Stalled Mumbai Project Taken Over? New Builder Pays Delay Interest, Majority Deals Do Not Bind You

On 30 October 2026 the Maharashtra REAT ordered Ricardo Constructions, which took over a stalled Nahur project, to pay interest at SBI MCLR plus 2% from 1 January 2016 to possession, holding that consent letters signed by 78% of buyers do not bind those who refused. What Mumbai buyers should check.

Legal & Documentation
Updated on
November 15, 2026
12 min read

On 2 October 2011, a Mulund couple booked a 625 sq ft flat on the 23rd floor of a tower called Match Point at Nahur, Mumbai. The agreement for sale, signed on 22 November 2011, promised possession in December 2015. They paid Rs 1,05,80,514. Years later, a new company had taken over the project, about 78% of buyers had signed consent letters accepting a compensation arrangement and a new possession date of 31 March 2026, and the couple had refused to sign.

On 30 October 2026, the Maharashtra Real Estate Appellate Tribunal ruled in their favour. It held that the new promoter, having taken on the old promoter's obligations, must pay interest for delay from 1 January 2016 until actual possession, and that consent letters signed by other buyers do not bind those who did not sign. For any Mumbai buyer in a stalled project that changes hands, the ruling answers two practical questions: who pays for the delay, and can the majority sign away your rights?

The short answer. In Appeal No. AT006000000103935 of 2022, pronounced on 30 October 2026, the Maharashtra REAT directed Ricardo Constructions Private Limited, the promoter that took over the project, to pay interest on Rs 1,05,80,514 at SBI's highest MCLR plus 2% per annum from 1 January 2016 until actual possession, within four weeks, plus Rs 25,000 in costs. Interest is calculated excluding stamp duty, registration charges and government taxes. The trade-off for buyers: declining a majority settlement preserved this couple's statutory interest, but it also meant a longer legal route, with the original complaint filed in 2020.

What happened in the Match Point case?

According to the Maharashtra REAT judgment, the buyers booked Flat No. 2306 in Wing B, Match Point, in a Nirmal Lifestyle Limited project in village Nahur, Mumbai Suburban District, for a total consideration of Rs 1,03,14,905. The agreement for sale dated 22 November 2011 fixed possession for December 2015. After a demand letter dated 4 October 2016, the buyers say they realised construction had stalled, and they raised the delay by email on 15 July 2017.

Emails dated 28 June 2018 and 3 August 2018 told the buyers about an arrangement with Shapoorji Pallonji and Company Private Limited for balance construction work. Ricardo Constructions Private Limited then wrote to them on 4 July 2019 about the Match Point building, and the project was later transferred to Ricardo. The buyers filed Complaint No. CC006000000161352 of 2020 before MahaRERA, which on 15 September 2021 disposed of it with directions to comply with an interim order of 4 September 2020. The buyers appealed.

The appeal was heard by a bench of Chairperson Justice S.S. Shinde and Member Dr. Rajagopal Devara, who wrote the judgment. It was reserved on 27 August 2026 and pronounced on 30 October 2026 through video conference. The tribunal framed two points for decision and answered both in the affirmative, partly allowing the appeal. Both Nirmal Lifestyle Limited and Ricardo Constructions were named as respondents, and the operative directions are addressed to Ricardo as the present promoter.

Who pays delay interest when a new builder takes over?

The tribunal held that the new promoter does. It said the transfer of the project to Ricardo "does not take away the rights" of the allottees arising from the failure to hand over possession within the agreed period, and that "having accepted the pending obligations of the erstwhile Promoter under Section 15(2) of the RERA Act 2016", Ricardo is "liable to discharge the statutory obligation to pay interest for delayed possession".

Section 15 of the RERA Act deals with transfer of a project to a third party. Our earlier explainer on Section 15 and the consent needed when a new developer takes over sets out the consent requirement. This judgment adds the consequence on the money side: the new promoter steps into the old promoter's shoes for pending obligations, including interest for a delay that began before it arrived.

Are buyers bound by consent letters signed by the majority?

No, according to this judgment. Ricardo's counsel argued that about 78% of allottees had signed consent letters, that the non-signing buyers were bound by the arrangement accepted by the majority, and that the possession date had been extended to 31 March 2026. The tribunal said it was "unable to accept" that the buyers were "automatically bound by the compensation arrangement merely because a majority of the Allottees have accepted it".

It noted that these buyers had "consciously elected not to sign the Consent Letter" and chose to seek interest under Section 18. It also said that consent given for the transfer of a project "cannot be treated as consent to waive accrued rights arising from delayed possession", and that consent letters executed by other allottees cannot "deprive them of their individual statutory rights". The extension to 31 March 2026 accepted by others "cannot be applied" to these buyers, whose interest runs from the contractual date.

How is the interest calculated in this order?

The operative order sets out four elements. The base is the consideration amount of Rs 1,05,80,514. The rate is the highest Marginal Cost of Lending Rate of SBI plus 2% per annum, as prescribed under Section 18 and the rules. The period runs from 1 January 2016 until the actual date of possession. And the interest is to be calculated on the consideration "excluding stamp duty, registration charges and other applicable taxes paid to government authorities".

Two points in this structure matter for anyone tracking their own claim. First, the start date is the day after the contractual possession month ended, not the date of the complaint or the date of the takeover. Second, the end date is actual possession, so interest keeps running for as long as the flat is not handed over. The new promoter must pay within four weeks of the order and pay Rs 25,000 as costs. The tribunal directed that a copy be sent to MahaRERA and the parties under Section 44(4).

ItemDetail in the judgmentDate or figureSource in orderBuyer lesson
Agreed possessionAgreement for sale dated 22 November 2011December 2015Facts, paragraph 3The contract date is the anchor for interest
Amount paidPayments in response to demandsRs 1,05,80,514Facts and operative orderKeep every receipt; it sets the interest base
Majority settlementAbout 78% signed consent lettersExtension to 31 March 2026Paragraphs 31 and 32Others' consent does not bind you
Interest awardedSBI highest MCLR plus 2% per annumFrom 1 January 2016 to possessionOperative order, item 2Delay interest survives a change of promoter
Exclusions and costsStamp duty, registration and taxes excluded; costs orderedRs 25,000 costs; pay in 4 weeksOperative order, items 3 and 4Interest is on consideration, not on government levies

What should a Mumbai buyer do when a stalled project is taken over?

A takeover can be the best news a stalled project gets. But it usually arrives with paperwork asking buyers to accept a revised date, revised terms or a fixed compensation. This judgment shows that signing or not signing is a real choice with consequences. It also shows that a buyer's own records, from the booking date to each email about the delay, became the evidence the tribunal relied on years later. Before deciding, work through this list.

  1. Find your original agreement for sale and note the contractual possession date; it is the date interest is measured from in this ruling.
  2. Total every payment you have made, with receipts, separately from stamp duty, registration and taxes.
  3. Read any consent letter or letter of understanding line by line and check whether it waives interest or extends your possession date.
  4. Ask the new promoter in writing whether it has accepted the old promoter's pending obligations to allottees.
  5. Check the project's MahaRERA page for the current promoter name and any transfer approval.
  6. Remember that a majority decision by other buyers did not bind the non-signing buyers in this case.
  7. Take legal advice before signing, and keep a copy of whatever you sign or refuse.

Is signing a majority compensation deal always a mistake?

Not necessarily. A negotiated compensation may arrive sooner and with less cost than a complaint and appeal; in this case the complaint was filed in 2020 and the tribunal ruled in October 2026. The booking itself dates to October 2011, so these buyers have been waiting for their home for 15 years. The judgment does not say a settlement is wrong. It says only that a buyer who chooses not to sign keeps the statutory right to interest, and that the consent of others cannot take it away.

The decision on what to sign depends on your contract, your payments and how much delay you face. For the choice between refund and interest under Section 18, see our guide to refund or interest for a delayed Mumbai flat. For advice on your own documents, consult a lawyer who handles RERA matters.

Frequently asked questions

Does a new builder pay delay interest after taking over a stalled Mumbai project?

In a judgment pronounced on 30 October 2026, the Maharashtra REAT held that Ricardo Constructions, having accepted the previous promoter's pending obligations under Section 15(2), must pay interest for delayed possession. It ordered interest at SBI's highest MCLR plus 2% from 1 January 2016 until actual possession, within four weeks.

Am I bound if most buyers sign a compensation consent letter?

Not according to this judgment. The tribunal rejected the argument that buyers who did not sign were bound because about 78% of allottees had signed consent letters. It said consent letters executed by others cannot deprive non-signing buyers of their individual statutory rights, including interest under Section 18.

Does a revised possession date agreed by other buyers apply to me?

In this case, no. The new promoter said the possession date had been extended to 31 March 2026 with majority consent. The tribunal held that this extension cannot be applied to buyers who did not sign, and that their interest must be worked out from their own contractual date and the statute.

Is delay interest calculated on stamp duty and registration charges?

Not in this order. The Maharashtra REAT directed that interest be calculated on the consideration amount excluding stamp duty, registration charges and other applicable taxes paid to government authorities. The base used was Rs 1,05,80,514, the amount the buyers paid in response to the promoter's demands.

Last updated 2026-11-15. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.