Reading Your Builder's Form-3 CA Certificate: A Guide for Hyderabad Flat Buyers
TG-RERA's Form-3 is a chartered accountant's certificate filed at registration, each quarter and for withdrawals. This guide explains its withdrawal formula, the three RERA bank accounts it reports, and when 100 percent of receivables must be ring-fenced, for Hyderabad buyers.
Somewhere in the paperwork of every registered Hyderabad project is a certificate signed by a chartered accountant, stamped, and tagged with a membership number and a UDIN. It is called Form-3. Most buyers never see it, and the few who do tend to skip past the tables. That is a pity, because Form-3 is where the builder's own numbers have to line up: what the project was expected to cost, what has actually been spent, how much buyers have paid, and how much money the builder was allowed to take out of the project's bank account.
TG-RERA publishes the current format of this certificate on its website, listed as the new Form-3 Chartered Accountant's Certificate. This guide walks through what each part of that format asks for, so that if you ever get a copy from your builder, or are asked to rely on one, you know which lines to read first.
The short answer. TG-RERA's Form-3 format is a chartered accountant's certificate submitted at registration, with quarterly updates, at completion and for withdrawals from the project's separate account. Its key line is a formula: total estimated cost multiplied by the proportion of land and construction cost actually incurred and paid, minus what has already been withdrawn, gives the net amount the builder may withdraw. If estimated receivables fall short of the balance cost to complete, 100 percent rather than 70 percent of receivables goes into the designated account. The trade-off: the certificate is detailed and signed by a professional, but it is based on records and explanations given by the builder's management, so it is a starting point for your questions rather than a guarantee.
What is Form-3 and when is it filed?
Form-3 is a certificate of the financial progress of a project, issued by a chartered accountant on letterhead under Regulation 5. TG-RERA's format states that it is to be submitted at the time of registration, with quarterly updates, at the completion of the project, and for subsequent withdrawal of money from the separate account of the project.
The quarterly link matters. TG-RERA's Circular II dated 18 March 2025 says promoters must submit quarterly progress reports within 15 days from the end of each quarter and refers to those reports as Form-1, Form-2 and Form-3. So in principle, a fresh CA certificate is part of every quarterly cycle for an ongoing project.
The certificate's opening paragraph is worth reading carefully. It says the certificate is based on the records and documents produced before the chartered accountant, explanations provided by the management of the company, and verification of books of accounts for the quarter ended on a stated date. That is a normal professional disclaimer, and it tells you what kind of document this is: a certified reading of the builder's books, not a site inspection.
How does the withdrawal formula work?
The formula sits at the bottom of Table A. Column A records estimated costs and Column B records costs incurred. Land cost covers items such as the cost of land or development rights, premiums for development rights or FSI, TDR acquisition, stamp duty and registration paid by the project, and, for redevelopment schemes, rehabilitation costs. Development cost covers construction, on-site expenditure, statutory taxes and fees, and interest on construction borrowings.
For construction cost, the form asks for two figures: the estimated cost of construction as certified by the engineer, and the actual cost incurred and paid as per the books as verified by the CA. A note says the minimum of the two is to be considered. The form also records the percentage of completion of construction work as per the project architect's certificate.
From these, the form works out the proportion of cost incurred and paid to the total estimated cost. The amount which can be withdrawn from the designated account is the total estimated cost multiplied by that proportion. The amount already withdrawn till the date of the certificate, as per the books of accounts and bank statement, is then subtracted, leaving the net amount which can be withdrawn under this certificate.
A simple illustration, using made-up round numbers: if the total estimated cost is Rs 200 crore and Rs 80 crore of eligible cost has been incurred and paid, the proportion is 40 percent. Rs 200 crore multiplied by 40 percent is Rs 80 crore. If Rs 70 crore has already been withdrawn, the certificate would allow a further Rs 10 crore. If Rs 85 crore had already been withdrawn, the net figure would be negative, and that is a line any buyer would want explained.
Which lines should a buyer read first?
You do not need to audit the whole certificate. The table below lists five lines from TG-RERA's format and what each one can tell you.
| Line in Form-3 | What the format asks for | What it can tell a buyer | What to compare it with |
|---|---|---|---|
| Table A, total estimated cost | Land cost plus development cost, estimated at registration (Column A) | The size of the project as the builder declared it | The estimate in earlier certificates for the same project |
| Table A, percentage of completion | Completion of construction work as per the project architect's certificate | How far construction has progressed on paper | The construction stage in your latest payment demand |
| Table A, net amount which can be withdrawn | Estimated cost times proportion of cost incurred and paid, less amount withdrawn till date | Whether withdrawals are within the formula | The amount withdrawn till date on the same table |
| Table B, booked inventory | Unit consideration as per agreement, amount received and balance for each booked unit | How much buyers have paid and still owe | Your own unit's figures, if listed |
| Additional information, 70 percent or 100 percent | Estimated receivables compared with estimated balance cost to complete | Whether future collections are expected to cover the remaining work | Table D, which shows how the project is being financed |
What do the three bank accounts in Table C mean?
Table C asks for details of three RERA bank accounts: the collection account of the project, the separate account of the project, and the transaction account of the project. For each, the chartered accountant records the account number, bank name, IFSC code, opening balance, deposits during the period, withdrawals during the period and closing balance.
Below Table C, the format contains two certifications. In the first, the chartered accountant certifies that the required proportion of money, as specified in the Act, collected from allottees of the units in Table B has been deposited in the designated RERA bank account. In the second, the CA certifies that the promoter has utilised the required proportion of money collected from allottees for the land and construction of this project only.
Those two sentences are the heart of the certificate for a buyer. If a certificate for your project is ever produced with either sentence missing, qualified or struck out, ask why in writing.
When does the 70 percent rule become 100 percent?
The additional information section at the end of the format answers this. It asks for the estimated balance cost to complete the project, the balance receivables from booked units, the estimated sale proceeds of unbooked units, and the total estimated receivables. Then it sets a test.
If estimated receivables are greater than the balance cost to complete, 70 percent of the balance receivables of the project will be deposited in the designated account. If estimated receivables are lesser than the balance cost to complete, 100 percent of the balance receivables of the ongoing project will be deposited in the designated account. In plain terms, when the money still to come in may not be enough to finish the project, the format requires all of it to be ring-fenced.
Table D, headed Means of Finance, completes the picture. It sets out own funds, secured and unsecured borrowed funds with drawdowns availed, customer receipts used for the project and total funds, against the total estimated cost. A project that leans heavily on customer receipts has less of a cushion if bookings slow.
How can a Hyderabad buyer use this in practice?
Start by finding your project on TG-RERA's project search page and noting the registration number. Then use the checklist below when you speak to the builder or review documents. Our page on My Home Vyoma in Nanakramguda is one example of a registered project you can practise the lookup on.
- Note your project's TG-RERA registration number and the quarter you are asking about.
- Ask the builder in writing for the latest Form-3 chartered accountant's certificate filed for the project.
- Check that the certificate shows the CA's name, firm, membership number and UDIN.
- Read the net amount which can be withdrawn in Table A and ask about any negative figure.
- Compare the percentage of completion with the construction stage in your last payment demand.
- Look at the 70 percent or 100 percent test in the additional information section.
- Keep the certificate with your agreement and payment receipts, and repeat the request each quarter.
The annual audit in Form-7 is the companion document to these quarterly certificates. Our explainer on TG-RERA's extension of the Form-7 deadline to 21 December 2026 covers what that audit verifies. If you are trying to understand a separate change to completion dates, see our piece on the West Asia extension to 30 November 2026.
What can Form-3 not tell you?
It cannot tell you whether the building is being built well, whether the title is clean, or whether your own possession date will be met. It is a financial certificate based on books, records and management explanations. Read it alongside the project's approvals, your agreement for sale and what you see on site, and take professional advice before acting on anything that looks wrong.
Frequently asked questions
What is the TG-RERA Form-3 certificate?
Form-3, issued under Regulation 5, is a chartered accountant's certificate on the firm's letterhead. TG-RERA's format says it is submitted at the time of registration, with quarterly updates, at completion of the project and for subsequent withdrawal of money from the project's separate account.
How does Form-3 decide how much a builder can withdraw?
Table A multiplies the total estimated cost of the project by the proportion of land and construction cost actually incurred and paid. The amount already withdrawn, as per the books and bank statement, is subtracted. The balance is the net amount the certificate allows to be withdrawn from the designated account.
When must a Hyderabad builder deposit 100 percent instead of 70 percent?
The additional information section of Form-3 says that if the estimated receivables of the project are less than the estimated balance cost to complete it, 100 percent of the balance receivables will be deposited in the designated account. If receivables are greater, 70 percent will be deposited.
Which bank accounts does Form-3 report?
Table C asks for details of three RERA bank accounts: the collection account of the project, the separate account of the project and the transaction account of the project. For each it lists account number, bank, IFSC, opening balance, deposits, withdrawals and closing balance for the period.
Last updated 2026-11-17. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.