The RERA Filing Behind Every Project: How Bengaluru Buyers Can Use Section 4(2)
RERA Section 4(2) requires builders to file past five years' projects with delays and cases, approvals, plans, proforma agreements, carpet areas and a sworn title and funds declaration, and Section 11(1) puts them on the Authority's website. Here is how a Bengaluru buyer can use that filing.
Before a Bengaluru builder can advertise or book a single flat in a new project, it has to put a stack of documents in front of the regulator. The list is set out in one section of the RERA Act, and it is more revealing than most brochures: the builder's other projects and their delays, pending cases, the sanctioned plan, the draft sale agreement, carpet areas, and a sworn declaration about the land.
Most buyers never look at this material, even though the Act requires much of it to be made public. This guide walks through what Section 4(2) requires and how you can use it to check a project before you pay a booking amount.
The short answer. Section 4(2) of the RERA Act, 2016 requires a promoter applying for registration to file, among other things, details of projects launched in the past five years including delays and pending cases, approvals and the commencement certificate, the sanctioned plan and layout, proforma allotment letter, agreement for sale and conveyance deed, carpet areas, and an affidavit on land title, encumbrances, completion time and the seventy per cent separate account. Section 11(1) requires these details to be entered on the Authority's website for public viewing. The trade-off: the information is detailed and sworn, but it is the builder's own filing, so it tells you what was declared, not whether every declaration is true, and you still need independent title checks.
What does Section 4(2) require a builder to file?
Section 4(1) says every promoter shall apply to the Authority for registration of a real estate project in the form, manner and time, and with the fee, specified by regulations. Section 4(2) then lists the documents the promoter shall enclose. They fall into four groups.
The first group is about the builder. Clause (a) asks for brief details of the enterprise, including name, registered address, type of enterprise, particulars of registration, and the names and photographs of the promoter. Clause (b) asks for brief details of projects launched in the past five years, whether completed or being developed, including the current status, any delay in completion, details of cases pending, details of type of land and payments pending.
The second group is about approvals and plans. Clause (c) requires an authenticated copy of the approvals and commencement certificate from the competent authority, phase by phase where the project is phased. Clause (d) requires the sanctioned plan, layout plan and specifications of the proposed project or phase, and of the whole project as sanctioned. Clause (e) requires the plan of development works and proposed facilities, including fire fighting facilities, drinking water facilities, emergency evacuation services and use of renewable energy. Clause (f) requires location details with clear demarcation of the land and its boundaries, including the latitude and longitude of the end points of the project.
What does the filing say about my contract and my flat?
The third group goes to the documents you will sign and the unit you will get. Clause (g) requires the proforma of the allotment letter, agreement for sale and conveyance deed proposed to be signed with allottees. Clause (h) requires the number, type and carpet area of apartments for sale, along with the area of exclusive balcony or verandah and exclusive open terrace areas. Clause (i) requires the number and areas of garages for sale.
Clauses (j) and (k) add the names and addresses of the promoter's real estate agents, if any, and of the contractors, architect, structural engineer and others concerned with development. That makes it possible to check whether the agent selling to you is the one named in the filing. Our explainer on carpet area under RERA explains how to read the Clause (h) figures.
What does the builder swear about land and money?
The fourth group is a declaration under Clause (l), supported by an affidavit signed by the promoter or an authorised person. It must state that the promoter has legal title to the land on which development is proposed, with legally valid documents and authentication of title if the land is owned by another person. It must state that the land is free from all encumbrances or, as the case may be, give details of encumbrances, including any rights, title, interest or name of any party over the land. It must state the time period within which the promoter undertakes to complete the project or phase.
It must also state that seventy per cent of the amounts realised for the project from allottees, from time to time, shall be deposited in a separate account in a scheduled bank to cover the cost of construction and the land cost, and shall be used only for that purpose. Provisos add that withdrawals from that account must be in proportion to the percentage of completion, and only after an engineer, an architect and a chartered accountant in practice certify that the withdrawal is in that proportion.
If the title declaration later proves wrong, the Act has consequences, which our piece on compensation for defective land title covers.
The table below maps five filings to the buyer question each one answers.
| Section 4(2) clause | What the builder files | Buyer question it answers | What to cross-check |
|---|---|---|---|
| (b) | Projects launched in the past five years, with status, delays, pending cases and payments pending | How has this builder performed recently? | Possession dates of those projects against their promised dates |
| (c) and (d) | Approvals, commencement certificate, sanctioned plan, layout plan and specifications | Is what I am shown actually sanctioned? | The brochure and sample flat against the sanctioned plan |
| (g) | Proforma allotment letter, agreement for sale and conveyance deed | What will I be asked to sign? | The documents you receive at booking against the proforma |
| (h) and (i) | Number, type and carpet area of apartments; exclusive balcony and terrace areas; garages | Is the area quoted to me the declared carpet area? | The area in your cost sheet and agreement |
| (l)(A) to (D) | Affidavit on title, encumbrances, completion time and the seventy per cent separate account | What has the builder sworn about the land, timeline and money? | An independent title and encumbrance search |
Can I actually see these documents?
The Act intends you to. Section 11(1) says the promoter, on receiving its login ID and password, shall create its web page on the Authority's website and enter all details of the proposed project as provided under Section 4(2), in all the fields provided, for public viewing. It adds quarterly updates of apartments and garages booked, approvals taken and pending after the commencement certificate, and the status of the project.
Section 11(2) adds that the builder's advertisements and prospectus must prominently mention the Authority's website address, where all details of the registered project have been entered, and include the registration number. So the registration number on an advertisement is your starting point for finding the filing.
How should a Bengaluru buyer use the filing before booking?
Treat it as a free due diligence pack. Whether you are looking at a large launch or a smaller project such as Godrej Tiara on Tumkur Road, the routine is the same.
- Take the registration number from the advertisement or brochure and find the project on the K-RERA website.
- Read the builder's list of projects from the past five years, noting any delays and pending cases.
- Download the sanctioned plan and layout plan and compare them with the brochure and sample flat.
- Compare the proforma agreement for sale with the draft you are given at booking.
- Match the carpet area of your unit type with the area in your cost sheet.
- Read the land title and encumbrance declaration, then commission your own title and encumbrance search.
- Check the declared completion time against the possession date the sales team promises.
What if the project is being built in phases?
Then check that you are reading the right filing. The Explanation to Section 3 says that where a real estate project is to be developed in phases, every such phase shall be considered a stand-alone real estate project, and the promoter shall obtain registration for each phase separately. Clause (c) of Section 4(2) similarly asks for approvals and the commencement certificate for each phase.
In practice, a large Bengaluru township may carry several registration numbers. The completion date, carpet areas and approvals in one phase's filing do not automatically apply to another, so match the registration number on your own allotment letter with the filing you study.
What can the filing not tell me?
It cannot tell you that every statement in it is accurate, or that the project will be built on time. It is a set of documents and sworn declarations by the promoter. The Act backs those declarations with consequences, but your protection is strongest when you check the key facts independently, especially title and encumbrances, and take legal advice before paying anything substantial.
Frequently asked questions
What documents does a builder file to register a project under RERA?
Section 4(2) of the RERA Act lists them, including enterprise details, projects launched in the past five years, approvals and commencement certificate, sanctioned and layout plans, development plans, location details, proforma allotment letter, agreement for sale and conveyance deed, carpet areas, garages, agents, contractors and a declaration on title and funds.
Can buyers see these registration details?
Section 11(1) says the promoter, on receiving login details, shall create a web page on the Authority's website and enter all details of the proposed project as provided under Section 4(2), in all the fields provided, for public viewing, along with quarterly updates on bookings, approvals and project status.
What does the builder declare about the land?
Under Section 4(2)(l), the promoter files a declaration supported by an affidavit stating that it has legal title to the land, that the land is free from all encumbrances or giving details of encumbrances, and the time period within which it undertakes to complete the project or phase.
Why does the past five years' project history matter?
Section 4(2)(b) requires brief details of projects launched by the promoter in the past five years, completed or under development, including current status, any delay in completion, details of cases pending, type of land and payments pending. It is a ready record of the builder's track record.
Last updated 2026-11-17. PropNewz Team.