When a Project's RERA Registration Is Extended, Lapses or Is Revoked: A Bengaluru Guide

Sections 6, 7 and 8 of the RERA Act set out when a project's registration can be extended, how it can be revoked, and what happens to the remaining work and to buyers afterwards. Here is how a Bengaluru buyer can read these events.

Legal & Documentation
Updated on
October 17, 2026
12 min read
Infographic of RERA registration extension, lapse and revocation for Bengaluru buyers, from a one year cap to 30 days notice

A buyer in an under construction project on Bengaluru's northern fringe opens the regulator's website one evening and notices that the project's registration validity has changed. The completion date now reads a year later than the one in the agreement. A neighbour in another project sees something worse: a defaulters list with a familiar builder's name on it. Both buyers want to know the same thing. What does this mean for my flat?

The Real Estate (Regulation and Development) Act, 2016 answers that question in three short sections. Section 6 covers extension of a project's registration, Section 7 covers revocation, and Section 8 covers what happens to the remaining work after a lapse or revocation. This guide reads all three from the Act and turns them into a buyer's checklist.

The short answer. Under Section 6 of the RERA Act, the Authority may extend a project's registration on the promoter's application due to force majeure, and in reasonable circumstances without default by the promoter for up to one year in aggregate. Under Section 7, the Authority may revoke registration for defaults, violations of approvals, unfair practices or fraud, but only after at least thirty days' written notice to the promoter. Under Section 8, after a lapse or revocation, the Authority may arrange for the remaining work to be carried out, and the association of allottees has the first right of refusal after a revocation. The trade-off: these powers protect buyers collectively, but they move slowly, so your individual rights to refund and compensation still need tracking.

When can a project's RERA registration be extended?

Section 6 of the Real Estate (Regulation and Development) Act, 2016 in its Gazette text says the registration granted under Section 5 may be extended by the Authority on an application made by the promoter due to force majeure, in the form and on payment of the fee specified by regulations.

The explanation to Section 6 defines force majeure narrowly. It means a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the project.

The first proviso adds a second route. The Authority may, in reasonable circumstances, without default on the part of the promoter, based on the facts of each case and for reasons recorded in writing, extend the registration for such time as it considers necessary, which shall in aggregate not exceed one year. The second proviso says no application for extension shall be rejected unless the applicant has been given an opportunity of being heard.

For a buyer, an extension is information, not a verdict. It tells you the registered timeline has moved. It does not, by itself, change the possession date in your agreement for sale, so read both side by side.

Diagram of the four grounds on which RERA can revoke a project registration, from default under the Act to fraud
Any one of these grounds can support revocation, but only after the promoter gets thirty days of written notice.

On what grounds can registration be revoked?

Section 7(1) allows the Authority to revoke registration on receipt of a complaint, on its own motion, or on the recommendation of the competent authority, after being satisfied of any of four grounds: the promoter makes default in doing anything required by the Act, rules or regulations; violates the terms or conditions of the approval given by the competent authority; is involved in any unfair practice or irregularities; or indulges in any fraudulent practices.

The explanation to Section 7(1)(c) defines unfair practice to include false statements that services are of a particular standard or grade, claims of approvals or affiliations the promoter does not have, false or misleading representations about the services, and permitting advertisements of services that are not intended to be offered.

There are procedural safeguards for the promoter too. Section 7(2) says registration shall not be revoked unless the Authority has given at least thirty days' written notice stating the grounds and has considered any cause shown. Section 7(3) lets the Authority, instead of revoking, keep the registration in force subject to further terms and conditions it imposes in the interest of allottees, and those terms bind the promoter.

Two features of Section 7 matter in practice. First, revocation can begin with a complaint, so buyers are not limited to waiting for the regulator to notice a problem; a well documented complaint is one of the three triggers in Section 7(1). Second, under Section 7(4)(a), the Authority informs regulators in other states and union territories about a revocation, and lists the promoter as a defaulter. If you are considering a builder with projects in several cities, a defaulters listing anywhere is worth knowing about before you book in Bengaluru.

What happens to a project after revocation or lapse?

Section 7(4) lists what the Authority does upon revocation. The table below sets out each step beside what it means for a buyer, with Section 8 alongside.

StepWhat the Act saysWhat it means for a buyer
Website access and defaulters listSection 7(4)(a): debar the promoter from the website for the project, list it as a defaulter and inform other state authoritiesThe revocation becomes visible on the regulator's website
Remaining developmentSection 7(4)(b): facilitate remaining works under Section 8Completion can continue through another route
Project bank accountSection 7(4)(c): direct the bank to freeze the separate project account, then act towards the remaining worksMoney in the project account is protected for completion
Further directionsSection 7(4)(d): issue directions to protect allottees or in the public interestWatch for orders that affect your project
Who completes the workSection 8: competent authority, association of allottees or another manner; association has first right of refusal after revocationBuyers, through the association, may get the first chance to complete

Section 8 also contains a pause. Its first proviso says no direction, decision or order of the Authority under that section shall take effect until the period of appeal under the Act has expired. So a revocation and the arrangements that follow can take time to settle.

Our earlier guide on verifying a Karnataka RERA project registration shows where a project's registration details sit on the regulator's website, which is where these changes will show up.

Comparison of the refund route and the completion route for buyers after a RERA project registration is revoked
Section 19(4) keeps your refund right alive, while Section 8 opens a path for buyers to complete the project.

What rights do individual buyers keep through all this?

Collective steps do not replace your own remedies. Section 19(4) entitles an allottee to claim a refund of the amount paid, with interest at the prescribed rate and compensation, if the promoter fails to comply or is unable to give possession in accordance with the agreement for sale, or due to discontinuance of its business as a developer on account of suspension or revocation of its registration.

That last phrase links revocation directly to your right to a refund. If your project's registration is revoked, you have a statutory basis to claim your money back with interest, alongside or instead of waiting for completion through Section 8. Which path suits you depends on how far the project has progressed and what the association decides, so take advice before choosing.

Delay remedies apply too. Our explainer on delayed possession interest and refund under RERA covers the Section 18 route for projects that miss the agreed date, which can run alongside an extension or a revocation.

How should a Bengaluru buyer read an extension?

Start by finding out which route was used. An extension for force majeure under the main part of Section 6 is different from an extension under the first proviso, which is for reasonable circumstances without default by the promoter and is capped at one year in aggregate. Ask the promoter for the order and the reasons recorded.

Then compare dates. Note the original registration validity, the extended validity and the possession date in your agreement for sale. If the extended date runs past your agreement date, your rights under the agreement and under Section 18 remain relevant, and you should keep a written record of when possession was due.

Finally, watch the project's quarterly updates. An extension paired with steady construction progress is a different situation from an extension paired with stalled work. The second is a reason to talk to other buyers and consider forming or strengthening the association early.

Diagram of the steps after a change in RERA registration status, from noting validity dates to joining the association
Each step builds the record you would need for a refund claim or a decision about completing the project.

What should you do if your project's registration changes?

Treat any change in registration status as a prompt to update your file. Use this checklist:

  1. Note your project's registration number, original validity and current validity.
  2. Ask the promoter for any extension order and the reasons recorded in it.
  3. Compare the extended validity with the possession date in your agreement for sale.
  4. Check the regulator's website for any revocation notice or defaulters listing.
  5. Join or form the association of allottees so buyers can act together.
  6. If registration is revoked, take advice on refund under Section 19(4) or completion under Section 8.
  7. Keep every receipt, demand letter, notice and order in one dated folder.

None of these steps requires waiting for the Authority to act. They put you in a position to use whichever route the Act opens up for your project.

What do Bengaluru buyers ask about RERA extension and revocation?

Can a builder get the RERA registration of a project extended?

Yes, under Section 6 the Authority may extend registration on the promoter's application due to force majeure, meaning war, flood, drought, fire, cyclone, earthquake or other natural calamity. It may also extend in reasonable circumstances without default by the promoter, for up to one year in aggregate, with reasons recorded.

On what grounds can RERA revoke a project's registration?

Section 7(1) allows revocation if the promoter defaults on obligations under the Act, rules or regulations, violates the competent authority's approval conditions, engages in unfair practices or irregularities, or indulges in fraudulent practices. Section 7(2) requires at least thirty days' written notice to the promoter first.

Who completes a project after RERA revokes its registration?

Section 8 lets the Authority, after consulting the appropriate government, arrange for the remaining work through the competent authority, the association of allottees or another manner. After a revocation, the association of allottees has the first right of refusal to carry out the remaining development works.

Can I get a refund if my project's registration is revoked?

Section 19(4) entitles an allottee to a refund with prescribed interest and compensation if the promoter cannot give possession under the agreement, including due to discontinuance of business on account of suspension or revocation of registration. Take advice on refund versus completion through Section 8.

Last updated 2026-10-17. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.