Cracks or Seepage in Your New Bengaluru Flat? What RERA's Five-Year Defect Rule Gives You

A crack in a beam or seepage through a wall in the first years after moving in is not just a maintenance problem. The Housing Ministry's RERA FAQ says the promoter is liable for structural and other specified defects for five years from possession, must rectify them within 30 days, and owes compensation if it fails. Here is how a Bengaluru buyer should use that.

Buying Guides
Updated on
November 16, 2026
12 min read

The first monsoon after possession is often the real inspection. A hairline crack in a living room beam widens. A bathroom wall on the floor below shows a damp patch. The builder's site office has moved to the next project, and the association is still finding its feet. For a Bengaluru family eighteen months into a new flat, the question is simple: whose problem is this?

The RERA Act gives a clear starting answer. The Ministry of Housing and Urban Affairs' Frequently Asked Questions on the RERA Act sets out a five-year defect liability for the promoter, a 30-day repair duty and a right to compensation. This guide explains how those pieces fit together and what a buyer should do to use them.

The short answer. MoHUA's FAQ says the promoter is liable for five years from the date of handing over possession for structural defects or any other defect as specified, must rectify such defects within 30 days, and if it fails, aggrieved allottees are entitled to appropriate compensation under the Act. A buyer who acquired the flat by transfer or sale is also an allottee. Complaints go to the Authority or the adjudicating officer under Section 31. The trade-off: the rule is strong on paper, but it rewards buyers who report defects early and in writing, and does little for those who wait until year six.

What does RERA's five-year rule actually say?

The FAQ says the promoter shall be liable for five years from the date of handing over of possession to the allottee towards structural defect or any other defect as specified in the provision. It says it is the duty of the promoter to rectify such defects within 30 days, and that if the promoter fails to do so, the aggrieved allottees shall be entitled to receive appropriate compensation as provided under the Act.

Three things in that sentence matter. The clock starts at possession, not at completion of the project. The duty is to rectify, within a fixed 30 days. And the remedy for failure is compensation, which a buyer has to claim.

When does the five-year clock start?

On the date possession is handed over to you. That makes the handover letter one of the most important documents you will receive. If your possession was delayed, or handed over in stages, ask for a letter that states the date clearly.

Possession itself is a duty for both sides. The FAQ lists, among the allottee's duties under Section 19, the responsibility to take possession. If possession is offered and you delay taking it, the start date can become a point of argument. We set out what to check at handover in our guide to builder obligations after possession.

What counts as a defect, and what does not?

The FAQ names structural defects and any other defect as specified in the provision. It does not list every kind of defect, so the exact scope depends on the wording of the Act and your agreement. In practice, buyers should treat structural cracks, failures of the building's frame and defects in workmanship, quality or services that the agreement promised as items to report.

Wear and tear from use, or damage caused by your own interior work, may well be treated differently. If you have knocked down a wall or changed plumbing, keep records of what was done and by whom, because the builder may point to it.

What the builder promised matters too. The FAQ says that under Section 12 the promoter is responsible for the veracity of all information in the advertisement and prospectus, and is liable to make good any loss caused by false information. If the brochure or specification sheet promised a particular waterproofing, flooring or fitting, and what you received falls short, keep the document; it supports a claim alongside the defect rule.

Do not count on insurance yet. The FAQ says Section 16 requires the promoter to obtain insurance towards title of the land and construction of the project, but that the provision shall only come into effect after, and in the manner, notified by the appropriate Government. Ask whether any such cover exists for your project rather than assuming it does.

Common areas are a shared problem. The FAQ says Section 17 provides for transfer of the undivided proportionate title in the common areas to the association of allottees, and makes the promoter responsible for handing over the necessary documents and plans to the association. Seepage through a terrace or a crack in a shared wall is better reported by the association, with the building plans in hand, so the complaint carries everyone's weight.

Construction standards are watched from another side as well. RBI's Master Circular on Housing Finance says banks should adhere to the National Building Code formulated by the Bureau of Indian Standards, given the importance of building safety especially against natural disasters, and should adopt National Disaster Management Authority guidelines in their loan policies.

What if the builder changes things after you move in?

Changes to the building are covered by a separate rule. The FAQ says that under Section 14, the promoter can modify sanctioned plans or project specifications after approval of the competent authority and disclosure to allottees only for minor additions or alterations. A major modification needs the approval of two-thirds of the allottees, with the promoter's own apartments excluded and one vote per allottee.

So if a defect repair turns into a redesign of common areas, or a builder proposes structural changes to fix a problem, check whether it is a minor alteration or a major one, and whether the required approvals have been taken.

The table below sets the defect rule beside the other protections a buyer is likely to use alongside it.

ProtectionWhat MoHUA's FAQ saysTime limitWho can use itWhat to keep
Defect liabilityPromoter liable for structural and specified defectsFive years from possessionAllottees, including transfereesHandover letter with date
Repair dutyPromoter must rectify the defect30 daysAllottee who reported itDated written complaint and photos
CompensationDue if the promoter fails to rectifyAfter the 30 days lapseAggrieved allotteesRepair quotes and costs incurred
Plan changesMajor changes need two-thirds of allotteesBefore the changeAllottees, one vote eachNotices and approvals
ComplaintAuthority or adjudicating officerAs per state rulesAggrieved personFull correspondence file

Can a resale buyer claim?

Yes, within the window. The FAQ says that under Section 2(d) an allottee includes a person who acquires the apartment or plot through transfer or sale, though not a person to whom it is given on rent. A buyer who purchases a two-year-old flat from its first owner steps into the allottee's position for the Act's purposes.

The practical point is the date. The five years run from the original possession, not from your purchase. Ask the seller for the handover letter and any defect complaints already made, and check how much of the window is left before you price the flat.

How do you make a claim that sticks?

Put everything in writing, with dates. Report each defect to the promoter by email or letter, with photographs, and keep the acknowledgement. Count 30 days from the report. If nothing is done, write again, and record the cost of any urgent repair you have to carry out yourself.

If the promoter still does not act, the FAQ says Section 31 allows an aggrieved person to file a complaint with the Regulatory Authority or the adjudicating officer, and that the adjudicating officer decides disputes under Sections 12, 14, 18 and 19, weighing factors such as the amount of loss and the repetitive nature of the default. The checklist below applies whether you live in a large township or a project such as Shree Vari Aeris in Horamavu.

  1. Keep the handover letter and note the exact date of possession.
  2. Inspect the flat and common areas after the first heavy rains and photograph any defect.
  3. Report each defect to the promoter in writing, with photographs, and ask for acknowledgement.
  4. Count 30 days from your report and diarise a follow-up.
  5. Keep records of any interior work you carried out, with dates and contractors.
  6. Ask the association to log common-area defects collectively in writing.
  7. If repairs are not done, file a complaint with the Authority or adjudicating officer before the five years run out.

If a defect turns out to be part of a wider dispute, our guide to choosing the right forum for a flat dispute explains how RERA, consumer forums and civil courts divide the work.

Is the five-year rule enough protection?

It is a strong floor, not a guarantee of quality. Five years gives many defects time to show themselves, and the 30-day duty gives buyers a clear yardstick. But the rule only works if defects are reported in time, recorded properly and pursued. Treat the first five years as a period of active ownership: inspect, report and keep the file.

Frequently asked questions

How long is a builder liable for defects in a new flat under RERA?

MoHUA's RERA FAQ says the promoter is liable for five years from the date of handing over possession to the allottee for structural defects or any other defect as specified in the provision. The five years run from possession, so the date on your handover letter matters.

How quickly must the builder fix a defect?

According to MoHUA's RERA FAQ, it is the duty of the promoter to rectify such defects within 30 days, and if the promoter fails to do so, the aggrieved allottees are entitled to receive appropriate compensation as provided under the Act. Report each defect in writing so the 30 days can be counted.

Can I claim for defects if I bought the flat from the first owner?

MoHUA's RERA FAQ says that under Section 2(d), an allottee includes a person who acquires the apartment or plot through transfer or sale, but not a tenant. A resale buyer within the five-year window should therefore check the original possession date and keep the earlier owner's defect correspondence.

Where do I complain if the builder does not repair defects?

MoHUA's RERA FAQ says Section 31 provides for filing a complaint by an aggrieved person with the Regulatory Authority or the adjudicating officer, and that the adjudicating officer decides disputes under Sections 12, 14, 18 and 19. The form and fee are set by state rules.

Last updated 2026-11-16. PropNewz Team.

Contact Us

Stay updated with latest news and new projects!

Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.
No pressure, ever

Tell us what you want, We'll do the rest.

Share your budget and where you're looking. An advisor who has actually walked the sites will shortlist a handful of RERA-registered projects and tell you which to skip.

We only contact you about projects you ask about
No spam, no reselling your number, unsubscribe anytime
Independent advice we're paid the same whoever you pick
Thank you! Your submission has been received, We'll get back in touch with you shortly.
Oops! Something went wrong while submitting the form.