Paragraphs 103 to 107, 119 and 120 of the RBI (Commercial Banks, Credit Facilities) Directions, 2025 tie bank credit to specific projects, bar finance for private builders' land purchases, require clearances before disbursement and mortgagee disclosure in brochures. Questions Bengaluru buyers can ask.
At a Bengaluru launch event, a sales manager mentions, almost in passing, that "a leading bank has funded the project." It is meant to reassure. For a buyer, the more useful response is a question: what did that bank have to check before it lent, and what does it have to keep checking? The Reserve Bank of India's credit rules for commercial banks answer that in a set of paragraphs that most buyers never see, and several of them line up neatly with what a buyer should be asking anyway.
This guide walks through paragraphs 103 to 107, 119 and 120 of the RBI (Commercial Banks, Credit Facilities) Directions, 2025, updated as on October 1, 2026, and turns each into a question you can put to a Bengaluru builder before you book.
The short answer. Under the RBI directions, banks may lend to private builders only through loans linked to each specific project, may not finance their land acquisition, and must ensure the builder has obtained the required government and local authority permissions before disbursing, even if the loan is sanctioned earlier. The financing bank must also make the builder name it as mortgagee in brochures and advertisements, and must withhold funds until that is done. The trade-off: a bank's involvement adds a layer of checking, but those checks protect the bank first, so they complement your own due diligence rather than replace it.
What does "funded by a bank" actually mean under the RBI rules?
Paragraph 103 says a bank may extend credit to private builders on commercial terms by way of loans linked to each specific project. So a bank loan to a builder is tied to a particular project, not a general line of credit for the builder's business. Paragraph 105 leaves the period of credit to the bank's commercial judgement, subject to usual safeguards and the security it considers appropriate.
Paragraph 106 adds that such credit may be extended to builders of repute employing professionally qualified personnel, and that the bank shall ensure, through close monitoring, that no part of the funds is used for speculation in land.
For a buyer, the practical point is that a project loan should be traceable to the project you are buying into. Ask the builder which bank, if any, has financed this specific project, and whether the loan covers your tower or phase.
The directions also give such loans their own category. Paragraph 131 describes Commercial Real Estate, Residential Housing, as a sub-sector carved out because residential housing projects carry lower risk and volatility than commercial real estate as a whole. It covers loans to builders and developers for residential housing projects, which shall generally not include non-residential commercial real estate, though integrated projects with some commercial space, such as a shopping complex or school, may qualify within a limit. Paragraph 105 adds that the bank takes such security as it deems appropriate, and paragraph 119, discussed below, is written for the case where that security includes the project property.
Can a bank finance the builder's land purchase?
No. Paragraph 104 says a bank shall not extend fund based or non-fund based facilities to private builders for acquisition of land, even as part of a housing project. Paragraph 98 sets out the contrast: banks may finance public agencies, not private builders, for acquisition and development of land as part of a complete project with infrastructure such as water, drainage, roads and electricity, by way of term loans, with the project to be completed within three years.
That has a useful implication. Under this rule, a private builder's land purchase should not have been financed by bank credit to the builder, so the presence of a bank lender tells you nothing about how the land was paid for. Title and the source of land are matters you should verify through the documents, not assume from the presence of a lender.
Must the builder have approvals before the bank releases money?
Yes, before disbursement. Paragraph 120 says that while appraising loan proposals involving real estate, the bank shall ensure that borrowers obtain prior permission from government, local governments or other statutory authorities for the project, wherever required. So that the loan process is not held up, proposals may be sanctioned in the normal course, but disbursements shall be made only after the borrower has obtained the requisite clearances from the government authorities.
The distinction between sanction and disbursement matters. A builder can truthfully say a bank has "sanctioned" a project loan before every clearance is in place. What paragraph 120 restricts is the release of money. Ask the builder whether disbursement under the project loan has begun, and ask to see the approvals that the bank would have required for it.
| What the builder says | What the RBI directions require of the bank | Your follow-up question |
|---|---|---|
| "A bank has funded the project" | Loans to private builders are linked to each specific project (para 103) | Which bank, and does the loan cover my tower or phase? |
| "The bank has sanctioned our loan" | Disbursement only after requisite government clearances (para 120) | Has disbursement begun, and which approvals are in place? |
| "Our land is fully paid for" | Banks shall not finance private builders' land acquisition (para 104) | Can I see the title documents for the land? |
| Brochure with no lender named | Financing bank must make the builder disclose the mortgagee in brochures and ads (para 119) | Is the project mortgaged to any bank? |
| "Prices reflect costs" | Bank to take care that prices exclude any speculative element (para 107) | How is the price per square foot built up? |
Will the brochure tell me the project is mortgaged?
It should, if a bank has financed the specific project. Paragraph 119 says the bank shall stipulate that the builder discloses in pamphlets and brochures the names of the banks to which the property is mortgaged, appends the mortgage information when advertising a scheme in newspapers and magazines, and indicates in its brochures that it will provide a No Objection Certificate or permission of the mortgagee bank for sale of flats, if required. The bank shall ensure compliance, and funds shall not be released unless the builder fulfils these requirements.
Our guide to mortgaged projects and the lender's NOC explains how to use this disclosure when you sign the agreement for sale and the sale deed.
What does the RBI say about pricing?
Paragraph 107 is unusual in a banking rule. It says care shall be taken to see that prices charged from the ultimate beneficiaries do not include any speculative element, meaning that prices shall be based only on the documented price of land, the actual cost of construction and a reasonable profit margin. It sits in the part of the directions dealing with bank credit to builders, so it is framed as a matter for the lending bank's care rather than as a price control a buyer can enforce directly.
Still, it gives you a legitimate line of questioning. Asking a builder how the price is built up, in terms of land, construction and margin, is consistent with the logic the RBI applies to the banks that fund builders. You may not get a full cost sheet, but the way a builder answers the question, and whether the answer is consistent with the approvals and land documents you have seen, is itself information worth having before you commit.
How does this fit with my own home loan?
Your own lender has separate duties. Paragraph 116 says disbursal of housing loans to individuals shall be closely linked to the stages of construction, and upfront disbursal shall not be made for under-construction projects. So two streams of bank money may be moving: the builder's project loan, released only after clearances, and your home loan, released stage by stage. Our guide to 80:20 and builder-paid EMI offers explains what happens when those streams are tied together.
What should I ask a Bengaluru builder about project finance?
Put these questions in writing and keep the answers with your booking papers.
- Ask whether this specific project is financed by a bank, and which one.
- Ask whether the project loan covers your tower or phase, and whether disbursement under it has begun.
- Ask to see the government and local authority approvals for the project.
- Check the brochure and advertisements for the name of any mortgagee bank.
- Ask for the land title documents, since a bank cannot have financed the builder's land purchase.
- Ask when the mortgagee bank's NOC or permission for your unit's sale will be issued.
- Ask how the price is built up in terms of land, construction cost and margin.
When you shortlist a project, such as Embassy Lakeshore in Devanahalli or any other on our pages, run the same questions against it; a lender's name in a sales pitch is a starting point for checks, not the end of them.
Frequently asked questions
Can a bank fund a Bengaluru builder's land purchase?
No. Paragraph 104 of the RBI credit facilities directions says a bank shall not extend fund based or non-fund based facilities to private builders for acquisition of land, even as part of a housing project. Bank credit to private builders is linked to each specific project under paragraph 103.
Can a bank release a project loan before approvals are in place?
Paragraph 120 of the RBI directions says the bank shall ensure borrowers obtain prior permission from government, local or statutory authorities where required. Proposals may be sanctioned in the normal course, but disbursements shall be made only after the requisite clearances have been obtained.
Must the builder tell me which bank the project is mortgaged to?
Where a bank finances a specific housing project, paragraph 119 of the RBI directions says it shall stipulate that the builder discloses the mortgagee bank in brochures and adds mortgage information to advertisements, and funds shall not be released unless the builder complies.
Does the RBI say anything about flat prices in bank-funded projects?
Paragraph 107 of the RBI directions says care shall be taken that prices charged from ultimate beneficiaries do not include any speculative element, and are based only on the documented price of land, actual construction cost and a reasonable profit margin, in the context of bank credit to builders.
Last updated 2026-11-19. PropNewz Team.
Contact Us
Stay updated with latest news and new projects!
Tell us what you want, We'll do the rest.
Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.