's October 31, 2026 report, TG RERA passed an interim order on October 30 under Section 36 restraining Pacifica Constructions from cancelling the allotment of Flat AW4-909 solely over a disputed Rs 5,75,731 demand, and from alienating or creating third-party rights in it, until the December 3, 2026 hearing.
Can a Hyderabad builder cancel my flat whenever it wants?
Section 11(5) of the RERA Act says the promoter may cancel the allotment only in terms of the agreement for sale. If a cancellation is not in accordance with the agreement, is unilateral and without sufficient cause, the proviso lets the allottee approach the RERA authority for relief.
What is a Section 36 interim order?
Section 36 of the RERA Act lets the authority, during an inquiry, restrain any promoter, allottee or real estate agent from an act in contravention of the Act, rules or regulations that has been committed, continues or is about to be committed, until the inquiry ends or further orders, even without notice where necessary.
Do I have to pay every charge the builder demands?
Section 19(6) of the RERA Act makes an allottee responsible for payments in the manner and time specified in the agreement for sale, plus a share of registration charges, municipal taxes, utility and maintenance charges. Section 19(7) adds interest for late payment, which TG RERA's FAQ sets at SBI's highest MCLR plus 2 percent.
Last updated 2026-11-18. PropNewz Team.