Buying an Affordable PMAY Flat in Bengaluru: How AHP and Housing Vouchers Work for EWS Families
A guide for Bengaluru EWS families to the Affordable Housing in Partnership vertical of PMAY-U 2.0: who is eligible, how whitelisted projects and Redeemable Housing Vouchers work, how public and private AHP projects compare, and the RERA, timeline and lock-in rules that apply.

Picture a domestic worker and a delivery rider in Bengaluru, married, earning a little under Rs 3 lakh a year between them and renting a single room. A neighbour mentions that the government helps families like theirs buy a small flat, and that a private builder's project on the city's edge has "PMAY flats". What does that actually mean, and what should they check before paying anything? Under PMAY-U 2.0, the answer runs through a vertical called Affordable Housing in Partnership.
The short answer. Under the PMAY-U 2.0 scheme guidelines, Affordable Housing in Partnership provides central assistance to EWS beneficiaries, households with annual income up to Rs 3 lakh, for owning a pucca house of 30 to 45 square metres of carpet area built by public or private agencies. In private projects, the assistance comes as a Redeemable Housing Voucher, issued in the beneficiary's name on verified occupancy of the house and redeemed by the developer. Every AHP project must be registered under RERA, and the house carries a five year lock-in from possession. The trade-off: the scheme lowers the cost of a first home for an EWS family, but it limits the choice of project and size, and the house cannot be sold for five years.
What is Affordable Housing in Partnership under PMAY-U 2.0?
A supply side route to small, priced homes. The PMAY-U 2.0 scheme guidelines say the AHP vertical provides central assistance to EWS beneficiaries for owning a pucca house being built in different partnerships by states, union territories, cities and private agencies. Affordable houses of 30 to 45 square metres of carpet area are constructed by public or private agencies and made available for allotment to eligible EWS beneficiaries.
The window is time bound. The guidelines say PMAY-U 2.0 will be implemented for five years from 1 September 2024, so a family hoping to use it should apply while the scheme is running rather than assume it will run indefinitely.
Two models run side by side. In the first, public sector agencies and parastatals build the houses. In the second, private developers build them on their own encumbrance free land, either as a project exclusively for the EWS category or as a mixed project in which at least 25 percent of the houses are for the EWS category and a single project has at least 100 houses.
The state also sets a price ceiling. The guidelines say states and union territories shall decide an upper ceiling on the sale price of EWS houses in rupees per square metre of carpet area, with the objective of making them affordable and accessible to the intended beneficiaries. Ask for that ceiling before you compare prices.
Who can buy an AHP house?
An EWS family with no pucca house anywhere in India. The guidelines say families in the EWS, LIG and MIG categories, living in urban areas and having no pucca house anywhere in the country, are eligible under PMAY-U 2.0, and define EWS households as those with annual income of up to Rs 3 lakh. The AHP vertical itself is described as providing assistance to EWS beneficiaries.
Two further rules apply across the scheme. A beneficiary can take benefit under any one of the scheme's verticals, and a person allotted a house under any central, state or local government housing scheme in the last 20 years, in urban or rural areas, is not eligible. The guidelines also give preference to widows, single women, persons with disabilities, senior citizens and other vulnerable groups.
When allotting houses in AHP projects, the guidelines say families with a person with disability and senior citizens may be allotted a house preferably on the ground floor or lower floors. If that applies to your family, say so in the application.
How does a Redeemable Housing Voucher work?
It is the subsidy, tied to the house. The guidelines say central assistance is provided to beneficiaries through Redeemable Housing Vouchers in the case of private sector projects, and that the state government also provides its financial share towards its part in the housing voucher. The voucher is issued in the name of the beneficiary on verified occupancy of the house and is redeemed by the developer.
The sequence matters for a buyer. Private projects that meet the criteria are approved and whitelisted, then listed on the scheme's unified web portal. Interested beneficiaries apply for a house in a desired whitelisted project by filling the prescribed application form on that portal. The form goes to the urban local body to verify eligibility, and an eligible beneficiary is attached to the preferred project.
The guidelines also allow EWS beneficiaries eligible under AHP to buy a house in an open market project of their choice by applying on the same portal. In that case, the beneficiary still gets the AHP benefit, but the developer is not eligible for the scheme's predefined incentives. We set out the separate interest subsidy route, which covers higher income bands, in our guide to the PMAY-U 2.0 small print for Bengaluru buyers.
How do the public and private AHP routes compare?
The table below sets out five features of the two AHP models as the guidelines describe them:
| Feature | Public sector AHP project | Private sector AHP project |
|---|---|---|
| Who builds | Public sector agencies and parastatals | Private developers on their own encumbrance free land |
| Project mix | At least 25% EWS houses and at least 100 EWS houses for central assistance | Exclusive EWS, or at least 25% EWS in a project of at least 100 houses |
| How assistance reaches you | Released to the implementing agency in instalments | Redeemable Housing Voucher in your name |
| Price | Sale price fixed by the state on a no profit no loss basis | Within the state's ceiling in rupees per square metre |
| RERA | Mandatory registration | Mandatory registration |
For public projects, the guidelines say the remaining cost of the house, after central and state assistance, is borne by the beneficiary, and that states shall facilitate home loans at concessional rates through a special home loan product by banks and housing finance companies for the beneficiary's share.
What protections come with an AHP project?
RERA, a timeline and a fixed developer. The guidelines say all AHP projects should be mandatorily registered under the RERA Act, that a change of project proponent or construction agency is not permissible, and that RERA registration should be in the name of the agency against which the project was sanctioned. So the first check on any project described as a PMAY flat is its RERA registration and the name on it.
The guidelines also say AHP projects shall be completed within 24 to 36 months from receipt of all statutory approvals, with approvals to be obtained within three months of central approval. If a project is not completed within that timeline, later instalments of central assistance need the approval of the central sanctioning committee. Where an agency fails to meet its obligations or complete a project in the agreed timeframe, except in force majeure, earlier releases are to be recovered with interest.
Progress is also tracked in the open. The guidelines say AHP projects are geo-tagged at five construction stages, layout, foundation or plinth, superstructure, finishing and completion with infrastructure, and that the location of the project, the number of towers and the number of flats in a tower are captured through the BHARAT app. If you are waiting on a public or whitelisted project, ask the implementing agency or the urban local body which stage has been recorded.
A booking amount is expected. The guidelines say states and implementing agencies shall charge a minimum booking amount from beneficiaries, to eliminate non-serious applicants, and that it will be adjusted against the beneficiary's share. Keep the receipt with the project and unit details.
What do you commit to when you buy an AHP house?
Holding it, and putting it in the right names. The guidelines set a mandatory lock-in of five years from the date of possession of the house under AHP, during which the beneficiary is not allowed to sell or transfer it. They also say houses acquired with central assistance should be in the name of the female head of the household or jointly with her, except where there is no adult female member, and that an undertaking on income and not owning a pucca house is taken from the beneficiary.
Use this checklist before applying for an AHP house in Bengaluru:
- Confirm your household income is up to Rs 3 lakh and that no family member owns a pucca house anywhere in India.
- Confirm no family member was allotted a government scheme house in the last 20 years.
- Check the project is listed as a whitelisted project on the PMAY-U 2.0 unified web portal, or confirm the open market route applies.
- Check the project's RERA registration and that it is in the name of the sanctioned agency.
- Ask for the state's price ceiling per square metre and compare it with the price quoted.
- Apply on the unified web portal and keep the application reference and booking receipt.
- Plan to live in the house for at least five years from possession, as the lock-in requires.
For the broader rules on booking money in any new project, see our guide to RERA's cap on token payments.
Frequently asked questions
Who is eligible for an AHP house under PMAY-U 2.0?
EWS families, defined in the PMAY-U 2.0 guidelines as households with annual income up to Rs 3 lakh, living in urban areas and with no pucca house anywhere in India. A person allotted a government scheme house in the last 20 years is not eligible, and benefit is available under only one vertical.
What is a Redeemable Housing Voucher?
It is how central assistance reaches EWS buyers in private AHP projects, according to the PMAY-U 2.0 guidelines. The voucher, which includes the state's share, is issued in the beneficiary's name on verified occupancy of the house and is redeemed by the developer of the whitelisted or open market project.
Must an AHP project be registered under RERA?
Yes. The PMAY-U 2.0 guidelines say all AHP projects should be mandatorily registered under the RERA Act, in the name of the agency against which the project was sanctioned, and that a change of project proponent or construction agency is not permissible under the AHP vertical.
Can I sell an AHP house after buying it?
Not for five years. The PMAY-U 2.0 guidelines set a mandatory lock-in of five years from the date of possession of a house under the AHP vertical, during which the beneficiary is not allowed to sell or transfer the house. Plan to live in it for at least that long.
Last updated 2026-10-20. PropNewz Team.